Solicitation
View the file
Other files
| File | Type | Posted |
|---|---|---|
| FA8601-08-B-0009-0002.pdf | ||
| Questions and Answers.pdf | ||
| Site Visit Sign in Sheet.pdf | ||
| FA8601-08-B-0009-0001.pdf | ||
| Drawings.pdf | ||
| WD OH080002 4 July 2008.pdf | ||
| Specifications.pdf | ||
| Synopsis.doc | DOC document |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
See Schedule for applicable documents.
Enter prices in Section B.
The DO Rating for this project is DO-C2.
There is a mandatory cost limitation of $750,000 for this project.
Magnitude of Project = Betw een $250,000 and $500,000.
Minimum insurance requirments are in accordance w ith FAR 28.307-2.
Any prospective offeror desiring an explanation or interpretation of the solicitation, draw ings, specifications, ect., must request it in w riting no later than ten (10) days prior to closing date.
Notice to Offerors: Funds are not presently available for this project. No aw ard w ill be made under this solicitation until funds are available.
The Government reserves the right to cancel this solicitation either before or after the closing date.
Bid Opening w ill be held at 1940 Allbrook Drive, Suite 3, Room 111, Wright Patterson AFB, Ohio 45433 on 14 August 2008 at 2:00 PM EST.
X
MATTHEW PASSAGE 937-522-4562
NOTE: In sealed bid solicitations "offer" and "offeror" mean "bid" and "bidder".
10. THE GOVERNMENT REQUIRES PERFORMANCE OF THE WORK DESCRIBED IN THESE DOCUMENTS
NEGOTIATED
15-Jul-2008
(RFP)
(IFB)
CALL:
Replace San Antonio Ave Bridge
B. TELEPHONE NO. (Include area code) (NO COLLECT CALLS)
See Item 7
2. TYPE OF SOLICITATION
SEALED BID
3. DATE ISSUED
9. FOR INFORMATION A. NAME
SOLICITATION
NSN 7540-01-155-3212 1442-101 STANDARD FORM 1442 (REV. 4-85)
Prescribed byGSA FAR (48 CFR) 53.236-1(e)
11. The Contractor shall begin performance w ithin _______10 calendar days and complete it w ithin ________120 calendar days after receiving aw ard, X notice to proceed. This performance period is X mandatory, negotiable. (See _________________________FAR 52.211-10
12 A. THE CONTRACTOR MUST FURNISH ANY REQUIRED PERFORMANCE AND PAYMENT BONDS?
(If "YES," indicate within how many calendar days after award in Item 12B.)
X YES NO
13. ADDITIONAL SOLICITATION REQUIREMENTS:
A. Sealed offers in original and __________1 copies to perform the w ork required are due at the place specified in Item 8 by ___________ local time ______________14 Aug 2008 (date). If this is a sealed bid solicitation, of fers must be publicly opened at that time.
shall be marked to show the offeror's name and address, the solicitation number, and the date and time offers are due.
B. An offer guarantee X is, is not required.
C. All offers are subject to the (1) w ork requirements, and (2) other provisions and clauses incorporated in the solicitation in full text or by reference.
D. Offers providing less than _______150 calendar days for Government acceptance after the date offers are due w ill not be considered and w ill be rejected.
SOLICITATION, OFFER,
AND AWARD
(Construction, Alteration, or Repair)
1. SOLICITATION NO.
IMPORTANT - The "offer" section on the reverse must be fully completed by offeror.
4. CONTRACT NO.
7. ISSUED BY CODE
88 CONS/PKC - CONSTRUCTION FLIGHT
POC: MATTHEW S. PASSAGE
1940 ALLBROOK DR, RM 101
WRIGHT-PATTERSON AFB OH 45433-5309
FA8601
PAGEOF PAGES
1 OF
CODE
(Title, identifying no., date):
12B. CALENDAR DAYS
02:00 PM (hour) Sealed envelopes containing offers
5. REQUISITION/PURCHASE REQUEST NO. 6. PROJECT NO.
060023
8. ADDRESS OFFER TO (If Other Than Item 7)
937-257-2825FAX:TEL: 937-522-4562 TEL: FAX:
FA8601-08-B-0009 35
20B. SIGNATURE
(REV. 4-85)STANDARD FORM 1442 BACK
TO SIGN
NSN 7540-01-155-3212
SOLICITATION, OFFER, AND AWARD (Continued) (Construction, Alteration, or Repair)
CODE FACILITY CODE
17. The offeror agrees to perform the w ork required at the prices specif ied below in strict accordance w ith the terms of this solicitation, if this offer is accepted by the Government in w riting w ithin ________ calendar days after the date offers are due.
the minimum requirements stated in Item 13D. Failure to insert any number means the offeror accepts the minimum in Item 13D.)
AMOUNTS SEE SCHEDULE OF PRICES
18. The offeror agrees to furnish any required performance and payment bonds.
19. ACKNOWLEDGMENT OF AMENDMENTS
(The offeror acknowledges receipt of amendments to the solicitation -- give number and date of each)
AMENDMENT NO.
DATE
20A. NAME AND TITLE OF PERSON AUTHORIZED TO SIGN
OFFER (Type or print)
AWARD (To be completed by Government)
21. ITEMS ACCEPTED:
22. AMOUNT 23. ACCOUNTING AND APPROPRIATION DATA
24. SUBMIT INVOICES TO ADDRESS SHOWN IN ITEM
(4 copies unless otherwise specified)
CODE
(Insert any number equal to or greater than
20C. OFFER DATE
25. OTHER THAN FULL AND OPEN COMPETITION PURSUANT TO
10 U.S.C. 2304(c) 41 U.S.C. 253(c)
CODE27. PAYMENT WILL BE MADEBY:26. ADMINISTERED BY
(Include ZIP Code)14. NAME AND ADDRESS OF OFFEROR 15. TELEPHONE NO. (Include area code)
See Item 14
(Include only if different than Item 14)16. REMITTANCE ADDRESS
30B. SIGNATURE
29. AWARD (Contractor is not required to sign this document.)
document and return _______ copies to issuing office.) Contractor agrees Your of f er on this solicitation, is hereby accepted as to the items listed. This award con-to f urnish and deliv er all items or perf orm all work, requisitions identif ied summates the contract, which consists of (a) the Gov ernment solicitation and on this f orm and any continuation sheets f or the consideration stated in this y our of f er, and (b) this contract award. No f urther contractual document is contract. The rights and obligations of the parties to this contract shall be necessary .
gov erned by (a) this contract award, (b) the solicitation, and (c) the clauses, representations, certif ications, and specif ications or incorporated by ref er-ence in or attached to this contract.
