Example Project.pdf
PDF 479 KB Posted
- Attached to
- Delivery and Installation of Integrated Base Defense Security Systems (IBDSS) for buildings on Robins AFB
- Solicitation number
- FA850127R0003
About this file
This is a Statement of Work (SOW) for Honeywell Vindicator Intrusion Detection System (IDS) installation services at Robins Air Force Base, Georgia, with an estimated performance period of 90 days from contract award.
The contractor shall procure and install complete Vindicator IDS/Access Control Systems (ACS) across three distinct modular areas within Building 231: Lab 700 connecting to the Base Defense Operations Center (BDOC) in Building 988 via Building 228 datacenter; Labs 100-400 and Labs 500-600 (as separate systems) also connecting to BDOC via Building 288 datacenter; and the IT Lab connecting to BDOC via Building 228. Work includes installation of Vindicator Command/Control Panels (V5 or current standard), door alarms (balanced magnetic switches), motion sensors (PIR/microwave for volumetric coverage), and keypads for arming/disarming. All equipment must be Commercial Off-The-Shelf (COTS) from the Non-Nuclear IDS Configuration Management Database or approved non-CMD COTS equipment. The contractor must provide certified Honeywell engineers, network engineers, and Cisco Network Technicians for engineering and installation. Building 231 requires installation of a rack-mounted headend server system in an accredited secure area with capability to receive alarm annunciations and forward to Building 988; this portion requires NLT 90 days from award. Building 988 BDOC installation requires site survey for a monitoring system interfacing with Physical Security Information Management (PSIM) display, with documentation of connections, encryption devices, ports, and protocols.
The contractor shall conduct full testing per DAFI 31-101, DAFGM2022-01 GENADMIN, and ESE-TP-0023, with minimum 33-day testing phase requiring 72 continuous operational hours with no downtime and active 78 SFS monitoring capability. Each fiber strand must be tested for attenuation with optical power meter and light source; splice attenuation (fusion or mechanical) shall not exceed 0.3 dB loss. All cables shall be machine-labeled. AFTO Form 747 signifies project completion and system acceptance by user-level commander. Training shall be provided for operators and users (less than 10 personnel) in up to two sessions of maximum 4 hours each, with NLT 45 days after installation completion, covering system securing/disarming, badge management, troubleshooting, and IDS/ACS configuration. The contractor shall provide operational and maintenance manuals accounting for long-term system software updates without reliance on contractor-owned laptops. Warranty commences at facility turnover in accordance with base Performance Work Statement. All infrastructure, cabling, conduits, wiring, junction boxes, grounding, shielding, mounting brackets, hardware, and software must be contractor-furnished and meet EIA/TIA standards. Contractor must maintain current employee listings, comply with security training requirements per DoDM 5200.01 and DAFI 31-101, provide information for background checks, maintain CUI compliance per 32 CFR Part 2002, and retrieve identification media from departing employees. No wireless or cloud-based/internet devices are permitted. Contract Data Requirements deliverables include Training Documentation (A001), Testing Report (A002), Drawings and Schematics (A003), Warranty (A004), and AFTO 747 (A005). Site visit is mandatory on December 8, 2026 at 9:00 AM EST at Robins Visitors Center (218 Oak Ave., Warner Robins, GA 31088); questions must be submitted in writing by 4:00 PM EST on December 15, 2026 to Jessica Cobb and Kevin Hinman. Government representatives are Erickson Watkins (Primary) and William Atkinson (Alternate). Normal duty hours are Monday-Friday, 7:00 AM to 4:00 PM. No government-furnished property is provided. The contractor is responsible for hazardous materials management approval, universal waste disposal per 40 CFR Part 273, work area cleanup, fire prevention compliance per National Fire Code 30, and no-smoking policy adherence within Air Force facilities.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| PWS_IBDSS_30Sept2026.pdf | ||
| Alarm Building List.pdf | ||
| Solicitation - FA850127R0003.pdf | ||
| CDRLs Combined.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
1 | P a g e
STATEMENT OF WORK (SOW)
FOR
Honeywell Vindicator IDS Installation Services
Bldg.231
November 2026
AFLCMC ESY
220 Third Street, Bldg 231
BLDG 231
ROBINS AFB, GA 31098
2 | P a g e
1.0 DESCRIPTION OF WORK
The Contractor shall provide all labor, materials, equipment, and supervision necessary to modify the facility across 3 distinct, modular areas. This Statement of Work will be utilized, however the Base contract Performance Work Statement for Base Wide IBDSS can supersede. Should there be any conflicting details it will be resolved by the lead contracting officer, or designated government POC.
