This is a Purchase Description for a Halon Analyzer to be delivered to the 802d Maintenance Group Chemical Analysis Flight at Robins Air Force Base, Georgia.

The contractor shall provide a fully automated custom gas chromatograph system configured with a liquid autosampler, two split/splitless capillary injectors, two electron capture detectors, and Windows 11-compatible software with auditing capabilities. Delivery is required within 56 days after receipt of order on an FOB Destination basis to Building 165, Room 20, Robins AFB, GA 31098, with attention to Michael Tew (Primary Government Representative, 478-222-8378) or Della Smith (Alternate, 478-327-4754). Installation and configuration must be completed within 10 days of delivery, followed by a functional test observed by the Government Representative. An Installation Acceptance Report must be submitted via electronic email within 10 days of successful testing. The contractor shall provide one day of on-site operational training for up to four government personnel immediately following installation, with all associated travel and living expenses covered by the contractor. A standard warranty on parts and labor begins from equipment startup. The contractor must designate a Program Manager and provide their name and phone number in writing to the Contracting Officer within five calendar days of contract award. On-site work is performed at Warner Robins Air Logistic Complex in Building 165, normally 8:00 am to 4:00 pm EST, Monday through Friday, with flexibility for adjusted hours as required by the Government with 48-hour notice.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

PURCHASE DESCRIPTION

Halon Analyzer

21 October 2026

1.0 DESCRIPTION. The Contractor shall provide all the tools, parts, materials, labor, travel, installation, and training necessary to provide one halon analyzer consisting of one fully automated custom gas chromatograph system to the 802d Maintenance Group Chemical Analysis Flight (802 MXSS/MXDTA) at Robins Air Force Base (AFB), Georgia.

1.1 The gas chromatograph system shall be configured in the following manner:

• Liquid autosampler

• Two Split/splitless capillary injectors

• Detectors (2) Electron Capture

• Software must be compatible with Windows 11 operating system and have auditing capabilities

2.0 Service Support.

2.1 Delivery.

2.1.1 Government Representatives. The following individuals will serve as the Primary and Alternate Government Representatives as the points of contact through which all contractor-provided services will be requested and accomplished for MXSG. Government Representatives will not supervise the Contractor, and they are not empowered to make any contractual commitments or to authorize any contractual changes on the Government’s behalf. The following individuals will serve as Government Representatives for MXSG.

2.2 Shipping/Delivery/Period of Performance. The Contractor shall deliver all items, FOB Destination, within 56 days ARO.

2.3 Ship To Address.

Attention: Michael Tew Unit: 802 MXSS/MXDTA

DODAAC: F3QCCM

Address: 325 Richard Ray Blvd

Primary Government Representative Alternate Government Representative Name: Michael Tew Name: Della Smith Unit: 802 MXSS/MXDTA Unit: 802 MXSS/MXDTA Phone: (478) 222-8378 Phone: (478) 327-4754 Email: michael.tew.3@us.af.mil Email: della.smith@us.af.mil

Bldg. 165, Room 20 Robins AFB, GA 31098

2.4 Incidental Services.

2.4.1 Installation. Within 10 days of delivery, the Government Representative shall contact the Contractor to schedule installation and subsequent training. The Contractor shall install, configure, and verify the halon analyzer system. After installation has been completed, the Contractor shall perform a functional test to ensure proper operation. The Government Representative will observe the functional test results.

2.4.1.1 Acceptance. The system shall be deemed fully functional and ready for government use immediately upon successful completion and joint observation of the functional test described in paragraph 2.4.1. Within 10 days of successful testing, the Contractor shall provide, via electronic email to the Government Representative, an Installation Acceptance Report to verify that the installation and configuration were performed in strict accordance with technical specifications.

(CDRL A001, DI-NDTI-80809/NOT 3, Test/Inspection Report)

2.4.2 Training. Immediately following successful completion and Government acceptance of the functional test, the Contractor shall provide one (1) day of on-site operational training for up to four (4) government personnel during the same visit. The Contractor shall be responsible for all associated travel and living expenses.

2.5 Warranty. The Contractor shall provide a standard warranty on parts and labor which will begin from startup of the equipment.

