Drawings.pdf
PDF 312 KB Posted
- Solicitation number
- FA8601-10-R-0028
About this file
Drawings
View the file
Other files
| File | Type | Posted |
|---|---|---|
| VPP Safety Health Plan Requirement.doc | DOC document | |
| 091971 Add 1.doc | DOC document | |
| Amendment 2.doc | DOC document | |
| Question 1.doc | DOC document | |
| Question1 - AFIT SLD.pdf | ||
| Site Visit Sign in Sheet - 18 FEB 2010.pdf | ||
| NOTICE.docx | DOCX document | |
| Wage Decision 2.docx | DOCX document | |
| Amendment 1.doc | DOC document | |
| Amendment 1.doc | DOC document | |
| Wage Decision 2.docx | DOCX document | |
| Wage Decision - 091971R.docx | DOCX document | |
| Solicitation.doc | DOC document | |
| Specifications.pdf |
Show all 14
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
VICINITY PLAN
WPAFB
AREA C
AREA B
WPAFB
F A
IR
F
IE
L
D R
D
ST. RT. 444
ST. R
T. 4
T R
E B
E
IN
R D
I-675
COLONEL GLENN HIGHWAY
DAYTON YELLOW
SPRINGS RD.
N A
T
IO
N A
L R
D
NEW GERMANY TREBEIN RD.
COORDINATOR ENGINEERING CHIEF
DATE REVISION BYNO. DATE NO. REVISION BY
C I
V I
L E N G I N
E E
R
US AF
W PA F B
WRIGHT-PATTERSON AIR FORCE BASE
88TH ABW
OF
DESIGN CHIEF
DATEDRAWNDESIGNED CHECKED
ORTH
WPAFB
AREA A
NOT TO SCALE
PROJECT NUMBER 091971 1 2
GENERAL NOTES
3. ALL OTHER UTILITIES, STRUCTURES AND MISCELLANEOUS ITEMS NOT RELATED
TO THIS PROJECT MUST BE PROTECTED FROM HARM AND DAMAGES. ALL EXISTING
SYSTEMS AND UTILITIES SHALL BE MAINTAINED.
4. IT IS THE RESPONSIBILITY OF THE CONTRACTOR TO VERIFY THE EXTENT OF
THE WORK AT THE SITE. ALL DIMENSIONS ARE APPROXIMATE. THE CONTRACTOR
SHALL FIELD VERIFY ALL DIMENSIONS AND LOCATIONS OF EQUIPMENT.
SHEET SHEET TITLE
T-1
E-1
TITLE SHEET
T-1
ROBERT REYNOLDS
10/18/2009
ROBERT REYNOLDS ROBERT REYNOLDS
1. POWER OUTAGES SHALL BE FROM 1800-0600 DAILY OR FROM 1800 FRIDAY TO 0600
MONDAY UNLESS NOTED OTHERWISE. ALL POWER OUTAGES SHALL BE COORDINATED
AND SCHEDULED WITH THE CONTRACT INSPECTOR THREE (3) WEEKS PRIOR TO THE
ANTICIPATED POWER OUTAGE. POWER OUTAGE TIMES AND DURATION SHALL BE
MINIMIZED TO THE EXTENT PRACTICAL,
SOCCER FIE
LDS
TENTH
SUB.
STATIO
N
ELEVENTH
STREET
STREET
G
S
T R
E E
T
TENTH
STREET
D R
IV
E
36B
24B
17B
20B
71B
70B
33B
34B
68B
78B
PARCOURS
P
ATH
69B
89B
20390
THIRTEENTH STREET
B
SKYLINE DRIVE
S K
Y L
IN
E
STREET
TWELFTH
STREET
Q
T R
E E
T
ELEVENTH
70B
80B 81B
28B 82B
83B
88B
85B
84B
86B 87B
85B
88B
H O
B S
O N
W A
Y
37B
83B
AREA
GATE
22B
TRUCK TRAILER
CONNEX BOX
CONNEX BOX
14B
13B
R O
A D
5B75
L O
O P
27B
10B
22B
7B
26B
21B
27B
12B
12B
553 " D
S
T R
E E
T
D
S
T R
E E
T
TWELFTH STREET
T H
IR
T
E E
N T
H S
T R
E E
T
ELEVENTH STREET
"C" S
TREET
C
S
T R
E E
T
N A
T
IO
N A
L R
O A
D
87B
87B
ORTH
LOCATION PLAN-AREA B
SCALE: 1" = 400’
WORK LOCATION
AFIT FACILITIES
REPLACE ELECTRICAL FEED
TO AFIT FACILITIES
20641, 20642 & 20643
WRIGHT PATTERSON AFB
REPLACE ELECTRICAL FEED
AFIT BLDGS 641, 642 & 643
AFIT FACILITIES REMOVAL AND INSTALLATION PLAN
2. AFIT FACILITIES SHALL REMAIN OCCUPIED AND FUNCTIONAL. THE
CONTRACTOR SHALL PROVIDE TEMPORARY FENCING AS NECESSARY.
