This is a Fair Opportunity Proposal Request (FOPR) issued under the Automatic Test Systems Acquisition (ATSA) multiple award Indefinite-Delivery Indefinite-Quantity (IDIQ) contract for the F-16 Aircraft Adapter Group (AAG) Common Aircraft Portable Reprogrammable Equipment (CAPRE) Secure Memory Loader Verifier (SMLV) effort. The FOPR number is ATSA-0003-FO-1, and proposals are due by 4:00 PM Eastern Time on December 16, 2026, submitted electronically via DoDSAFE to the Contracting Officer Ben Wilton (benjamin.wilton@us.af.mil) and Contract Specialist Ashley Wynn (ashley.wynn.1@us.af.mil). The procurement follows RFO 16.507 ordering procedures and is not subject to FAR 15 source selection requirements.
Offerors must submit three separate volumes: Volume I (Technical Capability, maximum 20 pages), Volume II (Past Performance, maximum 15 pages), and Volume III (Cost/Price, no page limit). Technical evaluation encompasses three subfactors: Technical Data Package delivery commitment (Pass/Fail), LRU Data Possession and Access demonstrating understanding of configuration management and software analysis proficiency, and Manpower adequacy with clearly defined engineering levels (Staff, Senior, Mid, and Junior). Past Performance evaluation requires evidence of experience developing both software and aircraft cables for Line Replaceable Units and Memory Loader Verifiers within the past five years, plus production capabilities for ruggedized aerospace cables, with particular emphasis on F-16 platform experience or comparable high-complexity systems. Award will be made on a Technical, Past Performance, and Price Trade-Off (TPPT) basis, with non-price factors weighted more heavily than price. Cost proposals must include a Basis of Estimate addressing cost-type CLINs 0002/1002, 0003AA through 0003AK, covering both basic and option periods. The evaluation will use a Most Probable Cost methodology for cost-type CLINs and analyze price realism, reasonableness, and unbalanced pricing considerations. An Ombudsman is available to resolve procurement concerns at Col Ionio Andrus, 937-255-3008, or asca@us.af.mil.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Fair Opportunity Proposal Request (FOPR), Attachment A
FOPR# ATSA-0003-FO-1
Instructions to Offerors and Evaluation Factors for Award
1. Instructions to Offerors (ITO):
A. This is a competitive fair opportunity selection conducted in accordance with (IAW) Revolutionary Federal Acquisition Regulation Overhaul (RFO) Part 16.507. Orders placed under RFO 16.507 Indefinite-Delivery Indefinite-Quantity (IDIQ) contracts are not subject to RFO 15 source selection procedures. Accordingly, issuance of an order under this Fair Opportunity Proposal Request (FOPR), should an award be made, shall follow the ordering procedures outlined in RFO 16.507, as supplemented.
B. The proposal submitted in response to this FOPR must be in compliance with the terms and conditions of the Automatic Test Systems Acquisition (ATSA) multiple award IDIQ contract and the requirements as stated in the FOPR, including the F-16 Aircraft Adapter Group (AAG) Common Aircraft Portable Reprogrammable Equipment (CAPRE) Secure Memory Loader Verifier (SMLV) Statement of Work (SOW). All claimed capabilities to meet the requirements shall be realistic and are subject to verification by the Government. Non-conformance with these instructions may result in rejection of the proposal, an unfavorable proposal evaluation, or being deemed ineligible for award. The Fair Opportunity Decision Authority (FODA) will select the Offeror’s proposal which conforms to the FOPR requirements (to include all stated terms, conditions, representations, certifications, and all other information required by the submission instructions), and is judged, based on the evaluation factors, to represent the best value to the Government. Because the Government seeks to award to the Offeror whose proposal represents the best value in fulfilling Air Force requirements, this may result in an award to a higher-rated, higher-priced Offeror, where the decision is consistent with the evaluation factors, and the FODA reasonably determines that the technical and/or overall business approach of the higher priced Offeror outweighs the price difference.