1.1 GENERAL REQUIREMENTS
• Base Requirement (Bldg 231 Lab 700): The contractor shall procure and install all
Vindicator panels, sensors, and all supporting infrastructure (e.g., comm and electrical). The system will connect bldg. 231 Lab 700, to Base Defense Operations
Center (BDOC) -bldg.988, via bldg. 228 (Datacenter). The contractor will provide the customer with a hardware and software list (CDRL A005, AFTO 747).
• Requirement 2 (Bldg 231 Labs 100-400 and Labs 500-600): The contractor shall procure and install all Vindicator panels, sensors, and all supporting infrastructure
(e.g., comm and electrical). The system will connect Bldg. 231 Labs 100-400 and Labs
500-600, to Base Defense Operations Center (BDOC) -bldg.988, via bldg. 288
(Datacenter). The contractor will provide the customer with a hardware and software list (CDRL A005, AFTO 747). Labs 100-400 and Labs 500-600 are separate spaces and will need to have their own system not connected to each other.
• Requirement 3 (Bldg 231 IT Lab): The contractor shall procure and install all
Vindicator panels, sensors, and all supporting infrastructure (e.g., comm and electrical). The system will connect bldg. 231 IT Lab, to Base Defense Operations
Center (BDOC) -bldg.988, via bldg. 228 (Datacenter). The contractor will provide the customer with a hardware and software list (CDRL A005, AFTO 747).
• The contractor will provide a certified engineer, necessary supporting network engineer as well as a certified Vindicator Installer and Cisco Network Technician to complete the engineering and installation of all system components.
• All equipment will require testing. The following instructions MUST be adhered to:
Department of Air Force 31-101, Department of Air Force 31-101 DAFGM2022-01
GENADMIN, ESE-TP-0023, DAFI 31-220 and related standards.
• The contractor shall provide all ancillary equipment, materials, and infrastructure upgrades necessary to support system operations.
• The contractor shall ensure that the system delivered under this contract consists of
3 | P a g e
Commercial Off The Shelf (COTS) equipment from the Non-Nuclear, Intrusion Detection
System (IDS) Configuration Management Database (CMD)and/or, quality non-CMD COTS
IDS equipment that has been proven by the contractor. Any non-CMD COTS IDS equipment must be approved by the Government prior to purchase.
1.2 SPECIFIC REQUIREMENTS
The contractor shall install a complete and functional Vindicator IDS/ACS to include:
• Vindicator Panel: [1] Vindicator Command/Control Panel (V5 or current base standard).
• Door Alarms: [2] Balanced Magnetic Switches (BMS) for the main personnel door and the woven wire cage door.
• Interior Surveillance: [2] Motion sensors (PIR/Microwave) providing full volumetric coverage of the interior cage area.
• Arming/Disarming: [1] Keypad for arming/disarming the secure zone.
*The above is not an all-inclusive supply list
The contractor shall meet the following annunciation requirements:
• The Vindicator Command and Control (VCC) shall be installed in accordance with
OEM instructions and Section 4 ESE-SIT-0001.
• The VCC shall provide error detection, line supervision, and system control continuously.
• The VCC shall display the following:
▪ The status either automatically as changes occur, or when manually initiated by the operator.
▪ The highest priority alarm, according to user-defined parameters, in the queue regardless of arrival sequence.
▪ The alarm type, physical location, and sector or zone.
▪ At a minimum display the highest five (5) alarms text in the queue.
▪ Graphics for all alarms received.
▪ Alarm priority as programmed by the system administrator.
▪ Up to five (5) simultaneous alarms within (5) seconds.
• The VCC shall have 100% tamper detection and the capability for a duress alarm, 100% correct annunciation of alarms.
• The VCC shall archive and store all status changes and operator actions including
4 | P a g e maintenance periods, alarms, and sensor access attempts.
• Internal storage shall have a minimum 30-day capacity.
• The VCC shall have a re-initialization time of less than 10 minutes.
• Text, graphics indications, and total system status shall update automatically when changes occur or when requested by the operator.
