This document is a Questions and Answers (Q&A) file for a Computer-Aided Dispatch (CAD) system solicitation for Wright-Patterson Air Force Base. The government is seeking a standalone CAD system with specific technical requirements, including integration with APCO, Westnet Public Safety, and GPS Network Time Protocol. Key details include approximately 100 total users (3-5 administrators, 12 CAD users, 97 mobile users), with about 30 mixed iOS and Android mobile devices. The desired implementation timeline is 6-8 months, and the government prefers an on-premise solution with a possible hybrid-cloud consideration. The system must support fire and EMS personnel, with no current law enforcement requirements. Cybersecurity sustainment services are required, and the vendor must provide software, mapping systems, and necessary training. The proposal submission deadline has been extended to September 3, 2025, with electronic copies requested in two volumes: technical and pricing.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Questions Government Responses

OFFEROR A's Pro Suite is 100% managed by OFFEROR A's DevOps Engineers. To manage the servers, OFFEROR A's DevOps Team uses SSH secure connections for remote access to the servers. Pro Suite managed services requires an “always on” direct connection to the Pro Suite on-premise servers. The reason for that “always on” connection is many of the managed service portions of the server operations are automated. Would like to know if this model of a managed service would be acceptable to Wright Patterson Airforce Base's mode of operations? The "always on" connection is acceptable to us, but if Offeror A requires that, they would need to provide that network connection.

Does Wright Patterson AFB only require electronic copies of our response, just 2 files per page 2 of Attachment 2 “Additional Instructions to Offerors”?

Correct, per page 2 of "Instructions to Offerors" the Government requests electronic copies. Two separate Volumes, one for the Technical package and one for the Price package.

“For Volume II, submit the Pricing Exhibit/Attachment as both a PDF document and as a Microsoft Excel file. Ensure the Microsoft Excel file is not “Read Only” so the CO/buyer can verify the offeror’s calculations.”We cannot locate the Excel file, could this please be provided?

For the Pricing Volume (II), pricing shall be filled out in the Solicitation and can also be provided as an excel spreadsheet or word document to list/explaina costs. If there is an excel spreadsheet provided, please ensure it is not" Read Only". There is no Excel File provided by the Government.

We would like to request a two week extension.

The Government will grant an extension to 3 September 2025.

Please provide details with respect to the cyber security IT requirements including certifications (e.g., FedRamp) as well as any security clearance requirements. No

6 Does the government have a preference between Cloud/Hybrid-Cloud/On-Prem Solutions? We would prefer on-prem, possible hybrid-cloud would be considered

Can the Government please confirm whether the intent is that CAD will reside on the existing USAF network or shall CAD be on a stand-alone network? Stand-alone network

In addition to hardware, will the Government provide Microsoft operating systems and SQL server licenses through a Microsoft volume licensing agreement? Needs to be provided by vendor

9 Can the Government provide the number of concurrent users and/or licenses required for Mobile Laptop clients? Currently no mobile laptops 10 Can the Government provide the number of concurrent users and/or licenses required for iOS/Android devices? Approximately 30 mixed between iOS and Android

Does the Government intend for the vendor to include Cybersecurity sustainment services along with the 5 years of support maintenance and updates of the software. Yes

12 Can the Governemnt clarify if there are necessary clearances / identification requirements? Regarding access to the base, government personnel will sponsor necessary personnel 13 Can the Government confirm if the vendor shall have available staff certified to be compliant with DoDM 8140.03

The System Requirements Section states: "Meet or exceed all industry standard security compliance regulations" Can the government confirm which industry standard security compliance regulation is the minimum requirement?

Does the Government have its own Domain Controller with Active Directory/LDAP that the CAD is expected to use (e.g.