30A. NAME AND TITLE OF CONTRACTOR OR PERSON AUTHORIZED 31A. NAME OF CONTRACTING OFFICER (Type or print)
30C. DATE
(Type or print)
TEL: EMAIL:
31B. UNITED STATES OF AMERICA 31C. AWARD DATE
BY
CONTRACTING OFFICER WILL COMPLETE ITEM 28 OR 29 AS APPLICABLE
(Contractor is required to sign this28. NEGOTIATED AGREEMENT
(M ust be ful ly completed by offeror)OFFER
FA8601-08-B-0009
Section B - Supplies or Services and Prices
ITEM NO SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE AMOUNT
0001 1 Lump Sum
Replace San Antonio Ave Bridge WPAFB
FFP
The contractor shall provide all labor, materials, tools, equipment, transportation and supervision to complete the replacement of the San Antonio Ave bridge, Wright Patterson AFB, Ohio in accordance with the drawing and specifications.
FOB: Destination
SIGNAL CODE: A
NET AMT
Section C - Descriptions and Specifications
PKC C-001
PKC C001 - ENGLISH LANGUAGE REQUIREMENTS
(a) Deliver all documents in the English language.
(b) Provide an English language speaking person during on-site visits, inspections, reviews, audits, and other similar activities.
(End of clause)
Section E - Inspection and Acceptance
INSPECTION AND ACCEPTANCE TERMS
Supplies/services will be inspected/accepted at:
CLIN INSPECT AT INSPECT BY ACCEPT AT ACCEPT BY
0001 Destination Government Destination Government
CLAUSES INCORPORATED BY REFERENCE
52.246-12 Inspection of Construction AUG 1996
PKC E-001
PKC E001 - INSPECTION AND ACCEPTANCE
(IAW FAR 46.401(b) and 46.503)
Inspection and acceptance of the (Services/Supplies) will be performed at Wright-Patterson AFB OH by 88
ABW/CEC.
(End of Clause)
Section F - Deliveries or Performance
DELIVERY INFORMATION
CLIN DELIVERY DATE QUANTITY SHIP TO ADDRESS UIC
0001 120 dys. ADC 1 88 CEG/CERF
NO CONTACT IDENTFIED
1450 LITTRELL ROAD
WRIGHT-PATTERSON AFB OH 45433-5209
FOB: Destination
F4F2AA
CLAUSES INCORPORATED BY REFERENCE
52.242-17 Government Delay Of Work APR 1984 52.247-34 F.O.B. Destination NOV 1991
Section G - Contract Administration Data
CLAUSES INCORPORATED BY FULL TEXT
88 CONS G-001, WIDE AREA WORK FLOW – RECEIPT AND ACCEPTANCE (WAWF-RA)
ELECTRONIC INVOICING AND RECEIVING REPORT INSTRUCTIONS
1. CONTRACTORS SHALL SUBMIT INVOICES THROUGH WAWF-RA FOR PAYMENT.
SUBMISSION OF INVOICES VIA ANY OTHER METHOD SHALL DELAY PAYMENT. HARD COPIES
OF INVOICES ARE NO LONGER ACCEPTABLE METHODS OF SUBMISSION AND MAY BE RETURNED
TO THE CONTRACTOR.
2. The contractor shall be paid after submission of a properly prepared invoice and after final inspection and acceptance by the Government. In accordance with DFARS 252.232-7003, use of electronic payment requests is mandatory. Wide Area Workflow – Receipt and Acceptance (WAWF-RA) is the Department of Defense system preferred choice for submission of electronic payment requests and receipt and acceptance documents. The following information will aid in the submission of an invoice through WAWF-RA.
3. Information regarding WAWF-RA is available on the Internet at https://wawf.eb.mil. Note that the Software Users Manual posted to WAWF-RA is an excellent source for information when completing the invoice submission process. WAWF-RA training is also available at http://www.wawftraining.com.
4. Invoices shall be submitted: Monthly (After Performance)
5. The following codes are required to properly route your invoices and/or receiving reports through WAWF-RA.
Missing elements in the following areas may cause delays in the payment process.
a. CONTRACT NUMBER: TBD
b. CAGE CODE: TBD
c. PAY OFFICE DODAAC: F03000
6. The contractor shall submit invoices using the following format for Payment Type. Be advised that only the selections noted below shall be used in the submittal process. THE CONTRACTOR SHALL STRICTLY
ADHERE TO THE SELECTION NOTED BELOW TO AVOID DELAYS IN THE PAYMENT PROCESS.
SUBMISSION OF INVOICE OTHER THAN THAT SPECIFIED BELOW MAY DELAY PAYMENT
AND/OR CAUSE INVOICE TO BE RETURNED. Invoices must clearly delineate the cost to the respective Contract Line Item Number (CLIN) and sub-CLIN. (See FAR 4, DFARS 204.71 and AFMC FAR Supp 5304.71)
Construction Payment Invoice
Note that if the contractual document requires attachments to be submitted (e.g., a copy of a paid freight bill), this can be accomplished by following instructions under Software User’s Manual on the WAWF-RA site regarding “attachments”.
