309 MXSG SOW - Vandenburg Crane - Final (10-19-26).docx

DOCX document 135 KB Posted

Attached to
Vandenberg Crane Replacement
Solicitation number
FA8227-27-Q-1000
Issued by

About this file

This is a Statement of Work (SOW) for the removal of an existing indoor overhead crane system and the engineering, fabrication, delivery, installation, testing, and commissioning of a new underhung single-girder bridge crane system at Vandenberg Space Force Base (VSFB) Building 9320. The scope is limited to non-critical lifting operations, with operator training, daily inspections, and routine crane operations performed by Government personnel. The new crane system shall consist of one under-running single-girder bridge rated for 4-ton capacity with CMAA Class D service classification, two independently operated 2-ton capacity electric wire rope hoists mounted on trolleys with integrated system controls, and a complete electrical and control system including variable frequency drives (VFDs), pendant and backup radio remote controls, emergency stop capabilities, and overload protection. The hoist system must meet ASME HST-4 H4 duty classification with nominal speeds of 15 FPM for hoists and 50 FPM for trolleys, dual-reeved configuration with equalizer sheaves, and micro-speed positioning at 25 percent nominal speed. The bridge end trucks shall operate at 95 FPM with AC motor brakes and manual hand-release mechanisms, designed to prevent derailing during seismic events per SSCMAN 91-710 requirements. The electrical system requires 460 VAC, 3-phase, 60 Hz power with NEMA Type 12 steel control enclosures, fail-safe hardwired emergency stop circuits, and loss of radio frequency automatic shutdown capability.

The contractor must submit twelve Contract Data Requirement Lists (CDRLs) including a Crane Removal Plan (30 calendar days prior to removal), PE-stamped structural calculations and drawings (initial submission 30 calendar days prior to fabrication), Commercial O&M Manuals (30 calendar days prior to turnover), Electrical Documentation and Schematics, Spare Parts List (within 15 calendar days of award), Certificates of Compliance, Test Plan for proof-load testing (30 calendar days prior to testing), Field Test Report and Crane Certification (within 10 calendar days of test completion), Nondestructive Examination (NDE) Plan (30 calendar days prior to testing), Preventive Maintenance and Inspection Plan (30 calendar days prior to turnover), Integrated Master Schedule (15 calendar days after award with monthly updates), and Site-Specific Safety Plan (15 calendar days prior to on-site work). The contractor shall perform proof-load testing at 125 percent of rated capacity with NDE on safety-critical welds and components, and provide a minimum one-year comprehensive warranty. Performance is at VSFB Building 9320, California, during normal hours of Monday through Thursday 0600-1630, excluding federal holidays. The Government will provide facility access, working space with utilities, and existing facility drawings, with the contractor responsible for field verification of all critical dimensions and structural conditions, compliance with all applicable industry standards (CMAA, ASME B30 series, NFPA 70, OSHA, California Cal-OSHA for cranes over 3 tons), and adherence to AFMAN 91-203 safety standards and SSCMAN 91-710 seismic requirements.

View the file

Other files

File Type Posted
15853 - Vandenberg Crane Replacement Combo.docx DOCX document
CDRL - A005.pdf PDF
CDRL - A009.pdf PDF
CDRL - A012.pdf PDF
CDRL - A002.pdf PDF
CDRL - A003.pdf PDF
CDRL - A004.pdf PDF
15853 - Vandenberg Crane Replacement Combo.docx DOCX document
CDRL - A013.pdf PDF
CDRL - A011.pdf PDF
CDRL - A006.pdf PDF
CDRL - A010.pdf PDF
CDRL - A008.pdf PDF
CDRL - A001.pdf PDF
CDRL - A007.pdf PDF
Show all 15

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

statement of work (SOW)

Vandenberg Building 9320 Hoist/Trolly/Crane Replacement

U.S AIR FORCE

309th Maintenance Support Group (MXSG)

Mason Figueroa

Final

10/19/2026

TABLE OF CONTENTS

1DESCRIPTION OF SERVICES1
2APPLICABLE DOCUMENTS1
3Requirements3
4Service summary11
5CDRL SUMMARY12
6Quality Assurance13
7ADDITIONAL REQUIREMENTS14
8GENERAL INFORMATION14
Appendix A – ACRONYMS AND ABBREVIATIONS17
Appendix B – Crane compliance matrix (sscman91-710v318

Vandenberg Building 9320 Hoist/Trolly/Crane Replacement i

DESCRIPTION OF SERVICES

Scope This Statement of Work (SOW) defines the tasks required for the removal of the existing indoor overhead crane system and the engineering, fabrication, delivery, installation, testing, and commissioning of a new underhung single-girder bridge crane system with two independently operated trolley-mounted hoists in Building 9320 at Vandenberg Space Force Base (VSFB), California. This SOW applies to non-critical lifting operations only. Operator training, daily inspections, and routine crane operations are performed by Government personnel and are outside the scope of this contract.

Existing Conditions The existing facility system consists of an indoor overhead crane, hoists, runway rails, electrification, and associated controls. The Government will provide existing facility drawings and available runway documentation for reference. Technical requirements for contractor on-site field verification of all critical dimensions and structural conditions are detailed in Section 3.

APPLICABLE DOCUMENTS

Government / DoD Documents.

The following specifications, standards, and handbooks of the most recent version listed and any other applicable codes form a part of this SOW to the extent specified in Section 3 of this document:

AFMAN 91-203, Air Force Occupational Safety, Fire and Health Standard, dated 23 August 2022.

AFSPCMAN 91-710, Range Safety User Requirements, dated 1 July 2016.

Space Systems Command Standard SSCMAN 91-710, Volume 3, Chapter 6, “Cranes and Hoists,” dated 15 September 2021.

SSCMAN 91-710, Volume 5, Attachment 2, “Crane and Hoist Data Requirements,” dated 15 September 2021.

Industry Standards:

The following industry specifications, standards, and codes of the most recent version listed and any other applicable codes form a part of this SOW:

CMAA Specification No. 74, Specifications for Top Running & Under Running Single Girder Electric Overhead Traveling Cranes, 2020 Revision.

ASME B30.17, Cranes and Monorails (With Underhung Trolley or Bridge), 2026 Edition.

