Questions/Answers as of 6 Apr 11.

View the file

Other files

File Type Posted
Questions_and_Answers_FA8525-11-R-31678_12_Apr_11.pdf PDF
158.pdf PDF
Form1423_CDRL.pdf PDF
FA852511R31678_30 Mar 11.pdf PDF
EDL.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

FA8525-11-R-31678

Questions/Answers 6 Apr 11

Question: Do you have any extra detail on item -67 listed as relief valve?

Answer: The following EO should answer the -67 question.

Question: Does item -59 webbing attach to anything?

Answer: The -59 webbing at best answer from Boeing is that it is attached.

Question: Since we are quoting the -501 the identification plates should be the arrow shaped tag and not the rectangular ones. Is that correct? The parts list and the top level drawing say 17G001003-1 and 17G001005-1 which indicates the rectangular.

Answer: Yes, it is the arrow shaped one.

Question: On page 13 of the solicitation in the First Article area I understand the Dimensional portion. What is meant by Continuity, Isolation, and Material Test? If Material Test is referring to material certifications then I understand that but is there some kind of testing that needs to be performed on the raw material?

Answer: Material test is strictly the certification of the metal. Continuity is for any electrical that may be involved, the isolation does not need to be addressed on this.

Question: On drawing 17G450082 the testing for the hydraulic system is described on page 15. I called Tech support at Enerpac and read the testing instructions to him. He said that the equipment is not designed to hold those tolerances. He said that in a controlled laboratory environment that it might could be done but that the ambient air temperature could cause more than 100 psi fluctuation. Maybe the fluctuation is not a big deal as long as there is no leakage. Would we need to contract this testing out to someone?

Answer: As far as the testing goes on the hydraulics, that is your call to sub that out as long as the specs are complied with.

image1.emf

17G450082_88277_NULL_L_2008C000.pdf

April 04, 2011 12:52:16 [17G450082_88277_NULL_L_2008C0001-R_NT_0001_NULL_+_0001_1_U_N_N_N[1]]

File details come from the government source that posted it. Updated .