2.6 Options. None

3.0 Government Furnished Equipment and Services or Government Furnished Property

(GFP) and services. None

4.0 General Information.

4.1 Contractor Program Manager. The Contractor shall provide a Program Manager who shall be the single point of contact between the Contractor and the Government. The name and phone number of the Contractor’s Program Manager shall be provided in writing to the Contracting Officer, Government Representatives, and COR no later than five (5) calendar days after contract award date.

4.2 Place of Performance and Hours of Work. On-site contract services shall be performed at the Warner Robins Air Logistic Complex. The work will take place in building 165 at Robins Air Force Base, GA. The Contractor’s work hours (shifts) shall normally be from 8:00 am to 4:00 pm (EST), Monday through Friday. The Government may adjust the Contractor’s work hours based on workload requirements, with the flexibility to start work earlier, work odd shifts, and/or work weekends. The Government will provide the Contractor the required work hours

(schedule) for contractor personnel, and will provide a 48-hour notice prior to changing any work hours.

4.3 Recognized Holidays. Unless otherwise required by the Government, the Contractor shall not have access to Government facilities to work or telework on all federal holidays or during facility closings as authorized by the Government. If the holiday falls on Saturday, it is observed on Friday. If the holiday falls on a Sunday, it is observed on Monday.

4.4 Security Requirements.

4.4.1 Government Security Regulations. The Contractor shall ensure personnel, information, system, facility, and international security requirements are met in accordance with 32 CFR Part 117, National Industrial Security Program Operating Manual (NISPOM), Department of the Air Force Instruction (DAFI) 31-101, Base Defense Operations. The National Industrial Security Program Operating Manual (NISPOM), 32 CFR Part 117 is the authoritative manual concerning baseline standards for the protection of classified information in connection with classified contract and activities under the National Industrial Security Program.

- 32 CFR Part 117, National Industrial Security Program Operating Manual (NISPOM) “most current”

- DoDM5220.22V2_AFMAN16-1406V2, Operations Support: National Industrial Security Program: Security Procedures for Government Activities, “most current”;

Incorporating DAFGM2025-01, “most current”

- DoDD 5205.02E, DoD Operations Security (OPSEC) Program “most current”, Chg. 2;

“most current”

- DoDM 5205.02, DoD Operations Security (OPSEC) Program Manual “most current”, Chg. 2; dated “most current”

- AFI10-701, Air Force Operations Security (OPSEC) “most current” , Chg. 1, dated “most current”

- DoDI 5200.02, DoD Personnel Security Program (PSP) “most current”, Chg. 3; “most current”

- DoDM 5200.02 Procedures for The DoD Personnel Security Program (PSP) “most current”, Chg. 1; “most current”

- DoDM 5200.02_DAFMAN16-1405, Dept of Air Force Personnel Security Program “most current”; Incorporating DAFGM2026-01, “most current”

- DoDI 5200.48, Controlled Unclassified Information (CUI) “most current”

- DoDI5200.48_DAFI16-1403_DAFGM2025-01, Department of the Air Force Guidance

Memorandum to DoDI 5200.48_DAFI 16- 1403, Controlled Unclassified Information (CUI) (Under Secretary of Defense Memorandum, “most current”, Change to Policy on Sharing Controlled Unclassified Information with Foreign Entities) “most current”

- NIST SP 800-171A, Protecting Controlled Unclassified Information in Non-federal Systems and Organizations CSR May 2024, REV 3, “most current” SP 800-171 Rev. 3

- DoDI 8510.01, Risk Management Framework for DoD Systems “most current”

- DoDI 8582.01, Security of Non-DoD Information Systems Processing Unclassified

Nonpublic DoD Information “mot current”

- DoDM 5200.01-V1, DoD Information Security Program: Overview, Classification, and

Declassification “most current” , Chg 3; “most current”

- DoDM 5200.01V1_DAFMAN16-1404V1, Department of Air Force Information Security Program: Overview, Classification, & Declassification “most current:; Incorporating DAFGM2025-01, “most current”

- DoDM 5200.01-V2, DoD Information Security Program: Marking of Information “most current”, Chg 4; “most current”

- DoDM 5200.01V2_DAFMAN16-1404V2, Department of Air Force Information Security Program: Marking of Information “most current”; Certified Current “most current”

- DoDM 5200.01-V3, DoD Information Security Program: Protection of Classified Information”most current” , Chg. 4; “most current”