ASME B30.16, Overhead Underhung and Stationary Hoists, 2022 Edition.

ASME B30.10, Hooks, 2022 Edition.

ASME HST-4, Performance Standard for Overhead Electric Wire Rope Hoists, 2020 Edition.

NFPA 70, National Electrical Code (NEC), 2023 Edition.

OSHA 29 CFR Part 1910, Occupational Safety and Health Standards, current edition.

NEMA 250, Enclosures for Electrical Equipment (1000 Volts Maximum), 2020 Edition.

NEMA ICS 6, Industrial Control and Systems: Enclosures, 2020 Edition.

AWS D1.1/D1.1M, Structural Welding Code - Steel, 2020 Edition.

AISC 360-20, Specification for Structural Steel Buildings, 2020 Edition.

Order of Precedence.

In the event of a conflict between this SOW and the references cited herein, the more stringent technical, safety, code, or regulatory requirement shall apply unless a written waiver, or exemption is approved by Contracting Officer or the appropriate Government authority.

Nothing in this SOW shall be interpreted as waiving, reducing, or superseding applicable OSHA, AFMAN 91-203, SSCMAN 91-710, ASME, CMAA, NEC/NFPA 70, California code, or other mandatory requirements unless a specific written exemption has been obtained from the Contracting Officer and the responsible technical authority.

Requirements New Crane System General Description The contractor shall design, fabricate, and install a complete indoor under-running, single-girder bridge crane system serving the existing runway in Building 9320. All specified ratings are in U.S. short tons (2,000 pounds = 1 ton). The crane system shall include:

One under-running single-girder bridge rated for a capacity of 4 tons, CMAA Class D service classification, designed for indoor, non-critical, industrial service.

Two cross-mounted 2 ton capacity electric wire rope hoists mounted on trolleys, configured for independent lifting of non-critical loads.

Integrated system controls that mechanically and electrically limit the combined simultaneous lifting load of both hoists to ensure the total capacity of the bridge and runway is not exceeded under any operating condition.

Hoist and Trolley Performance The contractor shall ensure each hoist and trolley meets the following performance criteria:

Rated Capacity: 2 tons per hoist.

Lift: Minimum of 36 feet, or sufficient lift for the building and application as verified by field measurement.

Hoist Speed: Nominal speed of 15 Feet Per Minute (±10%) (FPM) utilizing Variable Frequency Drive (VFD) controls, including a micro-speed positioning function operating at 25 percent of nominal speed.

Trolley Speed: Nominal speed of 50 FPM (±10%) utilizing VFD controls, including a micro-speed positioning function operating at 25 percent of nominal speed.

Duty Class: Hoists shall meet ASME HST-4 H4 duty classification for high-volume industrial handling.

Hooks and Suspension: Hooks shall comply with ASME B30.10 and incorporate spring-loaded safety latches. Lower hook blocks shall allow hook to swivel to minimize rope twist and load rotation.

Reeving: Hoists shall be dual-reeved with equalizer sheaves in accordance with SSCMAN 91-710, Volume 3, paragraphs 6.3.1.11 and 6.3.5.1.8.

Bridge and End Trucks The contractor shall design, fabricate, and assemble the bridge crane structure in accordance with the following:

Bridge span, wheelbase, and end truck dimensions shall be matched to the existing runway geometry as verified by the contractor's field measurements.

The bridge girder shall be rated for a 4 tons capacity, under-running configuration, CMAA Class D service, designed in accordance with CMAA Specification No. 74 and ASME B30.17.

End trucks shall be driven by dual-motor VFDs with a nominal travel speed of 95 FPM (±5 FPM), incorporating AC motor brakes with manual hand-release mechanisms.

The bridge structure, end trucks, and runway attachments shall be detailed and built to prevent the crane from derailing or walking along the tracks during seismic events, in accordance with the seismic hazard provisions of SSCMAN 91-710, Volume 3, paragraph 6.3.4.2.2.

Electrical and Controls The contractor shall provide a complete crane control system, including:

Power Supply: Incoming power feed from disconnect is 460 Volts AC (VAC), 3-phase, 60 Hertz (Hz), with 115 VAC control power circuits. The contractor shall run power from disconnect on.

Control Enclosures: Enclosures shall be NEMA Type 12 steel control enclosures. If alternative environmental conditions require NEMA Type 3R enclosures, the contractor shall submit a technical justification to the Contracting Officer for written approval prior to procurement.

Drives: Solid-state VFDs shall control all crane motions (hoist, trolley, and bridge) and shall include line reactors, output reactors, dynamic braking resistors, and over-current protective devices.

Motors: All motors shall be inverter-duty rated with Class H insulation and Class B temperature rise, incorporating integral AC disc brakes with manual hand-release levers.

Pendant and Radio Controls: The contractor shall provide a primary pendant control station and a backup radio remote control system. Both control systems shall include functions for: mainline emergency stop (E-stop), Hoist 1 hoist/lower, Hoist 2 hoist/lower, Trolley 1 & 2 travel, Bridge travel, able to support 2 speed operations, warning horn, and auxiliary safety functions. The pendant station shall be physically suspended from a separate track to run parallel to the bridge girder.

Control Circuit Design: Control circuits shall incorporate electrical and mechanical interlocking to prevent simultaneous opposing commands, provide fail-safe stop functions, and comply with ASME B30.17 (Monorails and Underhung Cranes), ASME B30.16 (Overhead Underhung and Stationary Hoists), and NFPA 70. Over-travel limit switches and E-stop circuits shall be hardwired directly to the mainline contactor and shall not rely on programmable logic.

Safety and Lockout Features: The main electrical control panel shall incorporate a physical lockable disconnect switch and a keyed lockout switch to prevent unauthorized operation. Loss of radio frequency (RF) signals shall automatically trigger a hardwired emergency shutdown, reverting the crane to a safe, motion-inhibited state.

Overload Protection Each hoist shall incorporate an integral, non-adjustable mechanical or electronic overload protection system in accordance with ASME B30.16.

The overload protection system shall interrupt hoisting power when the load exceeds 110 percent (+0% / -5%) of the rated capacity of the individual hoist (2.5 tons), while permitting controlled lowering operations.

Overload settings shall be sealed and configurable only by qualified crane maintenance personnel following manufacturer instructions. Field adjustment by crane operators is prohibited.

