QuestionsAnswers - 16 September 2025.pdf
PDF 246 KB Posted
- Solicitation number
- FA860125Q0176
About this file
This document is a Questions and Answers (Q&A) document for Solicitation FA860125Q0176 issued by the Air Force Life Cycle Management Center (AFLCMC) at Wright-Patterson Air Force Base in Ohio, dated 16 September 2025. The Q&A addresses three key inquiries related to a construction/installation project in Building 856, Room W203. The responses clarify that the contractor is responsible for providing and installing power poles, with the government providing a licensed electrician to connect power to the building. A site visit will be conducted after contract award, and the vendor must determine required parts and installation details using existing and new drawings provided by the government.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
DEPARTMENT OF THE AIR FORCE
AIR FORCE LIFE CYCLE MANAGEMENT CENTER (AFLCMC)
WRIGHT-PATTERSON AIR FORCE BASE OHIO
16 September 2025
FROM: AFLCMC/PZIBA
2275 D Street Area B, Building 16, Room 128 Wright-Patterson AFB, OH 45433
SUBJECT: Response to Inquiries regarding Solicitation FA860125Q0176, Building 856 Room W203
QUESTIONS & ANSWERS
QUESTION: Who is purchasing/installing the power poles?
ANSWER: The contractor will be responsible for providing and installing the power poles. The government will provide a licensed electrician to connect the power to the building.
QUESTION: Has a site visit and inventory of parts/product onsite been verified?
ANSWER: Site visit will be provided after award. Inventory should be determined based on the existing drawings provided. All existing products are currently on site in the space; no additional loose parts are available.
QUESTION: Is there a BOM for new products to be received and delivered to site to complete installation?
ANSWER: Vendor is to determine new parts required to complete the installation, based on provided existing drawings and new drawings.
Jessica M. Stamper Contracting Officer