- DoDM 5200.01V3_DAFMAN 16-1404V3, Department of Air Force Information Security Program: Protection of Classified Information “most current:

- DODM 5400.07, DoD Freedom of Information Act (FOIA) Program “most current”

- DODM 5400.07_AFMAN 33-302, Air Force DoD Freedom of Information Act (FOIA)

Program “most current”

- DoD Issuances website https://www.esd.whs.mil/directives/issuances/dodm/

AF e-Publications website https://www.e-publishing.af.mil/Product-Index/

4.4.2 Communications Security (COMSEC). The Contractor shall use only secure communications methods and/or equipment to transmit or otherwise transfer classified and/or sensitive, but unclassified, information in accordance with 32 CFR Part 117.21, National Industrial Security Program Operating Manual (NISPOM). NSA/CSS Policy Manual 3-16, Control of COMSEC Material.

4.4.3 Contractor Access To Department of the Air Force Installations.

4.4.3.1 The contractor shall obtain base identification and vehicle passes, if required, for all contractor personnel who make frequent visits to or perform work on the Department of the Air Force installation(s) cited in the contract. Contractor personnel are required to wear or prominently display installation identification badges or contractor-furnished, contractor identification badges while visiting or performing work on the installation.

4.4.3.2 The contractor shall submit a written request on company letterhead to the Contract Surveillance Management Office (CSMO) POC (Wide Area Workflow – WAWF Acceptor or Contracting Office Representative – COR) listing the following: contract number, location of work site/building number, start and stop dates, and names of employees, birthdate; license number/state of issue; days of the week/hours needed (including overtime) and subcontractor employees needing access to the base. The letter will also specify the individual(s) authorized to sign for a request for base identification credentials or vehicle passes. The CSMO POC will endorse the request and forward it to the issuing base pass and registration office or Security Forces for processing. When reporting to the registration office, the authorized contractor individual(s) should provide a valid driver’s license/Identification card/Passport, current vehicle registration, valid vehicle insurance certificate, and all visitors are subject to a criminal background check and required to follow all traffic guidelines while on the installation to obtain a vehicle pass.

https://www.esd.whs.mil/directives/issuances/dodm/ https://www.e-publishing.af.mil/Product-Index/

4.4.3.3 During performance of the contract, the contractor shall be responsible for obtaining required identification for newly assigned personnel and for prompt return of credentials and vehicle passes for any employee who no longer requires access to the work site.

4.4.3.4 When work under this contract requires unescorted entry to controlled or restricted areas, the contractor shall comply with DAFI 31-101, Integrated Defense, and DODMAN5200.02_DAFMAN 16-1405 , Air Force Personnel Security Program

4.4.3.5 Upon completion or termination of the contract or expiration of the identification passes, the prime contractor shall ensure that all base identification passes issued to employees and subcontractor employees are returned to the issuing office.

4.4.3.6 The contractor shall provide an after-hours contact number or after-hours email in the Emergency Mass Notification System (EMNS) for each of their personnel, whose normal place of duty is on a DoD installation or within a DoD facility. The contractor shall comply with any additional requirements in DAFMAN 10-206 for emergency operational reporting. Foreign Nationals may participate and may remove themselves from the Emergency Mass Notification System at any time. To update information, personnel can access the globe icon on their system desktop screens and choose the “Access Self-Service” option.

4.4.3.7 Failure to comply with these requirements may result in withholding of final payment.

4.4.3.8 If a contractor is denied base access due to criminal activity the CSMO POC will notify the contracting company which will take appropriate action to resolve the issue.

4.4.4 Visitors Only – No Badging ID (Short Term Pass). The Air Force has mandated all visitors consent to a check of their criminal history prior to being allowed access to installations.

The check will be conducted at the Visitor Control Center (VCC) off Watson Boulevard, Robins AFB, GA. The Contractor shall submit a letter to the Badging Agent [CSMO POC (WAWF Acceptor or COR)] listing all contractor/subcontractor personnel requiring access with the information requested in paragraph 4.4.3.2. The pass issued by the Visitor Control Center authorizes unescorted entry to Robins AFB for the bearer only. For visitors, a short term pass is up to 60 days.