The hoist control system shall support torque-proving functions and adjustable overload test settings, including keyed overrides and load weight readouts, to facilitate required proof-load testing.

Safety Features The crane system shall include:

Two Independent Upper Hoist Limits: A primary control-circuit upper limit switch that stops upward motion (automatic reset via reversing control) and a secondary final upper limit switch that mechanically interrupts power to the hoist drive motor, requiring a keyed manual reset.

Travel Limits: Hardwired bridge and trolley travel limit switches to prevent the crane and hoists from striking physical end stops.

Warning Horn: An audible, operator-controlled horn (minimum 90 dBA at 10 feet) to warn personnel prior to and during load movement.

Travel Strobe: A red strobe light mounted on the bridge that automatically activates and flashes whenever the bridge or trolley is in motion.

Main Disconnect: A lockable, manual main power disconnect switch accessible from ground level.

Capacity and Warning Signage: Sized and lettered capacity placards on both sides of the bridge girder and hoists, and warning safety decals on the operator controls in accordance with ASME B30.17, ASME B30.16, and AFMAN 91-203.

Environmental and Finish All components of the crane system shall be designed for indoor, non-hazardous industrial environments.

Hoists and trolleys shall be painted safety yellow. The bridge girder and end trucks shall be finished with an industrial-grade rust-inhibitive primer and safety yellow polyurethane topcoat.

No paint, coatings, or primer shall be applied to wire ropes, hoist hooks, crane wheels, or cable sheaves.

Removal of Existing Equipment The contractor shall execute the safe removal of the existing crane system:

Removal Plan: The contractor shall submit a comprehensive Crane Removal Plan (CDRL A001, DI-MISC-80508B) to the 309th MMXG EN (309th Missiles Maintenance Engineer) and COR for review and approval 30 calendar days prior to commencing any physical removal activities. The removal plan shall detail the rigging procedures, crane dismantling sequence, lockout/tagout (LOTO) protocols, fall protection measures, and hazardous material handling.

Outage Coordination: The contractor shall coordinate all facility access and outage windows in writing with the Contracting Officer’s Representative (COR) 14 calendar days prior to the outage to minimize mission impacts.

Demolition Work: The contractor shall disconnect, disassemble, and remove the existing bridge crane, end trucks, hoists, trolleys, control panels, and existing electrification systems not designated for reuse.

Component Disposal: The contractor shall palletize and stage all removed crane components at the Government-designated storage yard located within Building 9320. The contractor shall dispose of non-reusable materials in accordance with the Government-approved Disposal Plan.

Site Housekeeping: The contractor shall clean the work area at the end of each workday, removing all debris, dust, and tools to maintain a safe environment for ongoing Government operations.

Installation of New Equipment.

Structural Verification: The contractor shall verify and analyze the load-bearing capacity of the existing runway beams, building supports, and connections to ensure structural adequacy for the new crane wheel loads, lateral thrusts, impact factors, and seismic forces.

Structural Calculations: The contractor shall perform structural calculations and design for any modified or new supports, anchorage, bracing, and end stops. All structural calculations and drawings shall be prepared, signed, and stamped by a Professional Engineer (PE) licensed in the State of California (CDRL A002, DI-SESS-81000F).

· Initial Submission: The contractor shall submit the complete, signed and PE-stamped initial design package to the 309th MMXG EN and COR for government review and written approval no later than 30 calendar days prior to the start of any physical fabrication or material procurement.

· Final Submission: The contractor shall incorporate all Government comments and deliver the final, certified as-built structural package with the system turnover package to the 309th MMXG EN and COR.

Government Approval: The contractor shall submit all PE-stamped calculations and drawings (CDRL A002) to the Civil Engineering and Range Safety offices for review and written approval prior to fabrication or installation of any permanent structural modifications. The Government’s review of the initial submission will be completed within 14 calendar days of receipt. Any required modifications identified during this review shall be corrected and resubmitted by the contractor at no additional cost to the Government Mechanical Installation: The contractor shall install the new end trucks, bridge girder, hoists, and trolleys in accordance with manufacturer specifications and approved shop drawings. All structural connections shall utilize Grade 5 or better load-bearing bolts and fasteners assembled with medium-strength thread-locking compound.

Electrification and Controls: The contractor shall install the runway conductor bars, bridge festoon systems, and route all control wiring between panels, motors, limit switches, and safety devices. The contractor shall implement electrical grounding and bonding in strict accordance with NFPA 70.

Alignment and Calibration: The contractor shall align, level, and square the bridge girder to the runway within CMAA Specification No. 74 tolerances. The contractor shall calibrate and adjust all hoist and travel limit switches and braking devices prior to load testing.

Documentation Deliverables The contractor shall deliver the following technical documentation in electronic format (editable CAD native files like .DWG/.DXF and searchable .PDF) to the 309th MMXG EN and COR.

Commercial O&M Manuals: Operating and maintenance manuals for the bridge, end trucks, hoists, trolleys, and control drives (CDRL A003, DI-TMSS-80527D), due 30 calendar days prior to final system turnover.

Electrical Documentation: Single-line power diagrams, detailed control schematics with terminal numbers, and PLC I/O lists (CDRL A004, DI-SESS-82351A). Initial submittal due 30 calendar days prior to fabrication; final as-built set due at turnover.

Mechanical and Structural Drawings: General arrangement drawings showing crane clearances, runway details, and PE-stamped structural designs (CDRL A002, DI-SESS-81000F). Initial submittal due 30 calendar days prior to fabrication; final as-built set due at turnover.

Spare Parts List: Recommended spare parts list with OEM part numbers, descriptions, and recommended quantities (CDRL A005, DI-PSSS-80134B), due within 15 calendar days of contract award.

Field Load Test and Commissioning Test Certificates: The contractor shall submit manufacturer test reports and component certifications (CDRL A006, DI-MISC-81356A) prior to field installation to the 309th MMXG EN and COR.

Field Test Plan: The contractor shall submit a comprehensive Final Test and Commissioning Plan (CDRL A007, DI-NDTI-80566A) to the 309th MMXG EN and COR for review and approval 30 calendar days prior to scheduled load testing.

