Attch__18-Drawings_S-105D_and_S-105E.pdf
PDF 11 MB Posted
- Attached to
- Repair-Replace Steam Pipe Stanchions Federal contract opportunity
- Solicitation number
- FA8601-15-R-0030
About this file
Attch 18-Drawings S-105D and S-105E
View the file
Other files for this federal contract opportunity
Show all 50
Repair-Replace Steam Pipe Stanchions has more files on GovTribe.
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
S-105D 5th STREET TUNNEL PHOTOS/DESCRIPTIONS
EXISTING CONDITION REPAIR PROCEDURE EXISTING CONDITION REPAIR PROCEDURE EXISTING CONDITION REPAIR PROCEDURE
EXISTING CONDITION REPAIR PROCEDUREEXISTING CONDITION REPAIR PROCEDUREEXISTING CONDITION REPAIR PROCEDURE
EXISTING CONDITION REPAIR PROCEDURE EXISTING CONDITION REPAIR PROCEDURE
105D-c105D-b105D-a
105D-d 105D-e 105D-f
105D-h105D-g
SUPPORT AT STANCHION 45.
CORROSION THROUGHOUT STEEL
SUPPORT AT STANCHION 60.
CORROSION THROUGHOUT STEEL
AT STANCHION 73.
INTRUSION PRESENT ALONG BASE
IN SUPPORT STANCHION. WATER
CORROSION THROUGHOUT STEEL
STANCHION 77.
BOTTOM HORIZONTAL SUPPORT AT
PIPE ROLLER SUPPORT MISSING AT
STANCHION 78.
AT BOTTOM HORIZONTAL SUPPORT AT
PIPE ROLLER SUPPORT MISSING
PRESENT ALONG WALL AT STANCHION 45.
CORROSION. CRACKING & WATER INTRUSION
CHANNEL INTO CONCRETE WALL HAVE
TOP VERTICAL SUPPORT LEG & CONNECTION
STANCHION 45.
PRESENT ALONG BASE AT
SECTION. WATER INTRUSION
CORROSION & LOSS OF STEEL
BASE OF VERTICAL SUPPORT LEGS
ALONG BASE AT STANCHION 73.
SECTION. WATER INTRUSION PRESENT
HAVE CORROSION & LOSS OF STEEL
& BOTTOM HORIZONTAL SUPPORT
BASE OF VERTICAL SUPPORT LEG
LOCATION AT BOTTOM HORIZONTAL SUPPORT.
PROVIDE NEW PIPE ROLLER FOR PIPE BEARING
CORROSION RESISTANT COATING TO STANCHION.
CLEAN EXISTING STANCHION AND APPLY A
AT HORIZONTAL SUPPORT.
ROLLER FOR PIPE BEARING LOCATION
STANCHION. PROVIDE NEW PIPE
REPAIR METHOD TO EXISTING STEEL
SEE SHEET S-302 FOR APPLICABLE
DETAIL.
SEE 1/S-303 FOR REPLACEMENT OF STANCHION
CLEAN AREA ADJACENT TO EXISTING STANCHION.
WATERPROOFING APPLICATION.
DETAILAND 1/S-301 FOR EXTERNAL
SEE 1/S-303 FOR REPLACEMENT OF STANCHION
CLEAN AREA ADJACENT TO EXISTING STANCHION.
WATERPROOFING APPLICATION.
DETAILAND 1/S-301 FOR EXTERNAL
SEE 1/S-303 FOR REPLACEMENT OF STANCHION
CLEAN AREA ADJACENT TO EXISTING STANCHION.
CORROSION RESISTANT COATING TO STANCHION.
CLEAN EXISTING STANCHION AND APPLY A
WATERPROOFING APPLICATION.
DETAILAND 2/S-301 FOR INTERNAL
SEE 1/S-303 FOR REPLACEMENT OF STANCHION
CLEAN AREA ADJACENT TO EXISTING STANCHION.
WATERPROOFING APPLICATION.
DETAILAND 2/S-301 FOR INTERNAL
SEE 1/S-303 FOR REPLACEMENT OF STANCHION
CLEAN AREA ADJACENT TO EXISTING STANCHION.
OF THE STANCHION.
THE BASE OF THE WALL & AROUND THE BASE
2. CLEAN ALL LOOSE PIECES OF DEBRIS FROM
COATING.
APPLICATION OF A CORROSION RESISTANT
STEEL SHALL BE CLEANED TO ALLOW FOR
STANCHIONS (TO REMAIN) SHALL BE REMOVED.
1. ALL CORROSION PRESENT ON EXISTING STEEL
NOTES:
COORDINATOR ENGINEERING CHIEF
DATE REVISION BYNO. DATE NO. REVISION BY
C I
V
IL
ENGI
N
E E
R
US AF
WRIGHT-PATTERSON AIR FORCE BASE
88TH ABW
OF
DESIGN CHIEF
DATEDRAWNDESIGNED CHECKED
RPR/RPL STEAM STANCHIONS
PROJECT NUMBER ZHTV 090018
SUBMITTAL - 100% GOVT. SUBMITTAL
SPR SPR MSS JUNE 2015
S-105E 5th STREET TUNNEL PHOTOS/DESCRIPTIONS 36
EXISTING CONDITION REPAIR PROCEDURE EXISTING CONDITION REPAIR PROCEDURE EXISTING CONDITION REPAIR PROCEDURE
EXISTING CONDITION REPAIR PROCEDUREEXISTING CONDITION REPAIR PROCEDUREEXISTING CONDITION REPAIR PROCEDURE
EXISTING CONDITION REPAIR PROCEDURE EXISTING CONDITION REPAIR PROCEDURE
105E-c105E-b105E-a
105E-d 105E-e 105E-f
105E-h105E-g
83 & TUNNEL INTERSECTION.