C. Offerors shall clearly identify any exception to the terms and conditions and shall provide complete supporting rationale. The Government reserves the right to determine any such exceptions are unacceptable. Any exception determined unacceptable by the Government may result in the Offeror’s proposal being determined noncompliant and ineligible for award. This information shall be provided in the format and content of the table below within the Offerors proposal cover letter. If no exceptions are taken, include a statement stating so within the proposal cover letter.
FOPR Exceptions
FOPR
Document
Page/ Paragraph
Requirement/ Portion Rationale
SOW,
ITO,
Evaluation Factor, etc.
Applicable Page and Paragraph Numbers
Identify the requirement or portion to which exception is taken
Describe why the requirement can/will not be met
D. The proposal shall be clear, concise, and shall include sufficient detail for effective evaluation and for substantiating the validity of stated claims. The proposal should not simply rephrase or restate the Government's requirements but, rather, shall provide convincing rationale to address how the Offeror intends to meet these requirements. Offerors shall assume that the Government has no prior knowledge of their facilities or experience and will base its evaluation on the information presented in the Offeror's proposal.
E. Discrepancies. If an Offeror believes the requirements in these instructions contain an error, omission, or are otherwise unsound, the Offeror shall immediately notify the Contracting Officer (CO) in writing with supporting rationale as well as the remedies the Offeror is asking the CO to consider as related to the omission or error.
F. Use of Non-Government Advisors. Offerors are advised that technical and cost/price data submitted to the Government in response to this FOPR may be released to non-Government advisors for proposal review and analysis. All non-Government advisors have signed non-disclosure statements. The non-Government advisors support will be provided by:
Non-Government Advisor Company Name Company POC POC Information PE Systems Vincent Adamo 478-497-7141 HX5 Melissa Dorman 478-472-1636
Offerors shall complete paragraph (2) below, or provide written objection to disclosure as indicated in paragraph (1) below, if the Offeror objects to disclosure of a portion of the proposal, the consent in (2) should be provided for the remainder of the proposal. Include either paragraph
(1) or (2) below, completed as applicable, in writing to the CO within ten (10) calendar days of the FOPR issuance:
(1) Any objection to disclosure:
(i) Shall be provided in writing to the Contracting Officer within ten (10) days of FOPR issuance; and
(ii) Shall include a detailed statement of the basis for the objection. The detailed statement shall identify the specific portions of the proposal the Offeror objects to disclosure to non-Government advisors.
(2) I understand technical and cost/price data submitted to the Government in response to this FOPR may be released to non-Government advisors. I consent to release of any (unless objection is provided in (1) above) proprietary, confidential, or privileged commercial or financial data provided by the firm(s) named below in response to this solicitation, to non-Government advisors for review and analysis:
Firm:
Name (individual authorized to commit firm):
Title:
Date of Execution:
Signature:
G. Each Offeror shall submit proposals electronically in format readable by Microsoft (MS) Office or Adobe Acrobat X Pro, as applicable, to the CO, Ben Wilton, benjamin.wilton@us.af.mil and the Contract Specialist Ashley Wynn, ashley.wynn.1@us.af.mil via DoDSAFE.
The Offeror shall submit proposals for consideration no later than 4:00pm (Eastern Time), 16 Dec 2026. Only one (1) proposal shall be submitted per company in response to this requirement.
Proposals received after the date/time specified will not be evaluated.
Proposal packages must be submitted via DoDSAFE at https://safe.apps.mil. To submit the proposal package, the offeror shall send an email to both the CO and Contract Specialist identified above and request a DoDSAFE drop-off link. Once the CO and/or Contract Specialist receive the request, a drop-off link will be sent to the offeror to upload and send the proposal submittal. NOTE: The proposal submittal, and not the request for a drop-off link, must be received by the CO and/or Contract Specialist by the proposal due date and time. Should the DoDSAFE proposal be received after the proposal due date and time, the proposal will be considered late and will not be evaluated.
H. Offerors submitting a proposal in response to this FOPR shall submit a Technical Volume (Volume I), Past Performance Volume (Volume II) and a Cost/Price Volume (Volume III). Text shall be single-spaced, on an 8 ½ x 11 letter size with a minimum one-inch margin all around.