7. The following additional codes are required to properly route your invoices and/or receiving reports through WAWF-RA. Note that if errors are received in the creation of your document, stop and call the Contracting Officer for verification of code required. Also note that some fields shown may or may not be included depending upon the type of invoice created. An example of the fields required when submitting an invoice are provided:
a. ISSUE BY DODAAC: FA8601
b. ADMIN DODAAC: FA8601 (Note to contractor: This field may also be referred to as ADMIN BPN)
c. INSPECT BY DODAAC or BPN: F4F2AA EXT: . . (Note to contractor: These fields may be blank if not filled out by the contracting office, EXT may be blank even if the Inspect By DODAAC is shown.)
d. MARK FOR CODE: Leave Blank
e. SHIP TO CODE: F4F2AA EXT: . . (Note to contractor: EXT may be blank even if the first code here is shown. Also note this may also be referred to as Service Acceptor Code or Contracting Officer Code. In the future, this code may be referred to as BPN)
f. SHIP FROM CODE: Leave Blank
g. SHIPMENT NUMBER: (Note to contractor: This field is created and provided by the contractor. If no shipment number is completed in the WAWF process, the invoice number will be the default number.)
h. INVOICE NUMBER: (Note to contractor: This is the invoice number created and provided by the contractor)
i. ADDRESSES TAB (Note to contractor: WAWF-RA will pre-populate the address information, ensure it is correct.)
j. DISCOUNT TAB (Note to contractor: This allows for prompt payment discounts)
k. FOB: D (D, S, V) (D denotes destination shipping, S denotes shipment address same as contractor’s address, V denotes shipment from other than contractor’s address.) (Note to contractor: If other than Destination (D), submission of a paid freight bill may be required as an attachment to substantiate shipping charge.)
8. When creating invoices and/or receiving reports, the contractor shall select the “Additional E-mail Notifications” link and enter the e-mail addresses below. The Government will advise the contractor of changes to these e-mail notifications by letter or e-mail vs. contract modification. Upon receipt of the change(s), the contractor shall include the new e-mail notifications when creating invoices and/or receiving reports.
Contractor shall send an email notification to the addressees listed below upon submittal of an invoice through Wide Area Work Flow (WAWF-RA).
a. INSPECTOR: TBD
b. ACCEPTOR: Timoth M Hayes – tim.hayes@wpafb.af.mil
c. CONTRACT ADMINISTRATOR: Matthew S Passage – matthew.passage@wpafb.af.mil
d. CONTRACTING OFFICER: Timothy M Hayes – tim.hayes@wpafb.af.mil
9. Questions concerning payments should be directed to the Defense Finance Accounting Services (DFAS) located in Block 27 of the contract/order. The contract, purchase order, or invoice number is required when inquiring about payment status. Payment information may also be accessed from the DFAS web site at https://myinvoice.csd.disa.mil/index.html.
10. DEFINITIONS. Following is a list of definitions that may be helpful. Additional information can be found at http://farsite.hill.af.mil/ and http://www.dod.mil/dfas/commpay/contractorpayment/.
BPN: Business Partner Number. An integrated electronic infrastructure the Government uses to manage (i.e., collect, validate, access and maintain) the information it needs to transact business with its contractors. The BPN is located at http://www.bpn.gov.
CAGE CODE: Commercial and Government Entity Code. A CAGE Code is a five (5)-position code that identifies companies doing or wishing to do business with the Federal Government. http://www.ccr.gov/ COMMERCIAL ITEM FINANCING IS a form of contract financing resulting from the Federal Acquisition Streamlining Act (FASA) of 1994. Use of this type of invoicing shall be approved by the Contracting officer.
CONTRACTING OFFICER: The person with the authority to enter into, administer, and/or terminate contracts and make related determinations and findings.
CONTRACTOR: Also known as vendor DODAAC: Department of Defense Activity Address Code. A six-position code that uniquely identifies a unit, activity, or organization that has the authority to requisition and/or receive materiel DELIVERY ORDER: An order for supplies placed against an established contract or with Government sources.
F.O.B. DESTINATION: Free on board at destination; i.e., the seller or consignor delivers the goods on seller’s or consignor’s conveyance at destination.
F.O.B. ORIGIN: Free on board at origin; i.e., the seller or consignor places the goods on the conveyance. Unless the contract provides otherwise, the buyer or consignee is responsible for the cost of shipping and risk of loss.
INSPECTION: means examining and testing supplies or services (including, when appropriate, raw materials, components, and intermediate assemblies) to determine whether they conform to contract requirements.
INVOICE: means a contractor's bill or written request for payment under the contract for supplies delivered or services performed (see also “proper invoice”).
MUST: see SHALL.
PERFORMANCE BASED PAYMENTS: A provision for the use of Performance Based Payments (PBPs) as an alternative to progress payments for contract financing. Use of Performance Based Payment method shall be approved by the Contracting Officer PROGRESS PAYMENTS: Progress payments are payments made based on the cost incurred by the contractor as work progresses under the contract. Use of Progress payment method shall be approved by the Contracting Officer.
PROPER INVOICE: An invoice that meets the minimum standards specified in FAR 32.905(b).
RECEIVING REPORT: Written evidence that indicates Government acceptance of supplies delivered or services performed.
SHALL: The imperative.
SHOULD: An expected course of action or policy that is to be followed unless inappropriate for a particular circumstance.
TAXPAYER IDENTIFICATION NUMBER (TIN): The number required by the IRS to be used by the offeror in reporting income tax and other returns.
WINS: Web Invoicing System. https://ecweb.dfas.mil/wins/login.jsp DFAS has implemented a Web Invoicing System (WInS) available through the Internet system in addition to the traditional Value Added Network (VAN) based EDI.
PKC G-002
PKC G002 - CONTRACT HOLIDAYS
(a) The prices/costs in Section B of the contract include holiday observances; accordingly, the Government will not be billed for such holidays, except when services are required by the Government and are actually performed on a holiday. Holidays in addition to those reflected in this contract, which are designated by the Government, will be billable provided the assigned Contractor employee was available for performance and was precluded from such performance.
(b) The following days are contract holidays: New Year’s Day; Martin Luther King’s Birthday; Presidents’ Day; Memorial Day; Independence Day; Labor Day; Columbus Day; Veteran’s Day; Thanksgiving Day;
Christmas Day.