4.4.5 Operations Security (OPSEC). The purpose of OPSEC is to reduce the vulnerability of USAF missions to adversary collection and exploitation of critical information. The Contractor shall comply with DoDD 5205.02E “DoD Operations Security (OPSEC) Program”, DoD Manual

5205.02 “DoD Operations Security (OPSEC) Program Manual” and AFI 10-701 “Operations Security (OPSEC)” to protect United States (U.S. Government interest. The Contractor shall ensure compliance with OPSEC requirements including procedures to protect classified and/or sensitive, but unclassified, Government projects and/or programs. The Contractor shall ensure Contractor personnel who perform work at Robins AFB or another Government facility comply with the OPSEC procedures of the facility.

4.4.6 Security Incident or Violation. The Contractor shall immediately notify the Government Security Office of any potential or actual security incidents or violations including potential or https://static.e-publishing.af.mil/production/1/af_a4/publication/dafi31-101/controlled_unclassified_information.pdf https://static.e-publishing.af.mil/production/1/saf_aa/publication/dodman5200.02_dafman16-1405/dodm5200.02_afman16-1405.pdf actual unauthorized disclosure or compromise of classified and/or sensitive, but unclassified, information.

4.5 Supply Chain Risk Management. The Contractor shall implement risk management procedures to ensure that system, equipment, components, software, maintenance equipment, and supplies do not incorporate counterfeit parts, malicious code, or other elements that would allow adversaries to gain access to data and critical program information and disrupt operations.

Contractor risk management procedures shall comply with:

DoDI5000.83 DAFI 63-113, Program Protection Planning for Life Cycle Management, SAE Aerospace Standard AS5553D, Counterfeit Electrical, Electronic, and Electromechanical (EEE) Parts; Avoidance, Detection, Mitigation and Disposition, National Institute of Standards and Technology (NIST) Special Publication 800-53 Rev 5, Security and Privacy Controls for Information Systems and Organizations.

4.6 Contractor Identification. Contractor personnel shall wear visible identification designating them as contractors at all times while on Robins Air Force Base.

4.7 Contractor Vehicle Entry. The Contractor shall contact the Robins Air Force Base Visitor's Center to and comply with local procedures for obtaining credentials and vehicle entry.

Information may be obtained by calling the following phone number: Commercial 478-222- 1972.

4.8 Agency Affirmative Procurement Program. In accordance with RFO 23.102 (Policy) and

23.103 (Procedures), 100% of purchases of Environmental Protection Agency (EPA)-designated products included in the Comprehensive Procurement Guidelines (CPG) list [https://www.epa.gov/smm/comprehensive-procurement-guideline-cpg-program] and/or United States Department of Agriculture (USDA)-designated products included in the bio based product listings [http://www.biopreferred.gov] shall, at a minimum, meet the EPA or USDA standards for recovered materials or bio based content, respectively, unless an item cannot be acquired competitively within a realistic timeframe, meet appropriate performance standards, and/or be acquired at a reasonable price.

4.8.1 The Contractor shall provide estimates and verification of recovered material for EPA-designated CPG products and certification for both EPA-designated CPG products and USDA-designated bio based products. In accordance with the Robins Air Force Base, Georgia / Affirmative Procurement Program (formerly Green Procurement Program (GPP)) Plan, the Contractor shall provide estimates and certifications to the Government for completion of the applicable attachment(s) to be included in the Purchase Request (PR) package.

4.9 Elimination of Use of Class I Ozone Depleting Substances (ODS)

4.9.1 Contractors shall not:

http://www.biopreferred.gov/

4.9.1.1 Provide any service or product with any specification, standard, drawing, or other document that requires the use of a Class I ODS in the test, operation, or maintenance of any system, subsystem, item, component, or process; or

4.9.1.2 Provide any specification, standard, drawing, or other document that establishes a test, operation, or maintenance requirement that can only be met by use of a Class I ODS as part of this contract/order.