Font shall be no less than Times New Roman 10pt. Offerors may use up to two (2) 11x17 inch foldout pages specifically for the Subfactor 1.3 Staffing Matrix/Manpower Plan. Each 11x17 page will count as two (2) 8.5x11 pages toward the Volume I page limit (i.e., up to four (4) pages). Pages shall be numbered consecutively within each volume. The page limits prescribed in the following table are maximum page limits for each volume. Cover pages, tables of contents, cross reference matrix, tables, and glossaries shall not be counted against prescribed page limits.
Pages submitted in excess of the limits in the below table will not be read or considered in the Government’s evaluation of the proposal.
Technical and Past Performance Volumes information shall be submitted in either MS Word or searchable PDF format. The Cost/Price Volume information shall be submitted in MS Excel format; except any narrative substantiation the Offeror provides in a separate Cost/Price Volume MS Word or PDF file.
Each volume shall be submitted as a separately labeled electronic file(s).
mailto:benjamin.wilton@us.af.mil mailto:ashley.wynn.1@us.af.mil https://safe.apps.mil/
Offerors must ensure that cost/price information is only included in Volume III. Do NOT include any pricing information in the Technical Volume. All unit and extended prices provided shall be rounded to the nearest dollar. Extended prices must be divisible by the number of units proposed.
All loaded labor rates shall be rounded to the nearest penny.
Submit your proposal electronically in accordance with the table below. All electronic submissions shall reference the complete FOPR number in the subject line.
VOLUME
REFERENCE
TITLE
MAXIMUM
NUMBER OF
PAGES
Cover Letter 2 Factor 1 Technical Capability
Sub-factor 1.1 Technical Data
Sub-factor 1.2
Access to Line Replaceable Unit (LRU) Data (Interface Control
Documents)
Sub-factor 1.3 Engineering Personnel Level Assigned per AAG
II
Factor 2 Past Performance 15 Subfactor 2.1 Past Experience of
Developing Software and Aircraft Cables for LRUs
Subfactor 2.2 Production Capabilities and Experience
III Factor 3 Cost/Price No page limit
(1) Volume I:
Cover Letter shall include the following (2-page max):
Offeror’s contact number Small business status/categories Company name and primary and alternate points of contact with email/phone and stating who all are authorized to contractually obligate the company
CAGE Code Unique Entity Identifier (UEI) number CMMC Unique Identifier (UID) A statement that the company understands the specified requirements and will meet the performance standards and requirements therein A statement that the company does or does not take exception to any of the requirements of this order Acknowledges use of non-Government advisors IAW para F, and, If proposing a teaming arrangement, specific information about what each vendor on the team will accomplish should the offeror become the awardee
A statement of proposal validity period of at least 120 days
Factor I: Technical Approach (20-page max)
The Technical Proposal should be specific and complete. Legibility, clarity, and coherence are very important. Your responses will be evaluated against the technical subfactors. Provide as specifically as possible with the actual methodology you would use for accomplishing/satisfying the subfactors outlined in Section 3 of this document.
Address your technical solution for meeting or exceeding the Government’s minimum performance or capability requirements of each technical subfactor. All the requirements specified in the solicitation are mandatory. By your proposal submission, you are representing that your firm will perform all the requirements specified in the solicitation. Do not merely reiterate the objectives or reformulate the requirements specified in the solicitation.
(2) Volume II:
Factor 2: Past Performance (15-page max)
The Offeror shall provide Past Performance evidence that clearly demonstrates their record of recent and relevant experience delivering capabilities similar to the requirements outlined in the SOW. Specifically, the Offeror shall provide detailed narratives and supporting data for prior efforts that demonstrate successful, integrated experience in the development of both software and aircraft cables designed for Line Replaceable Units (LRUs) and Memory Loader Verifiers (MLVs). To allow the Government to accurately assess the scope, magnitude, and complexity of these prior efforts, the Offeror shall provide the following specific information for each referenced contract or task order:
Recency – Effort(s) performed during the five (5) year period immediately preceding the date of issuance of this RFOP Relevancy – Provide the specific airframes, weapon systems, or aircraft networks supported, and detail their involvement across the engineering lifecycle (e.g., design, coding, fabrication, integration, testing)
Quantity: You may submit a maximum of three (3) prior efforts within the past 5 years. Any projects submitted beyond this limit may be disregarded by the evaluation team
(3) Volume III:
Factor 3: Cost/Price (no page limit)
1. The offeror shall complete the attached FOPR Attachment F, Offeror Cost Model, providing proposed direct and indirect rates, add-on factors, escalation, unit prices, and/or fee as applicable.