Section H - Special Contract Requirements
CLAUSES INCORPORATED BY FULL TEXT
88 CONS H-002 - Delivery Procedures Commercial Vehicles (JUL 2005)
All vehicles larger than a large pick-up truck are required to be inspected by the Wright-Patterson Air Force Base Commercial Vehicle Delivery Gate (CVDG) prior to entering the installation. Vehicles to be inspected include, but are not limited to, the following:
1. Step van/panel truck
2. Tractor/trailer, box and flat bed containing cargo
3. Tanker trucks
4. Box trucks
5. Tour buses
6. Garbage/recycled waste trucks
7. Concrete trucks/mixers, dump trucks
8. Cranes, recreational vehicles, petroleum tanker
This inspection will be conducted at Gate 16A located off State Route 444.
The following are exemptions to vehicles utilizing the CVDG:
1. If the vehicle has the product inside (concrete and asphalt trucks) and timely delivery is necessary due to product deterioration it does not need to enter the CVDG. To bypass the CVDG, the contractor shall submit a list containing drivers’ names, social security numbers and the state in which the driver's license is held for those drivers who will be entering the base. This shall be accomplished 24 hours prior to requested entry time. If entry is requested on Monday, this list must be submitted by Friday at 1630 hours. All lists shall be submitted to the 88th ABW/CE Directorate contract inspector. The only gates that may be used under this exemption shall be 15A, 26C, 38C, 1B, 26C and gate 1B. If the driver's name is not on the list, he/she will not be allowed access to the installation through these gates and the base will not assume liability for denied access.
2. If a delivery vehicle must exit, and then re-enter the base to complete its route, the vehicle shall be resealed upon exiting the base. After initially passing through the commercial vehicle delivery gate, trucks shall be resealed at Gates 15A, 38C and 22B. The resealing of the trucks will allow them to continue to any other area of the installation (Areas A, B, C, or Kittyhawk) without reprocessing through the CVDG. To receive resealing assistance, the drivers shall physically stop at one of the three authorized gates and request the installation entry controller to reseal their truck and provide the next location of their delivery. The controller will reseal the truck and give the delivery driver a pre-clearance form. The driver shall present the pre-clearance form to the entry controller at the next point of installation entry. This reentry can be through any base gate.
Vehicles may be subject to an inspection at any of installation entry control points during a directed random antiterrorism measure (RAM.) Any commercial vehicle, regardless of size, can be directed to the CVDG at the discretion of the installation entry controller.
CLAUSES INCORPORATED BY FULL TEXT
88 CONS H003 PROCEDURES FOR RETURNING GOVERNMENT-ISSUED IDENTIFICATION (DECEMBER
2006)
The Contractor shall use the following procedures for returning Government-issued identification. Government-issued identification includes, but is not limited to, the common access card (CAC), vehicle stickers, medical center badges, and badges required for entry into buildings or secured areas of the base.
It is the Contractor’s responsibility to ensure all Government-issued identification is safeguarded from theft or misuse as well as returned to the Government upon expiration or termination of the contract or order. Contractors shall follow these instructions at the end of each option year, if applicable, regardless of the decision to exercise the next option.
RETURNING GOVERNMENT-ISSUED IDENTIFICATION
1. The Contractor’s Contract Manager (or Program Manager) shall be responsible for collecting all Government-issued identification.
2. The Contractor shall contact Security Forces at (937) 257-6506 to schedule an appointment for identification return. All identification for this contract or order shall be returned during this appointment with minimal exception.
3. Upon return of all identification Security Forces will provide the Contractor with a letter verifying receipt of identification. This letter will identify any badges that were not returned.
4. Medical center badges shall be returned to the medical center staff. The Contractor shall obtain a letter of receipt from the medical center staff.
5. Final invoices will not be paid until letters of receipt are received by the acceptor identified in this contract or order.
6. The Government may withhold monetary consideration from the final invoice for identification(s) that are not returned.
7. The Government reserves the right to consider the Contractor’s history of returning Government-issued identification when evaluating past performance and responsibility for future awards. Failure to return Government-issued identification may result in ineligibility for future contract awards if the contractor is barred from the base.
(End)
PKC H-008
PKC H-008 - GOVERNMENT DOWN TIME FOR VARIOUS AUTHORITIES INCLUDING THE PRESIDENT, SECRETARY OF DEFENSE, SECRETARY OF THE AIR FORCE, AFMC/CC, ASC/CC, 88 ABW/CC, AND
PROGRAM MANAGERS
(a) Base Closures Due to Emergencies. From time to time, the Center or Base Commander or other authority may decide to close all or part of the base in response to an unforeseen emergency or similar occurrence. Sample emergencies include, but are not limited to, adverse weather such as snow or flood, an act of God such as a tornado or earthquake, acts of war or terrorism, computer failures, or a base disaster such as a natural gas leak or fire.
Contractor personnel are “non-essential” for purposes of any instructions regarding the emergency.
(1) Contractor shall be officially dismissed upon notification of a base closure in accordance with paragraph b. Contractor shall promptly secure all government furnished property appropriately and evacuate in an expedient but safe manner.
(2) With regard to work under the contract, the Government shall retain the following options:
(i) Government may grant a time extension in each task order delayed by the closure equal to the time of the closure, subject to the availability of funds.
(ii) Government may forego the work. The Contractor will not be paid for work not performed.
(iii) Government may reschedule the work on any day satisfactory to both parties.
(iv) The Government may, in its discretion, permit the Contractor to perform at an off-site location during the period of base closure if meaningful work can be accomplished. Contractor shall certify to the Government by letter within 5 business days of returning to work, the nature and scope of the work completed off-site. Contractor shall be permitted to bill the Government at the labor rates identified in the contract.
(v) In rare instances, Government may request that the Contractor continue on-site performance during the base closure period. Such a request shall be subject to agreement by Contractor.
(b) Base Closure Notification Procedures.