4.9.2 For the purposes of Department of the Air Force policy, the following products that are pure (i.e., they meet the relevant product specification identified in DAFMAN 32-7002) are Class I ODSs:

4.9.2.1 Halons: 1011, 1202, 1211, 1301, and 2402

4.9.2.2 Chlorofluorocarbons (CFCs): CFC-11, CFC-12, CFC-13, CFC-111, CFC-112, CFC-113, CFC-114, CFC-115, CFC-211, CFC-212, CFC-213, CFC-214, CFC-215, CFC-216, and CFC- 217, and the blends R-500, R-501, R-502, and R-503; and

4.9.2.3 Carbon Tetrachloride, Methyl Chloroform, and Methyl Bromide.

4.10 Environmental Management Systems (EMS) Awareness. Environmental Management Systems (EMS) Awareness Training: All contractor personnel working on Robins AFB who perform activities on the installation are required to complete Air Force-provided initial EMS Awareness Training. It is the responsibility of the Prime Contractor to ensure that all sub-contractors, vendors, and employees complete this training prior to beginning work on Robins AFB. Notification of training completion shall be sent to the Robins AFB Contracting Officer (CO) to be maintained in the contract file for tracking purposes. Failure to provide documentation of EMS Training may result in termination of the contract.

4.10.1 EMS training is provided by Environmental Management. Contractors have two options to satisfy the mandatory EMS Awareness Training requirement. (Front Desk: 478-926-1176)

4.10.2 Option 1: Contractors can register for an account through The Environmental Awareness Course Hub (TEACH), the Air Force training database: https://usaf.learningbuilder.com/account/login/?ReturnUrl=%2f

Search for Course ID: EMS110UHHZ00293 Directions:

1. Hover your mouse over the Courses and Transcripts tab.

2. Click on Transcripts

3. Click into the TEACH Course Completion Log by clicking the orange Continue or Begin button.

4. When you are on the transcript, click on the blue “Search for Course” button.

5. When the pop up appears enter the course name or course number and press search.

6. Once you find the course you want to add, click on the +Select button to add the course to your transcript.

https://usaf.learningbuilder.com/account/login/?ReturnUrl=%2f

(Note: TEACH may not be supported by Internet Explorer; recommend using Chrome.)

4.10.3 Option 2: Contractor requests a copy of the Robins EMS Awareness Training PowerPoint Presentation from Environmental Management. The request should be sent to the Environment Management Workflow Box at the following email address, jessica.parker.15@us.af.mil. Once the presentation is received, the contractor is responsible for ensuring that all his/her employees view the training. (CDRL A002, DI-MGMT-80368A/T, Status Report/EMS Training)

4.11 ISO 50001-Energy Management System. Due to the WR-ALC being ISO 50001 certified, all contractors are subject to the Energy Management System (EnMS) requirements and shall abide by certification guidelines whenever applicable.

4.11.1 EnMS Training. All contractor personnel working on Robins AFB who perform activities on the installation are required to complete Air Force provided initial EnMS Training. It is the responsibility of the Prime Contractor to ensure that all sub-contractors, vendors, and employees complete this training prior to beginning work on Robins AFB.

4.11.1.1 EnMS training is provided by the Energy Assurance Office. The Contractor shall request the training by sending an email to 402MXSG.MXDEA.EnergyAssurance@us.af.mil.

4.11.2 Notification of training completion shall be sent to the Energy Assurance Office (402MXSG.MXDEA.EnergyAssurance@us.af.mil) and the CSMO POC to be maintained for tracking purposes. Failure to provide documentation of EnMS Training prior to beginning work may result in termination of the contract. (CDRL A003 DI-MGMT-80368A/T, Status Report/EnMS Training)

4.12 Contractor’s Safety Program. (See Appendix C, Part II, Para 7) The Contractor shall establish and maintain an acceptable safety program in accordance with their accepted Safety and Health Plan. The Air Force is part of the OSHA Voluntary Protection Program (VPP). All shall familiarize themselves with the requirements of VPP. Information on the VPP can be accessed at http://www.osha.gov/dcsp/vpp/index.html. Additionally, the Contractor is responsible for the safety and health of all subcontractor employees. No more than two Class C mishaps per contract year and Zero Class A or B mishaps will be tolerated. All changes to the plan must also be submitted in writing and approved by the Government.

4.12.1 Safety and Health Plan: Within 10 calendar days after contract award, the contractor shall email a copy of their company Safety Plan that is required to ensure compliance with the Occupational Safety and Health Act (OSHA) (Public Law 91-596) to 402mxw.se.wf@us.af.mil.