2. In a separate narrative, the offeror shall provide a Basis of Estimate (BOE) that explains the basis of each proposed unit price, rate, and/or add-on factor for cost-type CLINs 0002/1002, 0003AA, 0003AB, 0003AC, 0003AD, 0003AE, 0003AF, 0003AG, 0003AH, 0003AJ, and 0003AK to allow the Government the ability to evaluate all costs IAW RFO FAR 15.404. These unit prices, rates, and/or add-on factors must be proposed for the basic and option period.
The Government intends to rely on the information provided in the BOE and the competitive environment to determine that the proposed price/cost is fair and reasonable. If the proposed rates are based on a Forward Pricing Rate Proposal (FPRP) or Agreement (FPRA), offeror shall provide a copy of FPRP or FPRA with the proposal.
2. Basis of Award:
A. Award will be made in accordance with the basic contract ordering procedures, the procedures specified in the FOPR and on the basis of a Technical, Past Performance, and the Price Trade-Off (TPPT). An order may be awarded to the contractor who is deemed responsible IAW RFO 9.1, as supplemented, whose proposal conforms to the FOPR’s requirements (to include all stated terms, conditions, representations, certifications, and all other information required by the FOPR instructions) and is judged, based on the evaluation factors and subfactors, to represent the best value to the Government.
B. The Government intends to award an order to the Offeror whose proposal represents the best value to the Government. The evaluation will be based on three factors, listed in descending order of importance: Factor 1 - Technical Capability, Factor 2 - Past Performance, and Factor 3 - Price. For this requirement, the non-price factors (Technical Capability and Past Performance), when combined, are more important than Price. The Government’s primary objective is to select the Offeror who submits the highest-rated technical proposal combined with a strong record of successful past performance. In the event the evaluation results in two or more proposals being determined to be technically equivalent, or otherwise indistinguishable in their technical merit among the highest-rated submissions, the Government will use Past Performance as the primary discriminator. If the highest-rated technical proposals also demonstrate essentially equal Past Performance confidence assessments, the Government will then use Price as the ultimate deciding factor. In such circumstances, the award will be made to the Offeror who has proposed the lowest evaluated price among the group of offerors with essentially equivalent technical and past performance ratings. Therefore, while Technical Capability and Past Performance are the primary basis for the award decision, Price may become the determining factor for award between otherwise equal proposals.
C. The Government intends to make award based on the initial proposal submissions without conducting interchanges. Therefore, each offer should contain the Offeror’s best terms from a Technical Capability, Past Performance, and Price standpoint. However, the Government reserves the right to conduct interchanges, utilizing Interchange Notices (IN), if, during the evaluation, it is determined to be in the best interest of the Government. Interchanges are fluid interaction(s) between the Contracting Officer (CO) and the contractors that may address any aspect of the proposal and may or may not be documented in real time. Offeror responses to INs will be considered in making the order selection decision. Interchanges may be conducted with one, some, or all offerors as the Government is not required to conduct interchanges with any or all contractors responding to this FOPR.
3. Requirement Factors Responses to this FOPR will be evaluated against the following factors and subfactors:
Factor 1: Technical Subfactor 1.1: Technical Data Package Subfactor 1.2: LRU Data Possession and Access Subfactor 1.3: Manpower
Factor 2: Past Performance Subfactor: 2.1: Past Experience of developing software and aircraft cables for LRUs Subfactor 2.2: Production Capabilities and Experience
Factor 3: Cost/Price
FACTOR 1: Technical.
The offeror’s proposal shall, at a minimum, address each of the subfactors, as they apply to the CAPRE SMLV SOW. The technical proposal should demonstrate the contractor’s ability to perform the technical requirements. Evaluation Ratings are located on the last page of this document.