• Visual indications shall include access/secure/maintenance/alarm conditions, video loss, line supervision status, power source in use, and self-test indications, using text and graphics.
• The VCC shall conduct system tests and diagnostics which are automatically and randomly generated every 6 to 8 hours and/or manually generated by the operator at any time.
• The VCC shall provide unique audible tones for sensor alarm conditions and other changes in the status.
• No wireless devices.
• No cloud based or internet devices.
• The IDS and components shall be installed, configured and maintained in compliance with DoD Manual 5200.01, Volume 3.
1.3 Building 231 Requirements
• The contractor shall complete a site survey to provide and install a Vindicator rack mounted head end server system in the accredited secure area as identified by the customer. This system shall encompass all requirements to receive all alarm annunciations from Vindicator IDS systems distributed on Robins AFB and ability to forward alarm annunciations to building 988 (BDOC).
• The contractor will provide the government with the topology of the IDS to include servers, switches, etc. (CDRL A005, AFTO 747).
• The contractor will provide a certified engineer and necessary supporting network engineers to complete this installation. This portion of the contract will have a period of performance of NLT 90 days from date of award.
1.4 BUILDING 988 BDOC DATA AND OPERATIONS ROOMS:
• The contractor will complete site survey for best installation of a monitoring system that will have the ability to interface with a Physical Security Information Management
(PSIM) display in BDOC and submit documentation of the connection between building
231 and the BDOC to include encryption devices used and ports and protocols (CDRL
5 | P a g e
A003, Drawings and Schematics).
• The contractor will verify full connectivity and operation from building 231 to building
988 via building 228.
• The contractor will provide a certified engineer and necessary supporting network engineers to complete this installation.
1.5 TRAINING:
A training session will be provided for the operators and users of the Vindicator system in building 231. Each training session, if multiple sessions (no more than 2) are required, should not take longer than 4 hours. The contractor will coordinate closely with the
Government on scheduling for various shifts, etc. Total personnel to be trained will be less than 10. This portion of the contact will have a period of performance of NLT 45 days after installation completion. Ensure users are trained in how to secure/disarm the system, create/add/remove badges, troubleshoot and manage IDS and ACS systems, program and configure Vindicator IDS system respectively.
1.6 OPERATIONAL AND MAINTENANCE MANUAL:
Maintenance of system should be accounted for prior to installation. The government cannot accept the use of a company owned laptop to update the system over the long term. This should be accounted for when considering what will be required for system software updates and information transfer.
1.7 WARRANTY:
• The contractor shall warranty in accordance with base Performance Work Statement. The full duration of such warranties shall commence at the time of facility turnover. The contractor shall track, by item and serial number, manage and enforce open warranties on all failed items.
• The contractor shall provide copies of all warranties for contractor furnished equipment and materials delivered under this contract.
1.8 TESTING AND GOVERNMENT ACCEPTANCE:
• The contractor will complete full testing as prescribed in DAFI 31-101, DAFGM2022-01
GENADMIN, and ESE-TP-0023.
• Contractor will coordinate closely with the Government on scheduling and testing. The contractor shall perform contractor Verification Testing of the system and subsystems to include information assurance verification and stability testing. (CDRL A002, Testing
6 | P a g e
Report)
• Contractor will obtain project completion signoff from the Government at the end of the successful test. The alarm must be functional for 72 hours and 78 SFS must have been able to actively see the current alarm state and not experience any down time etc.
The total time for the testing phases is a minimum of 33 days. If failures occur, then the contractor will fix the errors and restart the testing phases. If no failures occur, then there will be no reason to restart the testing phases. The contractor will provide the customer with a copy of all testing documentation IAW IBDSS SSP Annex for Vindicator, signed July 01, 2024 (CDRL A002 Testing Report, CDRL A005, AFTO 747).
• Each fiber strand shall be tested for attenuation with an optical power meter and light source. Cable length shall be verified using sheath markings. If splices are used, splice attenuation shall be verified with an Optical Time Domain Reflectometer (OTDR). Fusion or mechanical splices shall not have a loss of more than 0.3 dB. Any dB loss higher than .3 dB will require re-splicing by the contractor until dB loss is within parameters. All installed cables should be clearly machine labeled.
