Updated_Form_260_RPU_Repair_(PN_2689570-1)_Contractor_Testing_(3).pdf
PDF 15 KB Posted
- Attached to
- Repair Low Altitude Navigation and Targeting Infrared for Night (LANTIRN) Navigation Pod components
- Solicitation number
- FA853914R00158
About this file
Repair Test Article Requirements
View the file
Other files
| File | Type | Posted |
|---|---|---|
| FA8539-14-R-00158_Questions_and_Answers.docx | DOCX document | |
| SOW_CAVAF_CFM_V17 _8Aug2014.pdf | ||
| 1443085_PKGRQMT_REPORT.pdf | ||
| FA853914R00158.pdf | ||
| NEWTransportation_v_2.pdf | ||
| FD2060-14-00158_PWS_Final_3_Sep_14.pdf | ||
| 14-00158_QASP_w_signatures.pdf | ||
| CDRLS_A001-A008.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
AFMC Form 260, 20020830, V3 PageGenerated By PRPS Using Oracle Reports Version of4 1 3
16 OCT 2014
96214 / 2689570-1 5895012507263
2 EA
FIRST ARTICLE REQUIREMENTS
(AFMCI 64-110, AFMCI 23-102 and FAR Part 9, Sub Part 9.3) (Additional Instructions on Page 3)
1. DATE
2. PR/MIPR NUMBER 3. CAGE / REFERENCE NUMBER 4. NSN
5. FIRST ARTICLE QUANTITY
THE FIRST ARTICLE IS UNIT(S) OF LOT/ITEM
AND WILL BE: PART OF PRODUCTION QUANTITY IN ADDITION TO PRODUCTION QUANTITYX
6. ARTICLES
XWILL WILL NOT SERVE AS A MANUFACTURING
STANDARD
7. LONG LEAD TIME ITEMS
XREQUIRED NOT REQUIRED
(See FAR 52.209-3 OR -4, alternate II)
X
8. SPECIAL REQUIREMENT/PRODUCTION FACILITIES (See FAR 52.209-3 OR -4 Alternate I)
REQUIRED NOT REQUIRED
9. TEST/INSPECTION REQUIREMENTS
A. CONTRACTOR TESTING X
GOVERNMENT TESTING
Performance or other characteristics which the First Articles must meet are
X
The technical data package (TDP)/contract
B. The detailed technical requirements for First Article approval tests are contained in
The TDP/contract. Testing will be accomplished for Form,Fit, Function (FFF) in the next higher assembly (NHA).
C. X TEST PLAN REQUIRED
(Cite Spec and Para number)
Number of days for government approval/disapproval 45 days.
D. Contractor's notification to ACO and
407 SCMS/GULC
(Requesting Activity) of test time and location due 30 days prior to start of testing.
E. X TEST REPORT REQUIRED
(1) Forwarded to
WR-ALC AFMC AFLCMC/WNYED
Attn: Luis Bassora
235 Byron Street, Suite 19A
(2) Government written notice of approval/disapproval due 45 days after receipt of contractor's report.
F. FIRST ARTICLE DELIVERY
(1) Due within 180 calendar days from date contract.
(2) Notify 20 calendar days prior to shipment.
(3) Delivered to government at
DLA Central Receiving, DDWG ER
Special Handling, FAT Unit
455 Byron St.
(Set Forth Consignee and Address)
(4) Government written notice of approval/disapproval within 105 days after receipt of first article package.
Robins AFB, GA 31098-1670
Robins AFB, GA 31098-1887
"The First Article offered must be manufactured at the facilities in which that item is to be produced under the contract, or if the First Article is a component not manufactured by the contractor, such component must be manufactured at the facilities in which the component is to be produced for the contract. A certification to this effect must accompany each First Article which is offered."
FD2060
AFMC Form 260, 20020830, V3 PageGenerated By PRPS Using Oracle Reports Version of4 2 3
G. Estimated cost of government testing/inspection evaluation.
$5,000.0000
10. DISPOSITION OF FIRST ARTICLES
X Approved First Articles will be forwarded to
DLA requirement.
(insert quantity) First Articles will be expended in testing. Residual components of dispproved First Articles will be returned to the contractor will be retained by pending disposition instructions from the contractor.
First Articles will be installed on aircraft/equipment to determine proper fit/function. Approved article will remain on the aircraft/equipment and will not be forwarded to USAF Supply, but will be considered part of the contract quantity.
X will be retained by 402 MXSG/MXRILIM pending disposition instructions from the contractor.
On purchase requests designated as direct shipments the following disposition will apply. (NOTE: Always applicable on Foreign Military Sales (FMS)).
a. Approved First Articles will be returned to the contractor for shipment with production item.
b. Disposition of disapproved First Articles will remain the same as marked above.
X Other Disposition:
Vendor provides prepaid shipping labels for return
11. CONDITION(S) FOR WAIVER OF FIRST ARTICLE APPROVAL
a.
X
X b.
c.
d.
e.
f.
Offerors who have previously furnished production quantities of the same or similar article to the prime contractor for delivery to the
Government, DoD, Air Force.
Offerors currently in production of the same or similar article for a Government, DoD, Air Force contract and who have received First Article approval under the existing contract.
Offerors who have previously furnished production quantities of the same or similar articles to the
Government, X DoD, Air Force, provided articles thus furnished, have exhibited satisfactory performance in service in the opinion of the Air Force.
Provided not more than 36 months have elapsed since completion of the contract.
First Article testing will not be waived.
See Remarks in block 12 below.
A. PROCURING OFFICE B. CONTRACT NUMBER C. DATE OF CONTRACT D. SPECIFICATION NUMBER AND REVISION
X Disapproved First Articles
12. REMARKS
NOTE TO BUYER: UNDER CONDITIONS A AND C ABOVE, THE COGNIZANT ENGINEERING ACTIVITY WILL DECIDE WHETHER OR NOT THE ITEM HAS EXHIBITED SATISFACTORY PERFORMANCE IN SERVICE AND PREPARE AND RETAIN SUPPORTING DOCUMENTATION TO FULLY JUSTIFY THIS DECISION. THE BUYER MUST SOLICIT DUAL PRICES (That is, both with and without requirement for first article approval) AND MUST FURNISH THE COGNIZANT ENGINEERING ACTIVITY WITH THE FOLLOWING INFORMATION ON THE PREVIOUSLY SUPPLIED
ARTICLE:
14. COGNIZANT ENG ORGANIZATION RESPONSIBLE FOR
CONDUCTING TEST (Name, Organization, Phone)
13. COGNIZANT ENG ORGANIZATION RESPONSIBLE FOR
APPROVING TEST (Name, Organization, Phone)
Plaisted, Gary D will be returned to the contractor
AFMC Form 260, 20020830, V3 Generated By PRPS Using Oracle Reports Version Page of 4 3 3
Plaisted, Gary D
407 SCMS/GUEA
468-5319
478-926-5319
File details come from the government source that posted it. Updated .