Sub-Factor 1.1 – Technical Data Package – Submittal Requirements: This subfactor shall evaluate the offeror's commitment to the intellectual property and data rights requirements of this solicitation on a Pass/Fail basis. To achieve a "Pass" rating for the intellectual property aspect of the requirement, the offeror must affirmatively state in their proposal both (a) that they understand the Government is requiring the delivery of a full Technical Data Package (TDP) and
(b) that they are able to deliver the full TDP as specified. A proposal will be deemed to have passed this criterion if it clearly and unambiguously provides this affirmative statement. Failure to include such a statement, or the inclusion of an ambiguous or conditional statement, will result in the proposal being rated as "Fail" for this subfactor.
Sub-Factor 1.2 – LRU Data Possession and Access – Submittal Requirements:
The Government shall evaluate the Offeror’s understanding, capability, and readiness to manage, retrieve, and analyze Line Replaceable Unit (LRU) data, software, and associated documentation. The Offeror shall provide a comprehensive Technical Narrative demonstrating their ability to execute the LRU data requirements. The narrative must specifically address the following elements:
1.2.1 Possession and Access to LRU Data:
This element shall be met when the offeror acceptably demonstrates evidence of current possession of or authorized, unencumbered access to the required LRU TDPs, software baselines, and historical engineering documentation and acceptably demonstrates a data rights posture, to include any licensing agreements necessary, to utilize the data for Government purposes without delay. Examples of acceptable evidence to reflect ownership of or unencumbered access are LRU Interface Control Documents, Software Requirement Specifications, Design Documents, Test Plans, or mutually signed Formal Agreements or Letters of Commitment. These documents must be submitted in PDF Format; emails are not acceptable.
1.2.2 Retrieval and Configuration Management:
The element shall be met when the offeror describes their methodology and internal systems for securely storing, archiving, and retrieving legacy LRU data and software
The element shall be met when the offeror provides detailed Configuration Management (CM) processes, specifically demonstrating how they track, trace, and extract past revisions of LRU software and hardware documentation from historical baselines
1. 2.3 Analysis and Interpretation Proficiency:
The element shall be met when the offeror demonstrates their technical proficiency by detailing their approach to analyzing and interpreting past revisions of LRU software
The element shall be met when the offeror provides a practical methodology or past performance example detailing how they evaluate historical software code, release notes, and engineering changes to resolve current obsolescence issues, perform regression testing, or support system integration
Sub-Factor 1.3 – Manpower – Submittal Requirements:
This subfactor shall be met when the offeror’s manpower plan acceptably demonstrates adequate resources allocated to the AAG requirement. The proposal acceptably identifies each AAG development effort or task with clear mapping to the SOW or WBS and clear identification of the engineering levels assigned to each effort or task (see table below for engineering level definitions to be utilized).
Level Definition
Staff-Level This individual possesses a minimum of 8 years of experience in software development, with at least 3 years of experience leading software development teams specifically on projects of similar scope and complexity to the AAG effort (provide brief examples). They possess expert knowledge of the relevant programming languages, frameworks, and development methodologies.
Senior-Level Software Engineer with a minimum of 5 years of experience in relevant technologies.
Mid-Level Software Engineer with a minimum of 3 years of experience in relevant technologies.
Junior-Level Software Engineer with a minimum of 1 year of experience in relevant technologies.
Provide a brief rationale for the proposed engineering skill mix, demonstrating why the assigned levels of expertise are appropriate and necessary for the technical complexity of the specific AAG task.
FACTOR 2: Past Performance
Subfactor: 2.1: Past Experience of developing software and aircraft cables for LRUs – Submittal Requirements.
The Government shall evaluate the Offeror’s technical understanding, capability, and readiness to execute the current requirement based on their demonstrated past corporate experience in developing software and physical cable interfaces for LRUs and Memory Loader Verifiers (MLVs), Evaluation Ratings are listed on the last page of this document.