• AFTO FORM 747 is used to signify the completion of the project and acceptance of the installed system by the user. The completion of this form means the system has been tested and accepted as installed, and all noted exceptions corrected by the party responsible for the satisfaction of the signee. The decision to accept the successful completion of the test phase is a commander-level decision and should be completed by the appropriate commander at a given location.
1.9 INFRASTRUCTURE AND TOOLS:
• The contractor shall furnish and install all necessary infrastructure and incidentals required within the facility to support installation, testing and operation including, but not limited to, cabling, tools, conduits, wiring, interior junction boxes, grounding, shielding, foundations and supports, mounting brackets, environmental protection barriers, lockable, security bolts or screws, tamper resistant screws, hardware, software and any other equipment, parts, and items required to complete the installation and turnover to the user.
• The contractor shall furnish and install the necessary media (cable, fiber, etc.) needed for full connectivity and operation from building 231 to building 988 via building 228.
• The contractor will be responsible for material acquisition, shipment, staging and installation of all parts necessary to install and test badging headend in accordance with engineering and installation industry standards. All portions of this contract require adherence to all applicable EIA/TIA standards, unless otherwise specified and approved
7 | P a g e by the 78th Communications Squadron representative.
2. Contract Data Requirements List (CDRL):
Document Identifier
DID Title SOW Reference
A001 DI-MGMT-81862 Training Documentation 1.5
A002 DI-QCIC-80553 Testing Report 1.8
A003 MIL-HDBK-863A Drawings and Schematics 1.3
A004 DI-SESS-81639 Warranty 1.7
A005 MIL-STD-471 AFTO 747 1.8
A006 DI-SAFT-81563 Accident Incident Report PWS Dated 30 Sept 2026 (5.5)
A007 DI-SAFT-82313 Environmental, Safety, and Occupational Health (ESOH) Plan
PWS Dated 30 Sept 2026 (5.5)
2.1 QUALITY and Receipt of CDRL DELIVERABLE:
Reference Performance Work Statement paragraph 4.7.1 and 4.7.2 for quality and receipt of CDRL deliverable parameters.
3. PLACE OF PERFORMANCE:
Installation of Honeywell Vindicator IDS will be installed at the following location on Robins AFB:
220 Third Street
BLDG 231
ROBINS AFB, GA 31098
3.1 SITE VISIT: Site visit is mandatory for contractors and will be coordinated as outlined in the base contract as mentioned in section 1.0.
William Atkinson and Erickson Watkins will meet all contractors at the Visitors Center on the designated day and time. Contractors are required to provide identification. 2 forms of ID are required (Ie: driver's license, social security card…..), driver's license, and current vehicle registration.
Visitors Center address:
8 | P a g e
218 Oak Ave.
Warner Robins, GA 31088
Government Representative:
William Atkinson, 478-926-5987, william.atkinson.5@us.af.mil Erickson Watkins, 478-222-3891, erickson.watkins@us.af.mil
Site visit will be conducted on 8 December 2026 at 9am EST.
No remarks, explanations, or answers provided during site visit shall qualify or amend the terms of the RFP. All questions arising from the site visit must be:
• Submitted in writing by 4pm EST on 15 Dec 2026.
• Submitted to Jessica Cobb – jessica.cobb.3@us.af.mil and Kevin Hinman -kevin.hinman.2@us.af.mil
Any changes to the RFP will be issued via a formal amendment.
4. GOVERNMENT FURNISHED PROPERTY:
The Government will not provide any property, equipment, parts, or material to the Contractor as part of the contract.
5. GOVERNMENT REPRESENTATIVES:
The Primary and Alternate Government Representative are the points of contact through which all contractor-provided services will be requested and accomplished for their organization. Government Representatives will not supervise the Contractor, and they are not empowered to make any contractual commitments or to authorize any contractual changes on the Government’s behalf.
The following individuals will serve as Government Representatives:
Government Representative Primary
Government Representative Alternate
Erickson Watkins William Atkinson
Kevin Hinman Jessica Cobb
6. NORMAL HOURS OF OPERATION.
The Government’s normal duty hours are five days per week, Monday through Friday, from
7:00 AM to 4:00 PM.