Proof Load Testing: The contractor shall perform static and dynamic proof load testing of the installed crane system at 125 percent (+0% / -5%) of the rated capacity.

Test Report: The contractor shall submit a signed and certified Field Test Report and Crane Certification (CDRL A008, DI-NDTI-80809B) within 10 calendar days of successful test completion to the 309th MMXG EN and COR.

Nondestructive Examinations (NDE) Plan Following proof-load testing, the contractor shall perform nondestructive examinations (such as magnetic particle or liquid penetrant testing) on safety-critical welds, hooks, and load-bearing components in accordance with Chapter 6 of SSCMAN 91-710.

The contractor shall submit an NDE Plan (CDRL A009, DI-NDTI-80603A) detailing test methods, coverage areas, and pass/fail criteria to the 309th MMXG EN and COR, 30 calendar days prior to scheduled load testing. NDE results shall be included in the final test report (CDRL A008).

Preventive Maintenance and Inspection Plan The contractor shall provide a complete Preventive Maintenance (PM) and Inspection Plan (CDRL A010, DI-MGMT-81911) for the crane and hoists 30 calendar days prior to final system turnover to the 309th MMXG EN and COR.

The PM plan shall include detailed checklists for daily, frequent, and periodic inspections; wear and discard limits for wire ropes and brake discs; and any other pertinent parts and recommended lubrication schedules in alignment with AFMAN 91-203 and ASME B30.

Program Management The contractor shall designate a single Project Manager as the primary point of contact for all contractual and technical matters

The contractor shall participate in a project kickoff meeting within 30 calendar days of contract award (virtual or on-site).

Project Schedule: The contractor shall submit an Integrated Master Schedule (CDRL A011, DI-MGMT-81861D) to the 309th MMXG EN and COR, 15 calendar days after contract award and provide monthly progress updates.

Tools, Equipment, and Temporary Works The contractor shall furnish all tools, rigging gear, temporary supports, manlifts, scaffolding, and any additional equipment required to execute the work safely. All temporary works shall comply with OSHA standards and AFMAN 91-203.

Facility Modifications and Services The contractor shall make no permanent modifications to the facility structure without prior written approval from the Contracting Officer. The contractor shall protect existing facility finishes, utilities, and structures from damage, and shall repair any damage caused during performance to a condition equal to or exceeding the pre-existing state as documented in the pre-construction photographic survey.

Access, Security, and Safety All contractor personnel shall comply with all VSFB access control, badging, and escort requirements.

Site Safety Plan: The contractor shall submit a Site-Specific Safety Plan (CDRL A012, DI-SAFT-82313) to the 309th MMXG EN and COR 15 calendar days prior to starting any on-site work. The safety plan shall include detailed procedures for lockout/tagout (LOTO), fall protection, electrical safety, and hot work Warranty The contractor shall provide a minimum one-year comprehensive warranty on all furnished equipment, parts, and installation labor, starting on the date of final Government acceptance. The warranty shall cover the repair or replacement of any defective components, including all labor, materials, and re-testing costs, at no additional cost to the Government.

Service summary

SOW Paragraph
Performance Objective

Performance Threshold

3.8
Removal of Existing Equipment: Safely remove, palletize, stage, or dispose of existing crane, hoist, and controls without impacting ongoing facility operations.
Zero unauthorized outages or damage to facility infrastructure during removal.
3.9-3.9.5
Engineering and Design: Provide accurate structural calculations and drawings to ensure building supports can handle the new crane system and seismic loads.
100% compliance with PE-stamping requirements; zero unapproved structural modifications.
3.1-3.7 & 3.9
Crane System Installation: Furnish and install the new 4-ton under-running bridge crane and two 2-ton hoists with all required safety, control, and overload features.
Crane operates within CMAA Class D standards; 100% compliance with electrical/overload safety criteria.
3.12-3.13 & 3.15-3.16
Testing and Commissioning Perform operational checks, dynamic/static proof load testing (Not to exceed 125% rated capacity), and Nondestructive Examinations (NDE).
100% of tests successfully completed and certified by a qualified person; NDE reports submitted within 10 days.
3.10, 3.13, 3.14 & Section 5
Deliverables and Documentation (CDRLs)Submit all required manuals, electrical drawings, schedules, maintenance plans, and compliance matrices
No more than one late CDRL per quarter; substantive mistakes corrected within two working days.
3.17 & 3.15
Site Safety and Security: Comply with all VSFB access, security, and safety protocols (including LOTO, fall protection, and AFMAN 91-203).
Zero safety violations, and no more than one validated customer complaint** per quarter regarding contractor site conduct.

Definitions:

** Validated customer complaint – A customer complaint that is reviewed, documented, and confirmed via a Corrective Action Report (CAR).

CDRL SUMMARY

Contract information data shall be delivered electronically in accordance with the corresponding requirement for each Data Item listed in Table 5-1 (below). The contractor shall have no more than one error per quarter for all Contract Data Requirement List’s (CDRLs) submittals. The contractor shall submit CDRLs according to the due date indicated and have no more than one CDRL per quarter submitted after the identified due date. Grammatical errors do not count as an error. Substantive mistakes shall be corrected within two working days and corrective action taken to prevent recurrence of inaccurate late CDRLs.

Table 5-1

Exhibit
Data Item Description (DID) #
Title
SOW Paragraph

Delivery

A001
DI-MISC-80508B
Crane Removal Plan
3.8.1
30 calendar days prior to commencement of removal activities
A002
DI-SESS-81000F
Structural & Mechanical Drawings / Calculations
3.9.2, 3.9.3, 3.10.3
Initial: 30 calendar days prior to fabrication. Final: With turnover
A003
DI-TMSS-80527D
Commercial O&M Manuals
3.10.1
30 calendar days prior to final system turnover.
A004
DI-SESS-82351A
Electrical Documentation & Schematics
3.10.2
Initial: 30 calendar days prior to fabrication. Final: With turnover
A005
DI-PSSS-80134B
Spare Part List
3.10.4
Within 15 calendar days of contract award for Government review and Approval
A006
DI-MISC-81356A
Certificate of Compliance
3.11.1
Prior to field installation.
A007
DI-NDTI-80566A
Test Plan (Proof Load Testing)
3.11.2
30 calendar days prior to scheduled proof load testing.
A008
DI-NDTI-80809B
Final Test Reports & Crane Certification
3.11.4
10 calendar days after successful completion of testing.
A009
DI-NDTI-80603A
Nondestructive Examination (NDE) Plan
3.12.2
30 calendar days prior to scheduled proof load testing.
A010
DI-MGMT-81911
Preventive Maintenance & Inspection Plan
3.13.1
30 calendar days prior to final system turnover.
A011
DI-MGMT-81861D
Integrated Master Schedule (Project Schedule)
3.14.3
15 calendar Days After Contract Award; Updated monthly
A012
DI-SAFT-82313
Site-Specific Safety / Plan
3.17.2
15 calendar days prior to commencement of site work
A013
DI-QCIC-81794A
Quality Control Plan
6.2
14 calendar days after contract award

