Question_from_Site_Visit_Dec_18.docx

DOCX document 12 KB Posted

Attached to
Custodial Services at Wright Patterson Federal contract opportunity
Solicitation number
FA8601-19-R-0018
Issued by
Department of the Air Force Materiel Command Lifecycle Management Center Wright Patterson Air Force Base

About this file

Here are a list of questions from the site visit

View the file

Other files for this federal contract opportunity

Other files attached to Custodial Services at Wright Patterson, newest first.
File Type Posted
20630.pdf PDF
26933_1_CDC.pdf PDF
26933_School_Age_1.pdf PDF
26933_School_Age_1.pdf PDF
11403.pdf PDF
20234_1.pdf PDF
20234_2.pdf PDF
NASIC_1st_Floor_Facility_Custodial_Plan_2014-06-25-Model.pdf PDF
NASIC_3rd_Floor_Facility_Custodial_Plan_2009-02-18-Model.pdf PDF
NASIC_2nd_Floor_Facility_Custodial_Plan_2014-06-25-Model.pdf PDF
Questions_2.docx DOCX document
Questions.docx DOCX document
InstructionToOfferors_Attachment_2.pdf PDF
Final_PWS_Attachment_3.pdf PDF
1449.pdf PDF
Evaluation_Factor_Attachment_4.pdf PDF
blank_IGE_Attachment_1.xlsx XLSX spreadsheet
wage_determmination_Attachment_5.pdf PDF
Final_PWS_Attachment_1.docx DOCX document
Evaluation_Factor_Attachment_4.doc DOC document
Voluntary_Protection_Progam_(VPP)_PWS_Addendum_Attachment_5.docx DOCX document
i._2_Contractor_Manpower_Reporting_PWS_Attachment_3.docx DOCX document
InstructionToOfferors_Attachment_2.docx DOCX document
Show all 23

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Question from Site Visit Dec 18, 2018 for CDC buildings and NASIC

We were just able to drive around the NASIC building and were unable to go inside due to security reasons.

Building 1403 Area A CDC Will the contractor be responsible for cleaning electronics such as TV monitors?

No the contractor will not be responsible.

Will the contractor be responsible for cleaning the kitchen?

No, the contractor will not be responsible.

Will the contractor be responsible for cleaning the playground equipment?

No, but they will be responsible for emptying trash cans on the playground.

What is the frequency of trash pick-up on the playground?

Daily in the summer and as needed in the winter.

How many rooms in this building?

Please see site map.

Building 630a Area B CDC Will the contractor be responsible for cleaning electronics such as TV monitors?

No the contractor will not be responsible.

Will the contractor be responsible for cleaning the kitchen?

No, the contractor will not be responsible.

Will the contractor be responsible for cleaning the playground equipment?

No, but they will be responsible for emptying trash cans on the playground What is the frequency of trash pick-up on the playground?

Daily in the summer and as needed in the winter.

How many rooms in this building?

Please see site map.

How many janitor closets?

There is one main closet and two smaller closets on the north and south side.

Building 6933-Page Manor How many classrooms on the CDC side of the building?

There are 8 classrooms.

How many classrooms on the opposite side?

There are 9 classrooms.

Is the contractor responsible for the gym floor?

Only to sweep the floor.

Prairie Youth Center How many rooms?

Please see site map.