2.1.1 Verifiable Experience Timeline & Scope:
The Offeror must clearly state the total years of verifiable experience they possess in this specific domain The Offeror shall identify the specific timeframes of performance (e.g., Month/Year to Month/Year) to demonstrate if the work occurred within the last five (5) years
The Offeror must explicitly state whether their experience encompasses both LRU/MLV software development AND aircraft cable development, or only one of those areas
2.1.2 Project Specifics and Platform Identification:
The Offeror shall provide specific examples of past projects. For each project, the
Offeror must provide:
Project Name / Contract Number Prime or sub-contractor Quantities delivered/developed The specific aircraft platform(s) supported. Note: Offerors must explicitly identify experience on platforms other than the F-16 Whether the platform was a military or commercial asset (Military platform experience is preferred)
2.1.3 Complexity and F-16 Comparability:
For each project example provided, the Offeror must include a brief technical description of the avionics system supported
The Offeror must explicitly compare the technical complexity and environmental stringency of their past platform experience to that of the F-16 environment, providing technical rationale to support their comparison
2.1.4 Lifecycle Involvement and Integration Challenges:
The Offeror shall detail their scope of involvement across the development lifecycle. To achieve maximum credit, the Offeror should demonstrate full lifecycle involvement (from initial requirements definition through final testing and integration)
The Offeror must provide a narrative demonstrating their practical understanding of the challenges involved in integrating software and hardware components within demanding aerospace environments, detailing how they successfully navigated these challenges in their past projects
Subfactor 2.2: Production Capabilities and Experience – Submittal Requirements.
The Government will evaluate the Offeror’s physical production capability and historical experience in manufacturing, testing, and delivering ruggedized aircraft cables for the F-16 or similarly highly complex aerospace platforms. To achieve the highest possible rating, Offerors must demonstrate comprehensive in-house production capabilities and extensive, verifiable experience specifically related to the F-16 or comparable high-performance platforms.
2.2.1 Production Facility and Capabilities (In-House vs. Outsourced):
The Offeror must explicitly state whether their ruggedized cable production capability is performed via an on-site, fully operational cable shop, or if the process is outsourced to a certified supplier
If performed In-House: The Offeror shall detail their comprehensive on-site capabilities, specifically addressing their equipment, processes, and capacity for cutting, stripping, termination, molding, over-molding, electrical and mechanical testing, and documentation
If Outsourced: The Offeror must provide a detailed description of their outsourcing management process. This must include supplier selection criteria, quality control (QC) procedures, and explicit risk mitigation strategies employed to ensure outsourcing does not result in cost increases or delivery delays
Certifications: The Offeror must provide proof of valid, current certifications required for the production of ruggedized aerospace cables (applicable to either their in-house facility or their chosen supplier)
2.2.2 Verifiable Experience Timeline & Scope:
The Offeror must clearly state the total years of verifiable experience they possess producing ruggedized aircraft cables. Offerors should clearly indicate if they meet or exceed the five (5) year threshold.
2.2.3 Project Specifics and Platform Identification:
The Offeror shall provide specific examples of past production projects. For each project, provide:
Project Name / Contract Number (if permissible) Quantities produced and delivered The specific aircraft platform(s) supported. Offerors must explicitly state if the cables were produced for the F-16 platform
If the platform was not the F-16, the Offeror must provide technical rationale demonstrating that the supported aerospace platform possesses environmental and performance requirements comparable to the F-16
2.2.4 Understanding of Requirements, Standards, and Challenges:
The Offeror must provide a narrative demonstrating a deep understanding of the specific requirements, quality standards, and rigorous testing procedures associated with aerospace-grade cable assemblies
The Offeror must detail specific manufacturing or integration challenges associated with producing cables for the F-16 (or comparable high-performance aircraft) and describe how their production processes successfully overcome these challenges
FACTOR 3: Cost/Price.
The Government will evaluate each offeror’s proposal submitted for Factor 3: Cost/Price for reasonableness, balance, and cost realism. Price realism is not a factor in this evaluation. A Total Evaluated Price (TEP), which will include an aggregate calculation of FFP CLINs and a Most Probable Cost (MPC) for cost-type CLINs, will be considered in making the award decision. The Government will evaluate each offeror’s cost/price proposal using one or more of the techniques described in RFO FAR 15.404. The Cost/Price factor will not receive an adjectival rating. Offerors whose price is determined to be unreasonable will not be considered for award. No cost/price data shall be included in any other volume, including cover letters. If cost/price information is included elsewhere in the documentation, the proposal may be deemed noncompliant and the proposal may not be evaluated. All dollar amounts shall be rounded to the nearest dollar. If any proposed unit/CLIN price does not meet the required rounding, the Government will round that unit/CLIN to the nearest whole dollar and the adjusted price will become the Offeror’s proposed amount. All labor rates should be rounded to the nearest penny.