(1) After an official decision to close Wright-Patterson AFB has been made by the Base Commander, the following radio and television stations shall be notified of the closure:
Television:
WHIO 7
WDTN 2
WTJC 26
WKEF 22
Radio:
WHIO AM 1290 WBVE FM 96-5
WONE AM 98 WTUE FM 104.7
WBLY AM 1600 WBZI FM 95.3
WIZE AM 1340 WYSO FM 91.3
WLW AM 700 WYMJ FM 103.9
WDAO AM 1210 WFCJ FM 93.7
WING AM 1410 WHKO FM 99.1
WAZU FM 102.9 WVUD FM 99.9
(2) The Contractor is directed to listen or watch one of the radio or television stations listed in paragraph b.1 for a base closure. Contractor should follow instructions intended for non-essential personnel.
(3) The Contractor will not receive any other form of notification of a base closure from the Government.
The Contractor is responsible for notification of his or her employees.
(4) If the decision to close all or part of the base is made during the duty day, and the Base Commander’s decision is transmitted through official notification channels, the Contractor shall follow the instructions as given.
Contractor personnel shall notify their task monitor and act in accordance with the task monitor’s instruction.
(c) Base Closure Due to Non-Emergencies. The Center or Base Commander or other authority may elect to close all or part of the base for non-emergency reasons such as time-off award, base open house, etc. In the event of a non-emergency base closure, the Contract Task Monitor and the Contractor shall jointly choose a course of action within the following options:
(1) If there is a need for the service during the base closure and a Government employee will be present, Contractor shall bill the Government at the labor rates identified in the contract.
(2) If there is a need for work during the base closure but either a Government employee will not be present or access will not be available, the Contractor may work off-site provided meaningful work may be accomplished. Contractor shall certify to the Government by letter within 5 business days or returning on-site the nature and scope of the work completed off-site. Contractor shall bill the Government at the labor rates specified in the contract.
(3) If there is no need for the service during the scheduled base closure, contractor shall not work on or off-site.
Government may grant a time extension in each task order delayed by the closure equal to the amount of time of the closure, subject to the availability of funds. The Government will not be liable for time not worked.
(End of Clause)
PKC H-018
PKC H-018 - EMS TRAINING
Initial Environmental Management System awareness-level training is required for all personnel working on base at WPAFB.
(a) The installation office responsible for providing the EMS training is 88 ABW/CEVY
(b) The training requires less than thirty minutes
(c) The EMS Awareness-level training shall be accomplished within thirty days of contract (or modification) award. New contract employees shall be trained within thirty days of starting work on the installation.
(d) The EMS Awareness-level training is available via the 88 ABW/CEVY website (https://wrigem.wpafb.af.mil/viewchild.cfm?id=228), which provides materials that meet the training requirement.
(e) Upon completion of the training, the contractor shall provide the AF program manager (PM) a list of the contractor employees' names and the date the training was completed.
Section I - Contract Clauses
CLAUSES INCORPORATED BY REFERENCE
52.202-1 Definitions JUL 2004 52.203-3 Gratuities APR 1984 52.203-5 Covenant Against Contingent Fees APR 1984 52.203-6 Restrictions On Subcontractor Sales To The Government SEP 2006 52.203-7 Anti-Kickback Procedures JUL 1995 52.203-8 Cancellation, Rescission, and Recovery of Funds for Illegal or Improper Activity
JAN 1997
52.203-10 Price Or Fee Adjustment For Illegal Or Improper Activity JAN 1997 52.203-12 Limitation On Payments To Influence Certain Federal
Transactions
SEP 2007
52.204-4 Printed or Copied Double-Sided on Recycled Paper AUG 2000 52.204-7 Central Contractor Registration APR 2008 52.204-9 Personal Identity Verification of Contractor Personnel SEP 2007 52.209-6 Protecting the Government's Interest When Subcontracting
With Contractors Debarred, Suspended, or Proposed for Debarment
SEP 2006
52.214-29 Order Of Precedence--Sealed Bidding JAN 1986 52.219-4 Notice of Price Evaluation Preference for HUBZone Small
Business Concerns
JUL 2005
52.219-8 Utilization of Small Business Concerns MAY 2004 52.222-1 Notice To The Government Of Labor Disputes FEB 1997 52.222-3 Convict Labor JUN 2003 52.222-4 Contract Work Hours and Safety Standards Act - Overtime
Compensation
JUL 2005
52.222-6 Davis Bacon Act JUL 2005 52.222-7 Withholding of Funds FEB 1988 52.222-8 Payrolls and Basic Records FEB 1988 52.222-9 Apprentices and Trainees JUL 2005 52.222-10 Compliance with Copeland Act Requirements FEB 1988 52.222-11 Subcontracts (Labor Standards) JUL 2005 52.222-12 Contract Termination-Debarment FEB 1988 52.222-13 Compliance with Davis-Bacon and Related Act Regulations. FEB 1988 52.222-14 Disputes Concerning Labor Standards FEB 1988 52.222-15 Certification of Eligibility FEB 1988 52.222-21 Prohibition Of Segregated Facilities FEB 1999 52.222-26 Equal Opportunity MAR 2007 52.222-27 Affirmative Action Compliance Requirements for
Construction
FEB 1999
52.222-35 Equal Opportunity For Special Disabled Veterans, Veterans of the Vietnam Era, and Other Eligible Veterans
SEP 2006
52.222-36 Affirmative Action For Workers With Disabilities JUN 1998 52.222-37 Employment Reports On Special Disabled Veterans, Veterans Of The Vietnam Era, and Other Eligible Veterans
SEP 2006
52.222-39 Notification of Employee Rights Concerning Payment of Union Dues or Fees
DEC 2004
52.222-50 Combating Trafficking in Persons AUG 2007 52.223-5 Pollution Prevention and Right-to-Know Information AUG 2003
