Copy of UHHZ170129 RFI TRACKER.xlsx
XLSX spreadsheet 27 KB Posted
- Solicitation number
- FA8501-27-RAPID-CIRCUIT-F1-170129-OTA
About this file
This is a Request for Information (RFI) Tracker documenting questions and responses regarding the replacement of Circuit F-01 transmission cable at Robins Air Force Base under the Department of the Air Force's RAPID (Robins Agile Practices for Infrastructure Development) umbrella framework.
The RFI addresses four primary areas of clarification: (1) scope confirmation that the entirety of the F-01 transmission circuit cabling requires replacement, as opposed to only portions referenced in preliminary documentation; (2) applicability of general boilerplate requirements such as plumbing, HVAC licensing, fire hydrant testing, and hazardous materials abatement, with the government confirming that only cable insulating compounds and liquids in manholes are primary concerns rather than asbestos or lead-based paint; (3) pavement, grading, and landscaping requirements related to the route crossing Taxiways E, J, D, and F, which the government confirmed are not needed given the cable is in concrete-encased duct bank; and (4) correction of NAICS and PSC classifications from 236220/Z2JZ (building construction) to NAICS 237130 (power and communication line construction), with the government confirming this revision would occur on SAM.gov but would not affect contractor eligibility or evaluation. All responses were provided on November 18, 2026, by Project Manager Brandon Williamson. The work involves replacement of 15kV, 500MCM cable throughout Circuit F-01, including removal of broken breakers, bad cable racks, installation of new bell ends on conduits, and water/dirt removal from manholes.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
RFIs
| Project Number & Title: UHHZ170129 |
| Project Manager: Brandon Williamson |
| Contracting Officer: Angela Whitley |
| Contractor: |
| RFI # | Question / Need / Issue - DO NOT FILTER | Request Date | Discipline | Response | Response Date | Responder | Status | PICTURES & OTHER | |
| 1 | Section 1.2 refers to replacing “the remaining aged portion” of Circuit F-01, which suggests some of the circuit has already been replaced. Section 3.3 states that all cable on the circuit is to be replaced “in its entirety.” The SAM.gov notice adds that deteriorated cable is to be replaced with new cable “in the Fowler Substation,” which could be read as limiting work to the substation. Please confirm the full extent of the work. If only part of the circuit is in scope, please identify the segments by manhole or switch number. | Wed 18 Nov 2026 | Scope Definition | The entirety of the F-01 transmission circuit cabling is to be replaced. | Wed 18 Nov 2026 | Brandon Williamson | |||
| 2 | Several requirements appear to be general boilerplate that may not apply to a cable replacement. Please confirm whether the following apply: | ||||||||
| • | Plumbing and HVAC licensing (1.1). | ||||||||
| • | Fire hydrant flow testing (3.1). | ||||||||
| • | Protection upon window removal (3.2). | ||||||||
| • | Building “half at a time” and occupied/unoccupied Dock phasing (3.3). | ||||||||
| • | “Construct the facility” (3.2; repeated in the notice). | ||||||||
| • | Asbestos and lead-based paint abatement (3.2; the notice also directs offerors to assume hazardous materials exist). If PCBs (cable compounds, switch oil) are the primary hazardous material concern, please state so. | Wed 18 Nov 2026 | Scope Definition | The following does not apply as it was a general template initially. Cable insulating compounds or liquid found in manholes would be the concern. | Wed 18 Nov 2026 | Brandon Williamson | |||
| 3 | The route crosses or runs along Taxiways E, J, D, and F and the runway area shown on sheet 0408. Will concrete and/or asphalt paving and striping be required as a part of this project? Will grading, grassing, landscaping, etc. be required in other areas? | Wed 18 Nov 2026 | Sheets 0211, 0212, 0309, 0408; SOO 2.2, 4 | It shouldn’t require such since cabling is in concrete encased duct bank. | Wed 18 Nov 2026 | Brandon Williamson | |||
| 4 | The notice lists NAICS 236220 (Commercial and Institutional Building Construction) and PSC Z2JZ (Repair or Alteration of Miscellaneous Buildings), while the work is underground power distribution. Will the classification be corrected (for example, to NAICS 237130, Power and Communication Line and Related Structures Construction)? Does the classification affect eligibility or the evaluation of past experience? | Wed 18 Nov 2026 | Selection / Agreement Terms | It should be revised to NAICS 237130 given it is just transmission cable work to be performed. | Wed 18 Nov 2026 | Brandon Williamson | Revised on SAM, though we don’t believe it will affect evaluation. The NAICS is just a different set of codes to classify the primary type of work . |