6.1 RECOGNIZED HOLIDAYS.
Holidays and Facility Closings: Contractor/subcontractor personnel shall observe holidays and mailto:william.atkinson.5@us.af.mil mailto:erickson.watkins@us.af.mil mailto:jessica.cobb.3@us.af.mil mailto:kevin.hinman.2@us.af.mil
9 | P a g e facility closings as authorized for government personnel. Contractor/subcontractor personnel shall only be permitted access to Government facilities when government personnel are present.
7. PERIOD OF PERFORMANCE.
The Government estimates the period of performance for this project to be 90 days from the contract award date. The Government understands that the period of performance may change due to potential long-lead time for required parts and components. Any changes to the period of performance or terms and conditions can only be approved by the Contracting Officer (CO).
7.1 LISTING OF EMPLOYEES. The contractor shall maintain a current listing of employees.
7.1.1 SECURITY TRAINING.
• Training must be conducted in accordance with DoDM 5200.01, DoD Information Security
Program, and DAFMAN 16-1404, Information Security Program, as well as DoDI 5200.48 /
DAFI 16-1403 for Controlled Unclassified Information (CUI). Contractor personnel who require unescorted access to or work within Air Force controlled or restricted areas must comply with and complete training in accordance with DAFI 31-101, Integrated Defense, applicable installation security directives, and local Base Operating Instructions (OIs). This standard language applies to contractor employees performing duties within Government-controlled installations, facilities, or restricted areas.
• The contractor shall comply with all applicable installation/facility access and local security policies and procedures, which may be obtained from the Contracting Officer’s
Representative (COR). The contractor shall also provide all information required for background checks to meet installation access requirements to be accomplished by the local installation’s Security Forces, Director of Emergency Services or local Security
Office.
• The contractor shall ensure compliance with all personal identity verification requirements as directed by DoD, HAF and/or local policy. Should the Force Protection
Condition (FPCON) change, the Government may require changes in contractor security matters or processes. For Contractors that do not require CAC but require access to a
DoD Facility and/or Installation, Contractor and all associated sub-contractors employees shall comply with adjudication standards and procedures using the National
Crime Information Center Interstate Identification Index (NCIC-III) and Terrorist
Screening Database (TSDB) (DODIO 2000.16V1_DAFI 31-145, DAFI 31-101 and DODM
5200.08v3_DAFMAN 31-101v3), applicable installation, facility and area commander installation/facility access and local security policies and procedures (provided by government representative), or, at OCONUS locations, in accordance with status of forces agreements and other theater regulations.
10 | P a g e
7.1.2 RETRIEVING IDENTIFICATION MEDIA.
The contractor is responsible for retrieving all identification media from employees who depart for any reason before the contract expires, e.g. terminated for cause, retirement, etc. The contractor shall return retrieved items to the Security Forces Pass and Registration
Office.
7.1.3 WEAPONS, FIREARMS, AND AMMUNITION.
Contractor employees are prohibited from possessing weapons, firearms, or ammunition, on themselves or within their contractor-owned vehicle or privately- owned vehicle while on Robins Air Force Base.
7.1.4 Controlled Unclassified Information (CUI).
The contractor shall comply with 32 CFR Part 2002 on Controlled Unclassified Information.
This regulation sets policy and procedures for the disclosure of records to the public and for marking, handling, transmitting, and safeguarding CUI material.
7.1.5 PHYSICAL SECURITY.
The contractor shall be responsible for safeguarding all Government property and controlled forms provided for contractor use. At the end of each work period, all
Government facilities, equipment, and materials shall be secured.
7.1.6 CONTROLLED/RESTRICTED AREAS. (IF APPLICABLE)
The contractor shall implement local base procedures for entry to Air Force controlled/restricted areas where contractor personnel will work. Contractors will be escorted by the owner/user into all controlled/restricted areas.
8. SPECIAL QUALIFICATIONS:
The contractor shall provide a certified Honeywell Engineer and Program manager for installation of equipment in building 228 (data center), building 988, and ensure connectivity with building 231.
9. HAZARDOUS MATERIALS:
The contractor shall have approval from the Hazardous Material Management Program
(HMMP) team prior to purchasing, handling, using, and storing any chemicals, solvents, lubricants, and other products that require Material Safety Data Sheets (MSDS).
o The contractor shall identify these materials on a contractor Hazardous Material
Inventory list.