52.223-6 Drug-Free Workplace MAY 2001 52.223-12 Refrigeration Equipment and Air Conditioners MAY 1995 52.223-14 Toxic Chemical Release Reporting AUG 2003 52.225-13 Restrictions on Certain Foreign Purchases FEB 2006 52.227-1 Authorization and Consent DEC 2007 52.227-2 Notice And Assistance Regarding Patent And Copyright
Infringement
DEC 2007
52.227-4 Patent Indemnity-Construction Contracts DEC 2007 52.228-2 Additional Bond Security OCT 1997 52.228-5 Insurance - Work On A Government Installation JAN 1997 52.228-11 Pledges Of Assets FEB 1992 52.228-12 Prospective Subcontractor Requests for Bonds OCT 1995 52.228-14 Irrevocable Letter of Credit DEC 1999 52.228-15 Performance and Payment Bonds--Construction NOV 2006 52.229-3 Federal, State And Local Taxes APR 2003 52.232-5 Payments under Fixed-Price Construction Contracts SEP 2002 52.232-17 Interest JUN 1996 52.232-23 Assignment Of Claims JAN 1986 52.232-27 Prompt Payment for Construction Contracts SEP 2005 52.232-33 Payment by Electronic Funds Transfer--Central Contractor
Registration
OCT 2003
52.233-1 Disputes JUL 2002 52.233-3 Protest After Award AUG 1996 52.233-4 Applicable Law for Breach of Contract Claim OCT 2004 52.236-2 Differing Site Conditions APR 1984 52.236-3 Site Investigation and Conditions Affecting the Work APR 1984 52.236-4 Physical Data APR 1984 52.236-5 Material and Workmanship APR 1984 52.236-6 Superintendence by the Contractor APR 1984 52.236-7 Permits and Responsibilities NOV 1991 52.236-8 Other Contracts APR 1984 52.236-9 Protection of Existing Vegetation, Structures, Equipment, Utilities, and Improvements
APR 1984
52.236-10 Operations and Storage Areas APR 1984 52.236-11 Use and Possession Prior to Completion APR 1984 52.236-12 Cleaning Up APR 1984 52.236-13 Accident Prevention NOV 1991 52.236-15 Schedules for Construction Contracts APR 1984 52.236-16 Quantity Surveys APR 1984 52.236-17 Layout of Work APR 1984 52.236-21 Specifications and Drawings for Construction FEB 1997 52.236-26 Preconstruction Conference FEB 1995 52.242-13 Bankruptcy JUL 1995 52.242-14 Suspension of Work APR 1984 52.243-4 Changes JUN 2007 52.243-5 Changes and Changed Conditions APR 1984 52.244-6 Subcontracts for Commercial Items MAR 2007 52.246-21 Warranty of Construction MAR 1994 52.248-3 Value Engineering-Construction SEP 2006 52.249-2 Termination For Convenience Of The Government (Fixed-
Price)
MAY 2004
52.249-10 Default (Fixed-Price Construction) APR 1984 52.253-1 Computer Generated Forms JAN 1991
252.203-7001 Prohibition On Persons Convicted of Fraud or Other Defense-Contract-Related Felonies
DEC 2004
252.204-7003 Control Of Government Personnel Work Product APR 1992 252.204-7004 Alt A Central Contractor Registration (52.204-7) Alternate A SEP 2007 252.209-7004 Subcontracting With Firms That Are Owned or Controlled
By The Government of a Terrorist Country
DEC 2006
252.223-7004 Drug Free Work Force SEP 1988 252.223-7006 Prohibition On Storage And Disposal Of Toxic And
Hazardous Materials
APR 1993
252.225-7012 Preference For Certain Domestic Commodities MAR 2008 252.232-7003 Electronic Submission of Payment Requests and Receiving
Reports
MAR 2008
252.232-7010 Levies on Contract Payments DEC 2006 252.236-7000 Modification Proposals-Price Breakdown DEC 1991 252.243-7001 Pricing Of Contract Modifications DEC 1991 252.243-7002 Requests for Equitable Adjustment MAR 1998
CLAUSES INCORPORATED BY FULL TEXT
52.211-10 COMMENCEMENT, PROSECUTION, AND COMPLETION OF WORK (APR 1984)
The Contractor shall be required to (a) commence work under this contract within 10 calendar days after the date the Contractor receives the notice to proceed, (b) prosecute the work diligently, and (c) complete the entire work ready for use not later than 120 days after the notice to proceed. The time stated for completion shall include final cleanup of the premises.
(End of clause)
CLAUSES INCORPORATED BY FULL TEXT
52.211-12 LIQUIDATED DAMAGES--CONSTRUCTION (SEP 2000)
(a) If the Contractor fails to complete the work within the time specified in the contract, the Contractor shall pay liquidated damages to the Government in the amount of $152.36 for each calendar day of delay until the work is completed or accepted.
(b) If the Government terminates the Contractor's right to proceed, liquidated damages will continue to accrue until the work is completed. These liquidated damages are in addition to excess costs of repurchase under the Termination clause.
CLAUSES INCORPORATED BY FULL TEXT
52.211-15 DEFENSE PRIORITY AND ALLOCATION REQUIREMENTS (APR 2008)
This is a rated order certified for national defense, emergency preparedness, and energy program use, and the Contractor shall follow all the requirements of the Defense Priorities and Allocations System regulation (15 CFR 700).
(End of clause)
CLAUSES INCORPORATED BY FULL TEXT
52.219-28 POST-AWARD SMALL BUSINESS PROGRAM REREPRESENTATION (JUNE 2007)
(a) Definitions. As used in this clause--
Long-term contract means a contract of more than five years in duration, including options. However, the term does not include contracts that exceed five years in duration because the period of performance has been extended for a cumulative period not to exceed six months under the clause at 52.217-8, Option to Extend Services, or other appropriate authority.
Small business concern means a concern, including its affiliates, that is independently owned and operated, not dominant in the field of operation in which it is bidding on Government contracts, and qualified as a small business under the criteria in 13 CFR part 121 and the size standard in paragraph (c) of this clause.
(b) If the Contractor represented that it was a small business concern prior to award of this contract, the Contractor shall rerepresent its size status according to paragraph (e) of this clause or, if applicable, paragraph (g) of this clause, upon the occurrence of any of the following:
(1) Within 30 days after execution of a novation agreement or within 30 days after modification of the contract to include this clause, if the novation agreement was executed prior to inclusion of this clause in the contract.