CORNER OF WALL NEAR STANCHION
CORRODED REBAR EXPOSED AT
CONCRETE SPALL & CRACKING w/
AT STANCHION 81.
THROUGHOUT GALVANIZED SUPPORT
CORROSION OF STEEL NOT PRESENT
RESISTANCE.
GALVANIZED STEEL AS SHOWN FOR CORROSION
ALL NEW STANCHION MEMBERS SHALL BE
BASE AT STANCHION 80.
WATER INTRUSION PRESENT ALONG
VERTICAL SUPPORT HAS CORROSION.
CONNECTION ANGLE AT BASE OF
STANCHIONS 44 & 50.
INTRUSION PRESENT ALONG CRACKS BETWEEN
ALONG LENGTH OF CRACK IN CEILING. WATER
EXISTING CONCRETE PATCH WORK PRESENT
REBAR EXPOSED WITHIN CEILING AT CRACK.
CONCRETE SPALL & CRACKING w/ CORRODED
OF CONCRETE TUNNEL DETAIL.
APPLICATION, & 2/S-303 FOR REPLACEMENT
DETAIL, 1/S-301 FOR EXTERNAL WATERPROOFING
SEE 1/S-303 FOR REPLACEMENT OF STANCHION
CLEAN AREA ADJACENT TO EXISTING STANCHION.
TO STANCHION.
AND APPLY A CORROSION RESISTANT COATING
CLEAN EXISTING STANCHION BASE CONNECTION
ALONG BASE AT STANCHION 83.
& PIPE ROLLERS MISSING. WATER INTRUSION PRESENT
SECTION. CENTER & BOTTOM HORIZONTAL SUPPORTS
CHANNELS HAVE CORROSION & LOSS OF STEEL
BASE OF VERTICAL SUPPORT LEGS & CONNECTION
OF CONCRETE TUNNEL DETAIL.
APPLICATION, & 2/S-303 FOR REPLACEMENT
DETAIL, 1/S-301 FOR EXTERNAL WATERPROOFING
SEE 1/S-303 FOR REPLACEMENT OF STANCHION
CLEAN AREA ADJACENT TO EXISTING STANCHION.
& CENTER PIPE AT STANCHION 84.
& ROLLERS MISSING FOR SINGLE PIPE & BOT.
& LOSS OF STEEL SECTION. PIPE SUPPORTS
CONNECTION CHANNELS HAVE CORROSION
BASE OF VERTICAL SUPPORT LEGS &
WATERPROOFING APPLICATION.
AND 2/S-301 FOR INTERNAL
REPLACEMENT OF STANCHION DETAIL
STANCHION. SEE 1/S-303 FOR
CLEAN AREA ADJACENT TO EXISTING
INTRUSION PRESENT ALONG BASE NEAR STANCHION 85.
SINGLE PIPE & BOTTOM & CENTER PIPE. WATER
SECTION. PIPE SUPPORTS & ROLLERS MISSING FOR
CHANNELS HAVE CORROSION & LOSS OF STEEL
BASE OF VERTICAL SUPPORT LEGS & CONNECTION
OF CONCRETE TUNNEL DETAIL.
APPLICATION AND 2/S-303 FOR REPLACEMENT
SEE 1/S-301 FOR EXTERNAL WATERPROOFING
OF CONCRETE TUNNEL DETAIL.
APPLICATION, & 2/S-303 FOR REPLACEMENT
DETAIL, 1/S-301 FOR EXTERNAL WATERPROOFING
SEE 1/S-303 FOR REPLACEMENT OF STANCHION
CLEAN AREA ADJACENT TO EXISTING STANCHION.
& 50.
STEEL SECTION BETWEEN STANCHIONS 44
SUPPORT LEGS HAVE CORROSION & LOSS OF
REBAR EXPOSED IN CEILING. TOP OF VERTICAL
CONCRETE SPALL & CRACKING w/ CORRODED
OF CONCRETE TUNNEL DETAIL.
APPLICATION, & 2/S-303 FOR REPLACEMENT
DETAIL, 1/S-301 FOR EXTERNAL WATERPROOFING
SEE 1/S-303 FOR REPLACEMENT OF STANCHION
CLEAN AREA ADJACENT TO EXISTING STANCHION.
OF THE STANCHION.
THE BASE OF THE WALL & AROUND THE BASE
2. CLEAN ALL LOOSE PIECES OF DEBRIS FROM
COATING.
APPLICATION OF A CORROSION RESISTANT
STEEL SHALL BE CLEANED TO ALLOW FOR
STANCHIONS (TO REMAIN) SHALL BE REMOVED.
1. ALL CORROSION PRESENT ON EXISTING STEEL
NOTES:
COORDINATOR ENGINEERING CHIEF
DATE REVISION BYNO. DATE NO. REVISION BY
C I
V
IL
ENGI
N
E E
R
US AF
WRIGHT-PATTERSON AIR FORCE BASE
88TH ABW
OF
DESIGN CHIEF
DATEDRAWNDESIGNED CHECKED
RPR/RPL STEAM STANCHIONS
PROJECT NUMBER ZHTV 090018
SUBMITTAL - 100% GOVT. SUBMITTAL
SPR SPR MSS JUNE 2015