The Safety Plan will be provided to the Safety Office for review. The Safety Office will provide acceptance or non-acceptance within 5 working days of receipt to the government point-of-contact who will notify the CO. (CDRL A004, DI-SAFT-82080/T NOT 2, Contractor's Safety Plan).

mailto:jessica.parker.15@us.af.mil mailto:402MXSG.MXDEA.EnergyAssurance@us.af.mil mailto:402MXSG.MXDEA.EnergyAssurance@us.af.mil http://www.osha.gov/dcsp/vpp/index.html mailto:402mxw.se.wf@us.af.mil

4.12.2 The Contractor Safety Plan shall address in detail the items listed in the Contract Appendix C, Part II through Part IV as applicable. For task specific procedures identified in the Contract Appendix C, the contractor’s internal procedures for those tasks must be identifiable within the submitted Safety Plan or shall be provided in an amendment or addendum to the company’s Safety Plan. If task specific procedures identified in the Contract Appendix C, are not submitted with the contractor’s Safety Plan, the submitted Safety Plan will be returned as NOT ACCEPTED. The contractor will have 5 working days to resubmit the Safety Plan, amendment or addendum to address or correct issues identified for non-acceptance. The Safety Office will provide acceptance or non-acceptance of the resubmission within 5 workings days of receipt to the government POC who will notify the CO.

4.12.3 In performing work under this contract on a Government installation, the contractor shall:

4.12.3.1 Take all reasonable steps and precautions to prevent accidents and preserve the health and safety of contractor and Government personnel performing or in any way coming in contact with the performance of this contract; and

4.12.3.2 Take such additional immediate precautions as the contracting officer may reasonably require for health and safety purposes.

4.12.3.3 The contracting officer may, by written order, direct Department of the Air Force Occupational Safety and Health (AFOSH) Standards and/or health/safety standards as may be required in the performance of this contract and any adjustments resulting from such direction will be in accordance with the Changes clause of this contract.

4.12.3.4 Any violation of these health and safety rules and requirements, unless promptly corrected as directed by the contracting officer, shall be grounds for termination of this contract in accordance with the Default clause of this contract.

4.13 Mishap Notification. (See Appendix C, Part II, Para 5) The Contractor shall notify the Robins AFB Safety Office telephonically at (478)327-4862 during duty hours and (478)926- 3567 after hours, within four (4) hour after initial notification of all mishaps or incidents for damage to DoD property (material plus labor) entrusted by this contract and employee injuries as a result of the contract operation. A follow-up (written or e-mail) of this mishap/incident notification shall be sent within three calendar days to the Government Representative, the Procurement Contracting Officer (PCO), Contract Surveillance Management Office (CSMO) Representative (with a copy to program manager), who will forward it to the Safety Office. The information that is not available at the time of the initial notification shall be provided within 20 calendar days after the mishap. Mishap notification shall contain, as a minimum, the following information:

a. Contract, Contract Number, Name and Title of Person(s) Reporting

b. Date, Time and exact location of accident/incident

c. Brief Narrative of accident/incident (Events leading to accident/incident)

d. Cause of accident/incident, if known

e. Estimated cost of accident/incident (material and labor to repair/replace)

f. Impound Authority Name and Phone Number (as applicable)

g. Nomenclature of equipment and personnel involved in accident/incident

h. Corrective actions (taken or proposed)

i. Other pertinent information

(CDRL A005, DI-SAFT-81563 NOT 2, Accident/Incident Report)

4.16 Inspection of Services/Inspection of Supply: In accordance with the Inspection of Supply/Services clause(s) identified in the contract/order, the Government reserves the right to inspect Contractor performance.

4.17 Invoice/Payment and Receipt/Acceptance: In accordance with R-DFARS clause 252.232-7003, Electronic submission of Payment Requests and Receiving Reports, the Contractor shall submit/process payment requests (invoices, Receiving Reports or combos) and receipt/acceptance documents via Procurement Integrated Enterprise Environment (PIEE) through module Wide Area Workflow (WAWF). Access at the following site:

https://piee.eb.mil/

4.18 Marking Requirement: Item Unique Identification and Valuation is required for all items to be delivered to the Department of defense (DoD) that meet the criteria established by the R- DFARS Clause 252.211-7003.

5.0 APPENDICES. None