(2) Within 30 days after a merger or acquisition that does not require a novation or within 30 days after modification of the contract to include this clause, if the merger or acquisition occurred prior to inclusion of this clause in the contract.
(3) For long-term contracts--
(i) Within 60 to 120 days prior to the end of the fifth year of the contract; and
(ii) Within 60 to 120 days prior to the exercise date specified in the contract for any option thereafter.
(c) The Contractor shall rerepresent its size status in accordance with the size standard in effect at the time of this rerepresentation that corresponds to the North American Industry Classification System (NAICS) code assigned to this contract. The small business size standard corresponding to this NAICS code can be found at http://www.sba.gov/services/contractingopportunities/sizestandardstopics/.
(d) The small business size standard for a Contractor providing a product which it does not manufacture itself, for a contract other than a construction or service contract, is 500 employees.
(e) Except as provided in paragraph (g) of this clause, the Contractor shall make the rerepresentation required by paragraph (b) of this clause by validating or updating all its representations in the Online Representations and Certifications Application and its data in the Central Contractor Registration, as necessary, to ensure they reflect current status. The Contractor shall notify the contracting office by e-mail, or otherwise in writing, that the data have been validated or updated, and provide the date of the validation or update.
(f) If the Contractor represented that it was other than a small business concern prior to award of this contract, the Contractor may, but is not required to, take the actions required by paragraphs (e) or (g) of this clause.
(g) If the Contractor does not have representations and certifications in ORCA, or does not have a representation in ORCA for the NAICS code applicable to this contract, the Contractor is required to complete the following rerepresentation and submit it to the contracting office, along with the contract number and the date on which the rerepresentation was completed:
The Contractor represents that it ( ) is, ( ) is not a small business concern under NAICS Code 237310- assigned to contract number TBD.
(Contractor to sign and date and insert authorized signer's name and title).
(End of clause)
52.225-9 BUY AMERICAN ACT—CONSTRUCTION MATERIALS (JAN 2005)
(a) Definitions. As used in this clause--
Component means an article, material, or supply incorporated directly into a construction material.
Construction material means an article, material, or supply brought to the construction site by the Contractor or a subcontractor for incorporation into the building or work. The term also includes an item brought to the site preassembled from articles, materials, or supplies. However, emergency life safety systems, such as emergency lighting, fire alarm, and audio evacuation systems, that are discrete systems incorporated into a public building or work and that are produced as complete systems, are evaluated as a single and distinct construction material regardless of when or how the individual parts or components of those systems are delivered to the construction site. Materials purchased directly by the Government are supplies, not construction material.
Cost of components means--
(1) For components purchased by the Contractor, the acquisition cost, including transportation costs to the place of incorporation into the construction material (whether or not such costs are paid to a domestic firm), and any applicable duty (whether or not a duty-free entry certificate is issued); or
(2) For components manufactured by the Contractor, all costs associated with the manufacture of the component, including transportation costs as described in paragraph (1) of this definition, plus allocable overhead costs, but excluding profit. Cost of components does not include any costs associated with the manufacture of the construction material.
Domestic construction material means--
(1) An unmanufactured construction material mined or produced in the United States; or
(2) A construction material manufactured in the United States, if the cost of its components mined, produced, or manufactured in the United States exceeds 50 percent of the cost of all its components. Components of foreign origin of the same class or kind for which nonavailability determinations have been made are treated as domestic.
Foreign construction material means a construction material other than a domestic construction material.
United States means the 50 States, the District of Columbia, and outlying areas.
(b) Domestic preference. (1) This clause implements the Buy American Act (41 U.S.C. 10a-10d) by providing a preference for domestic construction material. The Contractor shall use only domestic construction material in performing this contract, except as provided in paragraphs (b)(2) and (b)(3) of this clause.
(2) This requirement does not apply to the construction material or components listed by the Government as follows: NONE
(3) The Contracting Officer may add other foreign construction material to the list in paragraph (b)(2) of this clause if the Government determines that
(i) The cost of domestic construction material would be unreasonable. The cost of a particular domestic construction material subject to the requirements of the Buy American Act is unreasonable when the cost of such material exceeds the cost of foreign material by more than 6 percent;
(ii) The application of the restriction of the Buy American Act to a particular construction material would be impracticable or inconsistent with the public interest; or
(iii) The construction material is not mined, produced, or manufactured in the United States in sufficient and reasonably available commercial quantities of a satisfactory quality.
(c) Request for determination of inapplicability of the Buy American Act. (1)(i) Any Contractor request to use foreign construction material in accordance with paragraph (b)(3) of this clause shall include adequate information for Government evaluation of the request, including--
(A) A description of the foreign and domestic construction materials;
(B) Unit of measure;
(C) Quantity;
(D) Price;
(E) Time of delivery or availability;
(F) Location of the construction project;
(G) Name and address of the proposed supplier; and
(H) A detailed justification of the reason for use of foreign construction materials cited in accordance with paragraph (b)(3) of this clause.
(ii) A request based on unreasonable cost shall include a reasonable survey of the market and a completed price comparison table in the format in paragraph (d) of this clause.
(iii) The price of construction material shall include all delivery costs to the construction site and any applicable duty (whether or not a duty-free certificate may be issued).
(iv) Any Contractor request for a determination submitted after contract award shall explain why the Contractor could not reasonably foresee the need for such determination and could not have requested the determination before contract award. If the Contractor does not submit a satisfactory explanation, the Contracting Officer need not make a determination.
(2) If the Government determines after contract award that an exception to the Buy American Act applies and the Contracting Officer and the Contractor negotiate adequate consideration, the Contracting Officer will modify the contract to allow use of the foreign construction material. However, when the basis for the exception is the unreasonable price of a domestic construction material, adequate consideration is not less than the differential established in paragraph (b)(3)(i) of this clause.