1. The TEP will be used for evaluation purposes only. The TEP will be calculated for each Offeror by adding together the evaluated price for FFP CLINs and the most probable cost for cost-type CLINs as outlined below in both the basic and option periods;
the sum of the evaluated prices for CLINs 0001/1001, 0002/1002, 0003AA, 0003AB, 0003AC, 0003AD, 0003AE, 0003AF, 0003AG, 0003AH, 0003AJ, 0003AK, 0004AA, 0004AB, 0004AC, 0004AD, 0004AE, 0004AF, 0004AG, 0004AH, 0004AJ, 0004AK, 0005AB/1005AB, 0005AC/1005AC, 0005AD/1005AD, 0005AE/1005AE, 0005AH/1005AH, 0005AJ/1005AJ, 0006AB/1006AB, 0006AC/1006AC, 0006AD/1006AD, 0006AE/1006AE, 0006AH/1006AH, 0006AJ/1006AJ, A001/B001, A002/B002, A003/B003, A004/B004, A005/B005, A006/B006, A007/B007, A008/B008, A009/B009, A00A/B00A, A00B/B00B, A00C/B00C, A00D/B00D, A00E/B00E, A00F/B00F, A00G/B00G, A00H/B00H, A00J/B00J, A00K/B00K, A00L/B00L, A00M/B00M, A00N/B00N and A008. Evaluation of options or optional CLINs shall not obligate the Government to exercise such options or optional CLINs. The evaluated prices for each of the aforementioned CLINs will be calculated as explained in the following paragraphs:
a. CLINs 0001/1001, 0004AA, 0004AB, 0004AC, 0004AD, 0004AE, 0004AF, 0004AG, 0004AH, 0004AJ, 0004AK, 0005AB/1005AB, 0005AC/1005AC, 0005AD/1005AD, 0005AE/1005AE, 0005AH/1005AH, 0005AJ/1005AJ, 0006AB/1006AB, 0006AC/1006AC, 0006AD/1006AD, 0006AE/1006AE, 0006AH/1006AH, 0006AJ/1006AJ, A001/B001, A002/B002, A003/B003, A004/B004, A005/B005, A006/B006, A007/B007, A008/B008, A009/B009, A00A/B00A, A00B/B00B, A00C/B00C, A00D/B00D, A00E/B00E, A00F/B00F, A00G/B00G, A00H/B00H, A00J/B00J, A00K/B00K, A00L/B00L, A00M/B00M, A00N/B00N and A008 (FFP): The evaluated CLIN price will be calculated by multiplying the proposed unit price times the respective quantity.
b. CLINs 0002 and 1002 (CRNF): The Government will multiply the add-on factor resulting from the Government’s cost realism analysis by the Government-estimated travel cost (not disclosed to the offeror) per period. The resulting value will yield the evaluated CLIN price.
c. CLINs 0003AA, 0003AB, 0003AC, 0003AD, 0003AE, 0003AF, 0003AG, 0003AH, 0003AJ, and 0003AK (CPFF): The Government will multiply the proposed fee times the offeror’s most probable cost (excluding most probable cost of money), yielding the evaluated total fee dollars. The Government will add the evaluated total fee dollars to the offeror’s most probable cost and most probable cost of money, yielding the evaluated price. The Government will multiply the evaluated price times the respective quantity, yielding the evaluated CLIN price.
2. Reasonableness. The existence of adequate competition is expected to support a determination of reasonableness. The Government may use price analysis techniques described in RFO FAR 15.404 to further validate price reasonableness. If adequate competition is not obtained or if price reasonableness cannot be determined using price analysis of Government obtained information, additional information in accordance with RFO FAR 15.4 may be required.