11 | P a g e o The contractor shall provide this inventory list and 1 copy of the MSDS for each item to the HAZMAT Office for review and HMMP approval prior to any chemicals being brought onto Robins AFB, or within 15 days of the start of this contract.
o This inventory is also used by the contractor to annually report hazardous material usage. By 30 January of each calendar year, the contractor shall submit
2 copies of the completed contractor Hazardous Material Inventory list to 78
CES/CEV.
o The contractor shall maintain 1 copy of the MSDS for each hazardous material line item used within the work center.
• The generation of hazardous waste is not expected from this contract. It is the responsibility of the contractor to determine if hazardous waste is generated from contractor operations. 78 CES/CEV will assist with determination if requested by the contractor. In the event hazardous waste is generated, disposal of hazardous waste shall be handled by the Government. The generation of universal waste (including but not limited to mercury containing light fixtures) is probable under this contract. The contractor shall manage and dispose of universal waste in accordance with the base
Hazardous Waste Management Plan and 40 CFR Part 273, Universal Waste Rules.
• The contractor shall use the environmentally safe products when available. The contractor shall submit justification for the use of any Class I Ozone Depleting
Substances (ODS) as part of the afore mentioned contractor Hazardous Material
Inventory submittal process. The justification shall include at a minimum:
(1) the name of the ODS; (2) the ODS quantity to be used; (3) the frequency of ODS usage; (4) the purpose for using the ODS; and (5) reasons why the ODS cannot be substituted. The contractor shall request waivers for usage of any ODS and receive approval from the Contracting Officer in writing prior to using any ODS.
• The contract manager and alternate, as well as employees who handle hazardous and/or universal waste shall be required to attend Government-conducted
Hazardous Waste Training. The class will be taught at Robins Air Force Base. There will be no charge to the contractor for the training. The contractor shall contact 78
CES/CEV for such training. The contractor shall be required to provide proof that employees have attended the course on an annual basis. The Government may conduct a “no-notice” environmental inspection at any time.
10. CLEAN UP:
The contractor shall keep interior and exterior of the contractor’s office/maintenance location and all work areas and storage areas free from accumulation of waste material
12 | P a g e and rubbish. Upon completion of the job, the contractor shall leave the work area and surrounding premises in a clean and neat condition.
11. FIRE PREVENTION:
The contractor is responsible for following fire prevention practices and procedures.
The contractor shall provide approved storage facilities meeting National Fire Code 30, Flammable and Combustible Liquids Code, requirements for storage of flammable materials.
12. NO SMOKING POLICY:
The contractor and employees shall comply with policies stating smoking is prohibited within any Air Force Facility and use designated outdoor smoking areas.
| 1.0 DESCRIPTION OF WORK |
| 1.1 GENERAL REQUIREMENTS |
| 1.2 SPECIFIC REQUIREMENTS |
| 1.3 Building 231 Requirements |
| 1.4 BUILDING 988 BDOC DATA AND OPERATIONS ROOMS: |
| 1.5 TRAINING: |
| 1.6 OPERATIONAL AND MAINTENANCE MANUAL: |
| 1.7 WARRANTY: |
| 1.8 TESTING AND GOVERNMENT ACCEPTANCE: |
| 1.9 INFRASTRUCTURE AND TOOLS: |
| 2. Contract Data Requirements List (CDRL): |
| 3. PLACE OF PERFORMANCE: |
| Visitors Center address: |
| Government Representative: |
| 4. GOVERNMENT FURNISHED PROPERTY: |
| 5. GOVERNMENT REPRESENTATIVES: |
| 6. NORMAL HOURS OF OPERATION. |
| 6.1 RECOGNIZED HOLIDAYS. |
| 7. PERIOD OF PERFORMANCE. |
| 7.1.1 SECURITY TRAINING. |
| 7.1.2 RETRIEVING IDENTIFICATION MEDIA. |
| 7.1.3 WEAPONS, FIREARMS, AND AMMUNITION. |
| 7.1.4 Controlled Unclassified Information (CUI). |
| 7.1.5 PHYSICAL SECURITY. |
| 7.1.6 CONTROLLED/RESTRICTED AREAS. (IF APPLICABLE) |
| 8. SPECIAL QUALIFICATIONS: |
| 9. HAZARDOUS MATERIALS: |
| 10. CLEAN UP: |
| 11. FIRE PREVENTION: |
| 12. NO SMOKING POLICY: |