(3) Unless the Government determines that an exception to the Buy American Act applies, use of foreign construction material is noncompliant with the Buy American Act.
(d) Data. To permit evaluation of requests under paragraph (c) of this clause based on unreasonable cost, the Contractor shall include the following information and any applicable supporting data based on the survey of suppliers:
Foreign and Domestic Construction Materials Price Comparison Construction material description Unit of measure Quantity Price (dollars) \1\
Item 1
Foreign construction material Domestic construction material
Item 2 Foreign construction material Domestic construction material
Include all delivery costs to the construction site and any applicable duty (whether or not a duty-free entry certificate is issued).
List name, address, telephone number, and contact for suppliers surveyed. Attach copy of response; if oral, attach summary.
Include other applicable supporting information.
(End of clause)
52.228-1 BID GUARANTEE (SEP 1996)
(a) Failure to furnish a bid guarantee in the proper form and amount, by the time set for opening of bids, may be cause for rejection of the bid.
(b) The bidder shall furnish a bid guarantee in the form of a firm commitment, e.g., bid bond supported by good and sufficient surety or sureties acceptable to the Government, postal money order, certified check, cashier's check, irrevocable letter of credit, or, under Treasury Department regulations, certain bonds or notes of the United States.
The Contracting Officer will return bid guarantees, other than bid bonds, (1) to unsuccessful bidders as soon as practicable after the opening of bids, and (2) to the successful bidder upon execution of contractual documents and bonds (including any necessary coinsurance or reinsurance agreements), as required by the bid as accepted.-
(c) The amount of the bid guarantee shall be 20 percent of the bid price or $3,000,000 whichever is less.-
(d) If the successful bidder, upon acceptance of its bid by the Government within the period specified for acceptance, fails to execute all contractual documents or furnish executed bond(s) within 10 days after receipt of the forms by the bidder, the Contracting Officer may terminate the contract for default.-
(e) In the event the contract is terminated for default, the bidder is liable for any cost of acquiring the work that exceeds the amount of its bid, and the bid guarantee is available to offset the difference.
(End of clause)
CLAUSES INCORPORATED BY FULL TEXT
52.236-1 PERFORMANCE OF WORK BY THE CONTRACTOR (APR 1984)
The Contractor shall perform on the site, and with its own organization, work equivalent to at least 15 percent of the total amount of work to be performed under the contract. This percentage may be reduced by a supplemental agreement to this contract if, during performing the work, the Contractor requests a reduction and the Contracting Officer determines that the reduction would be to the advantage of the Government.
(End of clause)
CLAUSES INCORPORATED BY FULL TEXT
52.252-2 CLAUSES INCORPORATED BY REFERENCE (FEB 1998)
This contract incorporates one or more clauses by reference, with the same force and effect as if they were given in full text. Upon request, the Contracting Officer will make their full text available. Also, the full text of a clause may be accessed electronically at this/these address(es):
http://farsite.hill.af.mil
(End of clause)
CLAUSES INCORPORATED BY FULL TEXT
52.252-6 AUTHORIZED DEVIATIONS IN CLAUSES (APR 1984)
(a) The use in this solicitation or contract of any Federal Acquisition Regulation (48 CFR Chapter 1) clause with an authorized deviation is indicated by the addition of "(DEVIATION)" after the date of the clause.
(b) The use in this solicitation or contract of any Defense Federal Acquisition Regulation Supplement (48 CFR Chapter 2) clause with an authorized deviation is indicated by the addition of "(DEVIATION)" after the name of the regulation.
(End of clause)
252.236-7001 CONTRACT DRAWINGS AND SPECIFICATIONS (AUG 2000)
(a) The Government will provide to the Contractor, without charge, one set of contract drawings and specifications, except publications incorporated into the technical provisions by reference, in electronic or paper media as chosen by the Contracting Officer.
(b) The Contractor shall--
(1) Check all drawings furnished immediately upon receipt;
(2) Compare all drawings and verify the figures before laying out the work;
(3) Promptly notify the Contracting Officer of any discrepancies;
(4) Be responsible for any errors that might have been avoided by complying with this paragraph (b); and
(5) Reproduce and print contract drawings and specifications as needed.
(c) In general--
(1) Large-scale drawings shall govern small-scale drawings; and
(2) The Contractor shall follow figures marked on drawings in preference to scale measurements.
(d) Omissions from the drawings or specifications or the misdescription of details of work that are manifestly necessary to carry out the intent of the drawings and specifications, or that are customarily performed, shall not relieve the Contractor from performing such omitted or misdescribed details of the work. The Contractor shall perform such details as if fully and correctly set forth and described in the drawings and specifications.
(e) The work shall conform to the specifications and the contract drawings identified on the following index of drawings:
1 of 16 C001 Title Sheet 2 of 16 C002 Typical Sections 3 of 16 C003 General Notes 4 of 16 C004 Plan and Profile 5 of 16 C005 Cross Section 6 of 16 C006 Cross Section 7 of 16 C007 Cross Section 8 of 16 C008 Grading Plan / Storm Water Pollution Prevention Plan 9 of 16 C009 Traffic Control Plan 10 of 16 C010 Structure Site Plan
11 of 16 C011 Structure General Notes 12 of 16 C012 Inlet and Outlest Plan Views 13 of 16 C013 Inlet and Outlet Elevation 14 of 16 C014 Sections and Steel List 15 of 16 C015 20’ x 4’ Conduit Type A, 706.05 16 of 16 C016 Boring Logs
(End of clause)
5352.201-9101 OMBUDSMAN (10 AUG 2005)
(a) An ombudsman has been appointed to hear and facilitate the resolution of concerns from offerors, potential offerors, and others for this acquisition. When requested, the ombudsman will maintain strict confidentiality as to the source of the concern. The existence of the ombudsman does not affect the authority of the program manager, contracting officer, or source selection official. Further, the ombudsman does not participate in the evaluation of proposals, the source selection process, or the adjudication of protests or formal contract disputes.
This is the start of the file's text. The full file is on GovTribe.
File details come from the government source that posted it. Updated .