3. Unbalanced pricing. Offerors are cautioned against submitting an offer that contains unbalanced pricing. Unbalanced pricing exists when, despite an acceptable total evaluated cost/price, the cost/price of one or more contract line items or sub-line items (Basic and Option periods) is significantly overstated or understated as indicated by the application of cost/price analysis techniques. An overstated or understated CLIN cost/price may be due to (a) an illogical progression of rates or unit costs/prices between program years, (b) unit costs/prices that do not take into account quantity variations, or (c) the “front-loading” of CLINs; either of these situations would reflect an inaccurate “true” cost/price for that CLIN. Front-loading occurs when a larger than normal amount of costs are concentrated in an early contract period. The Government may consider any “front-loaded” CLIN as unbalanced, because acceptance of the proposal could result in advance payment. The Government will analyze offers to determine whether there are unbalanced, separately priced line items or sub-line items.
Proposed unit costs/prices will be compared and evaluated to ensure that a logical progression exists as related to price and/or quantity changes within each offeror’s response to the pricing structure in RFP Attachment XX, Excel Cost/Price Model.
Offers that are determined to be unbalanced may be rejected if the lack of balance poses an unacceptable risk to the Government.
4. Cost Realism: The Government will perform cost realism analysis on the CPFF CLINs’ proposed costs (CLINs 0003AA-AK). Cost realism is the process of independently reviewing and evaluating specific elements of each offeror’s proposed cost estimate to determine whether the estimated proposed cost elements are realistic for the work to be performed, reflect a clear understanding of the requirements, and are consistent with the unique methods of performance described in the offeror’s technical proposal. The burden of proof for cost realism rests with the offeror. Accordingly, proposals will be evaluated to assess the likelihood that the proposed technical and managerial approach can successfully accomplish the SOW at the competitively proposed cost for cost type CLINs. For cost-type CLINs, the result of cost realism analysis is the MPC. The MPC estimate is the Government estimate of the cost to acquire specified goods and/or services based on each offeror’s proposed approach. The MPC is based upon an analysis of each offeror’s unique proposal in accordance with FAR 15.404-1.
The MPC may differ from the proposed cost and will reflect the Government’s best estimate of the cost that is most likely to result from the offeror’s proposal. MPC will be used in making a determination of best value. The overall evaluated MPC includes the likely cost to the Government for all cost CLINs (Basic and Option periods).
Evaluation Ratings During evaluation of each proposal, the Government will assign each subfactor a rating as shown below for both technical and past performance requirement factors listed on Page 7. A rating of unacceptable in any one of the five subfactors listed on Page 7 will constitute an overall rating of unacceptable to the requirement factor.
Technical & Past Performance Ratings
Rating Description
Good
Proposal demonstrates a thorough approach and understanding of the requirements. The approach provides significant benefits to the Government (e.g., through innovation, efficiency, or reduced risk) that go beyond the stated requirements. All requirements are met or exceeded. The narrative is clear, comprehensive, and supported by thoroughly detailed evidence and analysis.
Acceptable
Proposal demonstrates an adequate approach and understanding of the requirements. All minimum requirements are met. The narrative provides sufficient detail to demonstrate compliance and a sound approach.
Unacceptable
Proposal fails to meet one or more stated requirements and contains at least one significant weakness. The narrative is unclear, lacks sufficient detail, or does not provide a coherent approach.
4. Ombudsman. An Ombudsman has been appointed to hear and facilitate the resolution of concerns from Offerors, potential Offerors, and others for this acquisition. If resolution cannot be made by the CO, concerned parties may contact the following agency: Col Ionio Andrus, at 937-255-3008, or via email, asca@us.af.mil.
mailto:Nicole.Furlough@us.af.mil
| 2. Basis of Award: |
| 3. Requirement Factors |
| Factor 1: Technical |
| Factor 2: Past Performance |
| Factor 3: Cost/Price |
| Sub-Factor 1.2 – LRU Data Possession and Access – Submittal Requirements: |
| Sub-Factor 1.3 – Manpower – Submittal Requirements: |
| FACTOR 2: Past Performance |
| Subfactor 2.2: Production Capabilities and Experience – Submittal Requirements. |
| FACTOR 3: Cost/Price. |
| Evaluation Ratings |