Quality Assurance Government Quality Assurance The government shall inspect and evaluate the contractors’ performance to ensure services are received in accordance with requirements set forth in this contract. The COR will use the contractor’s work schedule, or modified version thereof, to record validation results. Results of the validation then become the official Air Force record of the contractor’s performance. Government surveillance of tasks not listed in the SOW or by methods other than those listed in the SOW (such as provided for by the Inspection of Services clause) may occur during the performance period of this contract. Such surveillance will be done according to standard inspection procedures or other contract provisions. Any action taken by the CO as a result of surveillance will be according to the terms of this contract.

Quality Control Plan (QCP) The contractor shall develop, implement, and maintain a comprehensive Quality Control Plan (QCP) throughout the period of performance. The contractor shall submit the initial QCP (CDRL A013, DI-QCIC-81794A) to the Quality Assurance Program Coordinator (QAPC) for approval within 14 calendar days after contract award.

ADDITIONAL REQUIREMENTS

Government provided support The Government will provide working space, including heating, lighting, ventilation, and electrical power outlets for use by the contractor’s personnel during installation. The Government will provide access to the facilities where the work resides. The place of performance is Building 9320, Vandenberg Space Force Base (VSFB), CA. Contractor personnel shall use Government telephones for official business only. The contractor shall safeguard all Government property provided for contractor use.

Compliance Matrix The crane supplied by the contractor shall be in compliance with the compliance matrix in Appendix B.

GENERAL INFORMATION

Hours of Operation Normal Hours of Operation: The contractor shall perform the services required under this contract during the following hours: Monday through Thursday 0600-1630 – EXCEPT FEDERAL HOLIDAYS and other base closures.

Federal Holidays: Unless otherwise required by the Government, the contractor shall not have access to the Government facilities on the following federal holidays: New Year’s Day, Martin Luther King’s Birthday, Washington’s Birthday, Memorial Day, Independence Day, Juneteenth, Labor Day, Columbus Day, Veterans’ Day, Thanksgiving Day, and Christmas Day. If a holiday falls on Saturday, it is observed on Thursday and working hours are Monday through Wednesday for that week. If the holiday falls on a Sunday, it is observed on Monday. Any other circumstances that may prompt base closure, such as Days of National Mourning, may also restrict opportunity to perform the exchanges. In the event of a base closure, exchanges shall be performed on the next business day. There may also be up to six Goal Days and four Wingman Days per year awarded to Government civilian employees, as well as possible weather-related days and Government directed holidays. On these days, the contractor shall not generally be required to work, and the Government shall not be billed for work not performed.

Down Days/Weather Days: The Government will notify the contractor when official notice has been given for Energy/Weather Down days. The contractor is not expected to work on any Energy/Weather Down days.

Rescheduling: Down Days/Weather days may be rescheduled if conditions/emergency operations require.

Environmental Controls Hazardous Work Environment: Performance of services occurs within an industrial environment. Building 9320 has potential exposure hazards for industrial materials, including hexavalent chromium, cadmium, beryllium, and lead. Contractor personnel shall not perform duties inside designated regulated areas where exposures are projected to exceed Permissible Exposure Limits (PEL) established by 29 CFR 1910.10xx. The contractor shall provide all employee safety training, environmental exposure monitoring, and Personal Protective Equipment (PPE) in accordance with OSHA standards. The Government will make available the Space Launch Delta 30 (SLD 30) Bioenvironmental Engineering flight's industrial hygiene surveys upon contract award.

Environmental Compliance: The contractor shall comply with all applicable Federal, State, and local environmental protection laws and regulations Conservation of Utilities: The contractor shall adhere to VSFB utility conservation practices. The contractor shall operate all equipment and lights in an energy-efficient manner, turning off non-essential lights and water valves immediately after use.

Compliance with Laws and Regulations.

The contractor shall be knowledgeable of and comply with all applicable Interstate, Federal, State, and Local laws, regulations, and requirements regarding environmental protection. In the event environmental laws/regulations change during the term of this contract, the contractor is required to comply as such laws come into effect.

Appendix A – ACRONYMS AND ABBREVIATIONS

Acronym/AbbreviationsDefinition
ACAlternating Current
AFMANAir Force Manual
AFSPCMANAir Force Space Command Manual
AISCAmerican Institute of Steel Construction
ASMEAmerican Society of Mechanical Engineers
AWSAmerican Welding Society
CARCorrective Action Report
CADComputer-Aided Design
CDRLContractor Data Requirements Listing
CFRCode of Federal Regulation
CMAACrane Manufacturers Association of America
CORContracting Officer’s Representative
CUIControlled Unclassified Information
E-stopEmergency Stop
FPMFeet Per Minute
HzHertz
LOTOLockout/Tagout
NDENondestructive Examination
NECNational Electrical Code
NEMANational Electrical Manufacturers Association
NFPANational Fire Protection Association
O&MOperation and Maintenance
OEMOriginal Equipment Manufacturer
OSHAOccupational Safety and Health Act
PELPermissible Exposure Limit
PMPreventive Maintenance
PPEPersonal Protective Equipment
PLCProgrammable Logic Controller
QAPCQuality Assurance Program Coordinator
QCPQuality Control Plan
QASPQuality Assurance Surveillance Plan
RFRadio Frequency
SLD 30Space Launch Delta 30
SOWStatement of Work
SSCMANSpace Systems Command Manual
VACVolts AC
VFDVariable Frequency Drive
VSFBVandenberg Space Force Base