P2 0-3 350 MCM &1 #2 12470V
BLDG
BLDG
BLDG
BLDG
BLDG
ELEVENTH STREET
TENTH STREET
H O
B S
O N
W
A Y
COORDINATOR ENGINEERING CHIEF
DATE REVISION BYNO. DATE NO. REVISION BY
C I
V I
L E N G I N
E E
R
US AF
W PA F B
WRIGHT-PATTERSON AIR FORCE BASE
88TH ABW
OF
DESIGN CHIEF
DATEDRAWNDESIGNED CHECKED
ELECTRIC
MANHOLE
E445
ELECTRIC
MANHOLE
E439
ELECTRIC
MANHOLE
E437
ELECTRIC
MANHOLE
E507
REPLACE ELECTRICAL FEED
AFIT BLDGS 641, 642 & 643
INSTALLATION AND REMOVAL PLAN OF2 2
E-1
ROBERT REYNOLDS ROBERT REYNOLDS ROBERT REYNOLDS
10/18/2009
CODED ELECTRICAL NOTES
ORTH
LOCATION PLAN-AREA B
SCALE: 1" = 50’
2. REMOVE EXISTING (3) #2, 15KV CONDUCTORS FROM THE 4-WAY
SF-6 SWITCH TO THE 1500 KVA TRANSFORMER AT FACILITY 20641.
1. REMOVE EXISTING (2) SF-6, 4-WAY SECTIONALIZING SWITCHES.
REMOVE ALL TERMINATIONS, ELBOWS, CONDUCTORS AND CONNECTIONS.
REMOVE ALL MOUNTING LUGS AND ALL MOUNTING HARDWARE.
3. REMOVE EXISTING (3) #2, 15KV CONDUCTORS FROM THE 4-WAY
SF-6 SWITCH TO THE 1000 KVA TRANSFORMER AT FACILITY 20643.
4. REMOVE EXISTING (3) #350 KCMIL & (1) #2 GROUND, 15KV CONDUCTORS
FROM THE 4-WAY SF-6 SWITCH TO THE 1500 KVA INDOOR UNIT SUBSTATION
AT FACILITY 20642.
5. PROVIDE (2) 15KV, 4-WAY, AIR BREAK SECTIONALIZING SWITCHES.
PROVIDE ALL TERMINATIONS, ELBOWS, CONNECTIONS, CONDUCTORS
AND ALL MOUNTING HARDWARE.
6. PROVIDE (3) #2 EPR CONDUCTORS: 15KV, 133 PERCENT INSULATION
LEVEL. ROUTE FROM NEW 4-WAY AIR BREAK SWITCH TO EXISTING
1500 KVA TRANSFORMER AT FACILITY 20641. USE EXISTING DUCTS
UNLESS NOTED OTHERWISE.
7. PROVIDE (3) #2 EPR CONDUCTORS: 15KV, 133 PERCENT INSULATION
LEVEL. ROUTE FROM NEW 4-WAY AIR BREAK SWITCH TO EXISTING
1000 KVA TRANSFORMER AT FACILITY 20643. USE EXISTING DUCTS
UNLESS NOTED OTHERWISE.
8. PROVIDE (4) 5 INCH SCHEDULE 40 PVC DUCTS; DIRECT BURIED
AND CONCRETE ENCASED FROM MANHOLE E437 TO MANHOLE E439.
9. PROVIDE (2) 5 INCH SCHEDULE 40 PVC DUCTS; DIRECT BURIED
AND CONCRETE ENCASED FROM MANHOLE E445 TO MANHOLE E507.
10.PROVIDE (3) #1/0 EPR CONDUCTORS; 15KV, 133 PERCENT
INSULATION LEVEL. ROUTE FROM NEW 4-WAY SWITCH TO
EXISTING 1500 KVA UNIT SUBSTATION IN FACILITY 20642.
UTILIZE EXISTING DUCTS AND NEW DUCTS AS DENOTED.
EXISTING
OUTDOOR
1000 KVA
XFMR
EXISTING
OUTDOOR
1500 KVA
XFMR
4 9 10
EXISTING
INDOOR UNIT
SUBSTATION
1500 KVA
| afit2 |
| 2.pdf |
| afit |
File details come from the government source that posted it. Updated .