Wright-Patterson Domain)? No. CAD will stand alone as its own domain

Can the Government clarify the anticipated number of personnel for the System Administrator, CAD/Mobile training requirements? 3-5 administrators, 12 CAD, 97 mobile

17 Does the government anticipate PKI requirements for human and machine connections to the CAD system? No. CAD will stand alone as its own domain 18 Is the EMD requirement to integrate with both APCO and ProQA EMD simultaneously? Yes, only integration to APCO 19 Does the Government expect the vendor to offer software and licenses for the EMD solution? No licenses, only integration

Option 1 - Does the Government have a GIS system that the CAD system can integrate with? Option 2 - Does the government expect the vendor to offer software and licenses for the mapping system? Option 1: No, Option 2: Yes, for appropriate mapping systems

21 If Option 2 is selected from Item 13. Will the Government provide the GIS data in an ESRI format? Yes 22 In what capacity is the requirement of Google Maps used? Address/location verification

23 Could the Government extend the response deadline 14 days to Tuesday September 9th?

The Government will grant a proposal submittal extension to 3 September 2025. Official solicitation amendment including the extension is forthcoming.

24 Shall the contractors solution interface and integrate with AFnet or Base LAN? Are automatic operating system patching required? No. CAD will stand alone as its own domain

Shall the contractor support deliverables related to cyber compliance and Risk Management Framework (RMF) process to assist government in achieving Authority to Operate (ATO)? No. CAD will stand alone as its own domain

Shall the contractor support continuous ATO process over the five year POP to support cyber compliance of patching and software updates during the lifecycle of the CAD software? No. CAD will stand alone as its own domain

27 Shall the contractor's solution interface and integrate with Enterprise TMS (Unique Communications CAIRS) ALIson and VoIP discovery? Yes

Shall the contractors solution include IAT Level II technicians, systems engineers, field engineers, and customer service personnel with Motorola Vesta R7 and R8 training and certifications? No

Shall the contractors solution include IAT Level II technicians with Exacom installation, integration experience, testing experience, training and certifications? No

30 Shall the contractors solution include Westnet Public Safety integration capability? Yes

Shall the contractors solution include integration and test with the GPS Network Time Protocoal (NTP) Clock and NENA Standard compliance experience? Yes

32 Shall the contractors solution interface and integrate with Air Force Civil Engineering System - Fire Department (ACES-FD)? No

Shall the contractors training include all interfaces included in the solution and provide additional training at the 30 month timeframe as well as have remote training support from a NOC during the period of performance? Not required, but vendor option

Shall the contractor provide deliverables in accordance with CDRLs to meeting minutes, personnel lists, system design documents, training plan, training documents, key personnel, site concurrence letters or project support agreements, allied support requirements, software updates, etc? Yes

What is the current CAD system in use at Wright-Patterson AFB? When was it installed, and when does that contract end? Is the current CAD system deployed on-premise or cloud-based? Has an Authority to Operate (ATO) been issued for the current system, and will this be required for the new system?

No CAD

Have demonstrations of industry provider solutions been conducted in the past two years? If so, which vendor products were reviewed? Yes, CAD, EMD and station alerting

37 How many total sworn Fire & EMS personnel are in the agency/agencies? Plan for 100 38 How many total sworn law enforcement personnel are in the agency/agencies? Plan for 0 at this time 39 How many workstations are used to make entries into the state CIC/NCIC, if applicable? Not at this time 40 How many users will need to make NCIC basic inquiries (persons, vehicles, guns, boats, articles) in the CAD? Not at this time 41 Does the agency currently access NCIC through the County message switch, or directly to NCIC? Not at this time

The solicitation references “mobile in apparatus” (interpreted as Mobile Data Terminals/MDTs) as well as “Android and iOS” (interpreted as smartphones/tablets). Could the Government please clarify whether the mobile requirement pertains to: a) In-vehicle MDTs, b)Personal mobile devices (Android/iOS) or, c) Both iOS/Andriod devices located in fire/EMS apparatus

Additionally, please confirm whether licensing, pricing, and usage expectations should be scoped by device type or by end user. Device type - total of 3 computers and 30 iOS/Android mobile devices

Will Wright-Patterson AFB also use CAD on mobile phones (iOS/Android)? If so, how many total mobile phones will be used for dispatch across Fire, EMS, and Law Enforcement? Approximately 30 mixed between iOS and Android

45 What is the desired timeline to fully implement and achieve Go-Live with the new integrated CAD system? Desired 6-8 months