Appendix B – Crane compliance matrix (sscman91-710v3

Para
Title / Requirement
N/A
Compliance (I= Inspection, T= Test, D= Design, A= Analysis)
NOTES:

SSCMAN91-710V3 Chapter 6, 27 DECEMBER 2022

How will we show it is in compliance?
B9320 Crane Unit#XX. Non-critical V3 crane requirements shaded. Other testing requirements can be found in V6.
6.3
Cranes and Hoists. The following design, fabrication, testing, data submittal and WR specific seismic requirements are applicable to cranes and hoists used to handle critical and noncritical hardware. The requirements in 6.3.1 through 6.3.4 are applicable to all cranes and hoists. Additional requirements for critical cranes and hoists are specified in 6.3.5. Requirements for existing Real Property Installed Equipment (RPIE) crane and hoists are specified in 6.3.6. Note: Range Users shall ensure that handling processes are designed such that all crane and hoist testing requirements are met. Requirements of Volume 6, Chapter 6 shall also be met.
6.3.1
Crane and Hoist Design Standards and Requirements.
6.3.1.1
Cranes and hoists shall comply with the requirements in the following industry standards, as applicable, and the additional requirements described below:
6.3.1.1.1
29 CFR 1910.179, Overhead and Gantry Cranes.
6.3.1.1.2.
Department of the Air Force Manual (DAFMAN) 91-203, Air Force

Occupational Safety, Fire, and Health Standards.

6.3.1.1.3.
Crane Manufacturers Association of America (CMAA) 70, Overhead Cranes, and CMAA 74, Overhead Hoists, for overhead cranes and hoists.
6.3.1.1.4.
ASME B30 series safety standards.
6.3.1.1.5.
National Fire Protection Association (NFPA) 70, National Electrical Code (NEC) for all electrically powered cranes and hoists.
6.3.1.1.6.
ASME Hoist (HST) Standards.
6.3.1.1.7.
Hoist Manufacturing Institute (HMI) Standards.
6.3.1.1.8.
American Welding Society (AWS) Standards.
6.3.1.1.9.
American Institute of Steel Construction (AISC) Standards and Codes.
6.3.1.1.10.
National Electrical Manufacturer’s Association (NEMA) Industrial Control and Systems Standards.
6.3.1.1.11.
Software safety hazard analysis shall be completed for critical cranes. Analysis shall include fish bone diagram (or other appropriate analysis method) that allows for controls system troubleshooting for fault detection.
N/A
6.3.1.2.
Definitions and terminology used in test and NDE plans shall be IAW standard methodology used in the above applicable standards.
6.3.1.3.
Crane, hoist, and hook NDE plans shall be submitted to Wing Safety for review and approval. The plans shall identify all SFPs, NDE requirements and methodology, and acceptance criteria.
6.3.1.4.
All crane specifications, test plans, and test results shall be reviewed and approved by Wing Safety. Test plans shall include a detailed list of initial and periodic inspections, no-load tests, and proof tests, to include frequency of testing.
6.3.1.5.
Crane and Hoist Service Classifications.
6.3.1.5.1.
The service classifications found in CMAA 70 and 74 shall be used as the basis for selecting cranes and hoists to be used on the ranges.
6.3.1.5.2.
Cranes used to handle critical loads shall be at least Class D in accordance with CMAA classification, unless otherwise agreed to by Wing Safety. Note: The class D requirement is used as additional margin to mitigate construction quality concerns. Class C requirements may be negotiated if quality requirements are implemented as safety requirements.
6.3.1.6.
Bridge and Trolley Movement Marking.
6.3.1.6.1.
Each overhead crane shall have the directions of its bridge and trolley movements displayed on the underside of the crane. These directions (North, East, South, and West) shall correspond to the directions on the operator station.
6.3.1.6.2.
These markings shall be visible and legible from the floor and any operator station.
6.3.1.7.
Crane and Hoist Component Accessibility.
6.3.1.7.1.
Crane and hoist design shall provide for safe and adequate access to components to inspect, service, repair, or replace equipment.
6.3.1.7.2.
Access platforms and/or footwalks with guard rails and personnel tie-offs shall be provided to perform the tasks in 6.3.1.7.1.
6.3.1.7.3.
Crane and hoist design shall provide for visual and physical accessibility of all SFP components and welds and other safety critical parts during initial inspection.
6.3.1.7.4.
Clearances between the crane and stationary structures and clearances between parallel cranes shall be provided in accordance with 29 CFR 1910.179.
6.3.1.8.
Wire Rope Requirements. Rotation resistant wire rope with swivel links installed shall not be used for any purpose. Note: Rotation resistant wire rope is not recommended because past experience has shown that this type of rope can incur damage that is not readily detectable; for example, internal wire rope core damage.
6.3.1.9.
Use of Cast Iron. Cast iron and other similar brittle materials shall not be used in load bearing parts.
6.3.1.10.
Crane and Hoist Hooks.
6.3.1.10.1.
Hook shall be designed, fabricated, inspected, and tested in accordance with ASME B30.10, Hooks, and the additional requirements below.
6.3.1.10.2.
All hooks shall be equipped with a positive latching mechanism to prevent accidental load disengagement.
6.3.1.10.3.
The initial throat opening of a hook shall be measured and permanent reference marks placed on each side of the hook throat opening.
6.3.1.10.4.
Hook load-bearing attachment holes shall be inspected and their dimensions recorded during initial inspection.
N/A
6.3.1.10.5.
For hooks having load-bearing holes, the hook manufacturer shall specify the hole and pin diameter size to be used for attaching load-bearing fittings and the permissible diametral clearance pass/fail criteria for pin and hole to be used during hook inspection. Hooks with holes having cracks exceeding the manufacturer criteria shall be repaired or replaced.
N/A
6.3.1.10.6.
Attachments such as handles and latch supports shall not be welded to a finished hook in a field application. Note: If welding of attachments such as these is necessary, it shall be done by the hook manufacturer before any required final heat treatment, load test, and NDE.
N/A
6.3.1.10.7.
Before and after the hook initial proof-load test (before installation on the crane), volumetric and surface NDE shall be performed on the hook and its shank, shank threads, nut (including nut threads); or for pinned shank hooks, the attachment pin IAW the NDE plan.
6.3.1.11.
Reeving.
6.3.1.11.1.
For dual-reeved hoists, equalizer sheaves shall be self-aligning with the load line.

Comply(D)

6.3.1.11.2.
Load lines shall be attached to the crane by a rope termination method that develops 100% of the rope strength with the exception of rope-to-drum attachments. Newly installed rope termination sockets shall be volumetrically and surface inspected and certified before rope installation on the crane.
6.3.1.12.
Crane and Hoist Motion Controls.
6.3.1.12.1.
Controls shall provide positive motion control at all times. No un-commanded motion shall be allowed, including drum reversal during starting and stopping.
6.3.1.12.2.
Controls shall be of the fail-safe “dead man” type.
6.3.1.12.3.
Cranes shall be provided with pushbutton or lever-type control switches for controlling crane motion.
6.3.1.12.4.
Controls shall have an inching (jog) capability when the speed selector switch is in the slowest speed position.
6.3.1.12.5.
The controller(s) shall be capable of being adjusted for the desired amount of acceleration and deceleration rates.
6.3.1.12.6.
Pendant control stations shall be suspended by a strain relief chain or cable to protect the electrical conductors from strain.
6.3.1.12.7.
The control station(s) shall be located so that the crane operator has direct line of sight to the load at all times. If this is not possible, spotters or assistant operators shall have emergency stop capability at their location if inadvertent crane movement could result in personnel injury or death.
6.3.1.13.
Hoist Limit Switches. All overhead cranes and hoists shall be equipped with two limit switches in the “up” direction to prevent “two blocking” and one limit switch in the “down” direction to prevent a slack rope condition when unladen.
6.3.1.13.1.
The first “up” limit switch shall interrupt the movement control circuit and shall be reset by reversing the movement control.
6.3.1.13.2.
The second “up” limit switch shall be a mechanical fail-safe switch that will interrupt power to the hoist mechanism, and require key-operated reset.
6.3.1.14.
Bridge and Trolley Brakes. The overhead crane bridge and trolley shall be equipped with fail-safe brakes in both directions, designed IAW the stopping distance requirements of CMAA 70/74 and ASME B30.2, Overhead and Gantry Cranes.
6.3.1.15.
Crane and Hoist Grounding and Bonding.
6.3.1.15.1.
All cranes and hoists shall be grounded and bonded to provide hardware and personnel protection against electrical failures or lightning strikes.
6.3.1.15.2.
Grounding and bonding between trolley, bridge, and runway shall use separate bonding conductors that may be run with electrical circuit conductors.
6.3.1.15.3.
In accordance with NFPA 70/NEC, the trolley frame and bridge frame shall not be considered electrically grounded through the bridge and trolley wheels and its respective tracks.
6.3.2.
Crane and Hoist Inspection and Test Requirements.
6.3.2.1.
Crane and Hoist Initial Inspection and Test Requirements.
6.3.2.1.1.
All new, reinstalled, altered, repaired, or modified cranes and hoists shall be rated load tested to 125% (+0%, -5%) in accordance with ASME B30.2 methodology.
6.3.2.1.2.
Prior to, and after the rated load test, a full operational, no-load test shall be performed to test full functionality of crane, in accordance with ASME 30.2 methodology. At a minimum, testing will include (1) lifting and lowering, (2) trolley travel, (3) bridge travel, (4) all hoist-limit devices, (5) travel-limit devices, and (6) locking and indicating devices, if provided.
6.3.2.1.3.
During rated load testing, the test weight shall be moved throughout the complete operating envelope of the overhead crane or hoist system, stopping and starting at various locations to verify smooth operation. The test weight shall be raised to a sufficient height to ensure that each tooth of the lifting gear train is subjected to the rated load. Lower load to 4-8 inches from ground level prior to traversing crane/hoist travel envelope.
6.3.2.1.4.
The test weight shall be transported throughout the full length of the trolley and bridge envelope.
6.3.2.1.5.
Cranes and hoists shall be inspected and tested, at a minimum, IAW the requirements specified by OSHA, ASME, DAFMAN 91-203, and/or per manufacturer's recommendations.
6.3.2.1.6.
Before and after the crane and hoist rated load test, a complete functional test of all control systems, safety devices, and warning indicators shall be performed.
6.3.2.1.7.
The test weight shall be hoisted approximately 2 feet and suspended for a minimum of 3 minutes to verify hoist drum rotation and test weight drift are within acceptable limits.
6.3.2.1.8.
With the trolley located at the center of the bridge, the test weight shall be raised to the maximum height and then lowered in three increments, stopping each time to verify there is no un-commanded drum rotation or test weight lowering.
6.3.2.1.9.
The test weight shall be raised to sufficient height and at least one emergency stop shall be made at the fastest lowering speed to verify that brake application is positive and effective.
6.3.2.1.10.
Bridge, trolley, and hoists shall be tested at each specified speed, including braking, bumping, and jogging.
6.3.2.1.11.
Bridge and trolley brakes shall be tested to verify that they function in accordance with CMAA 70 and 74 and ASME B30 series requirements.
6.3.2.1.12.
Before any crane operations, a full functional test of all cranes and hoists shall be performed.
6.3.2.1.13.
Inspections and tests shall be performed by appointed competent persons or authorized persons. If state requirements mandate crane inspectors and certifiers are licensed (e.g., California), individuals shall identify the recognized certification authority and expiration date of the certification authority.
6.3.2.1.14.
Following the load test, NDE shall be performed on crane and hoist SFPs IAW the NDE plan. For recurring NDE, disassembly is not required. NDE is only applicable to accessible parts of SFPs and shall only be surface NDE.
6.3.2.2.
Crane Hook Initial Inspection and Test Requirements.
6.3.2.2.1.
Crane hooks shall be load tested and inspected by the manufacturer before assembly on the hoist using the guidelines provided in ASME B30.10.
6.3.2.2.2.
After the initial proof-load test but before installation on the hoist, volumetric and surface NDE shall be performed on the hook and its shank, shank threads, nut (including nut threads), or for pinned shank hooks, the attachment pin IAW the NDE plan.
6.3.2.2.3.
Following the crane load test, hooks shall be inspected in accordance with ASME methodology; NDE shall be performed on exposed portions of the hook IAW the NDE plan.
6.3.2.2.4.
Hook throat opening and load-bearing attachment holes shall be inspected, per the NDE plan, and throat and load-bearing hole measurements shall be taken and recorded. Measurements and inspection results shall be compared to the acceptance/rejection criteria in ASME B30.10 and manufacturer specifications. Hooks exceeding the inspection criteria shall be repaired or replaced.
6.3.3.
Crane and Hoist Data Requirements. Crane and hoist data requirements shall be

submitted IAW A2.2.5.7 of this volume and SSCMAN 91-710 Volume 5, Attachment 2.

6.3.4.
Unique WR Crane Design Standards and Requirements.
Table 6.2.
California Occupational Safety and Health Administration Requirements.
INFO
All cranes and hoists on Vandenberg AFB locations within California Occupational Safety and Health Administration (Cal-OSHA) jurisdiction, and greater than 3 tons rated capacity are subject to Cal-OSHA regulatory requirements.
6.3.4.1.
California Occupational Safety and Health Administration Requirements. In addition to the requirements in 6.3.1, 6.3.2, and 6.3.3, at the WR, cranes not on VAFB exclusive federal jurisdiction property shall be inspected, tested, and certified IAW the Cal-OSHA requirements.
6.3.4.2.
WR Crane and Hoist Seismic Design Requirements. The seismic design of cranes, craneways and support structures, and seismic loads calculations shall be IAW the requirements in Chapter 17 of this volume and those listed below:
6.3.4.2.1.
Seismic load calculations shall consider dynamic amplification effects and the dynamic characteristics of the crane or hoist and its craneway and support structure.
6.3.4.2.2.
Provisions shall be made to prevent the crane bridge and trolley(s) from “jumping” their rail anywhere along the track, during a seismic event.
6.3.4.2.3.
Seismic load calculations used for critical cranes shall ensure that the design and construction of the crane or hoist shall remain in place and support the critical load during and after a seismic event.
6.3.5.
Additional Requirements for Cranes and Hoists Used To Handle Critical Hardware and Used in Hazardous Environments. In addition to the requirements in 6.3.1 and 6.3.2, these requirements are applicable to all cranes and hoists used to support critical operations and cranes and hoists used in hazardous environments.
6.3.5.1.
Overhead Crane and Hoist Design Requirements.
6.3.5.1.1.
Controls.
6.3.5.1.1.1.
Lever type switches shall be provided with a positive latch that, in the off position, prevents the handle from being inadvertently moved to the on position. Note: An off detent or spring-return arrangement is not sufficient.
6.3.5.1.1.2.
All control panels shall have a lockout feature such as a keyed switch to prevent unauthorized operation.
6.3.5.1.1.3.
Control stations shall have the built-in capability to test the integrity of all indicator lamps and aural/visual warning devices.
6.3.5.1.1.4.
Cranes and hoists shall not be capable of being controlled by more than one control station at a time. Emergency stop capability from all emergency stop control stations shall be retained.
6.3.5.1.1.5.
For RF controllers, in the event of an interruption in the radio link from the transmitter to the receiver, both the transmitter and receiver will shut down. When the transmitter and receiver shut down, the brakes on the crane shall be set and the crane controls will be placed into a safe mode.
Table 6.3.
Smart Crane Controls.
INFO
Crane controls may feature technology for specialized speed and motion control, system self-diagnostics, load control safety features, and maintenance monitoring. For example:
INFO
Inching and micro-speed. Drive controls shall be capable of selecting increments of motion between 2 to 100 mm and drive speed selectability of 1% to 99% of full speed.
INFO
Shock load prevention. Controls shall have the capability to detect slack rope on lift to prevent shock load during lift train tensioning.
INFO
Load floating. Control functions will allow for the ability to hold a load with precision torque, without hoisting or lowering, and with the brakes open.
INFO
Snag detection/rope angle monitoring. Controls shall have the ability for real time monitoring of the wire rope and angle to detect unbalanced loads or a possible load snag.
INFO
Hook centering. A control system shall allow for automatic repositioning of trolley and bridge over the load to prevent side loading.
INFO
Operator panel/remote diagnostic capability. A control system shall allow for real time monitoring of parameters and status of all drives (speed, torque, current, temperature, etc.), fault and error indications, restricted zone operation, two-blocking load detection, and brake slip detection.
INFO
For hard-to-access cranes, an operator control interface shall have the capability to troubleshoot and reset faults remotely (without the need to climb up on the crane to diagnose issues). It shall allow an operator to remotely modify drive parameters, log fault/alarm/runtime events (cycles, speeds, load lift history), and signal when preventative maintenance and inspections are due.
6.3.5.1.1.6.
Emergency stop controls shall be hard-wired.
6.3.5.1.2.
Bridge and Trolley Travel Limit Switches. Each bridge and trolley shall be equipped with travel limit switches that will first slow the bridge or trolley to “creep” speed and a second limit switch that will remove power and apply the brake before it engages the bumper or other mechanical stop, but with subsequent creep-speed override to enable hard stop contact.
6.3.5.1.3.
Hoist Overload.
6.3.5.1.3.1.
Hoists shall be designed with an adjustable hoist overload detection device. When triggered, the device shall activate an overload indicator light and overload indicator horn and shut down the hoist, requiring key-operated reset. The device shall be capable of being overridden to enable the load test. A keyed override switch shall be provided.
6.3.5.1.3.2.
Hoists control panels shall be instrumented with a load readout. A load tare out button shall be provided to enable resetting the readout to zero with rigging on the hook.
6.3.5.1.4.
Hoist Braking.
6.3.5.1.4.1.
Powered hoists shall have dual fault tolerant braking systems.
6.3.5.1.4.2.
The overspeed device shall be located so that it monitors drum rotation irrespective of a single failure in the drive train.
6.3.5.1.4.3.
The braking system shall be capable of braking and holding at least 150% of torque exerted by full rated load on the hook.
6.3.5.1.4.4.
The braking system shall be activated by the emergency stop button.
6.3.5.1.4.5.
The dual fault tolerant braking system shall be capable of being tested in place.
6.3.5.1.4.6.
The application of multiple braking systems shall be synchronized to minimize shock loading.
6.3.5.1.4.7.