This is a Contract Data Requirements List (DD Form 1423) for the Vandenberg Building 9320 Hoist/Crane Replacement project. The form specifies a single data deliverable requirement identified as Data Item A008: Test/Inspection Report with the subtitle "Final Test Reports & Crane Certification." The requiring office is 309 MXSG/MASO at what appears to be a U.S. Air Force facility. The data item is referenced in Statement of Work Paragraph 3.11.4 and is derived from Data Acquisition Document DI-NDTI-80809B.
The contractor must submit the final test report within 10 calendar days of successful test completion. The report must be delivered electronically to four government addressees (Alan Taylor, Mason Figueroa, Shane Weston, and John Pedri) in Microsoft Office compatible format as searchable PDFs. Content requirements include written reports for static and dynamic proof load testing, final crane certification signed by a qualified person, and all non-destructive examination (NDE) results and certifications. The deliverable is classified as a one-time submission with subsequent resubmission only if required to correct deficiencies identified during government review. Final government acceptance and warranty commencement are contingent upon review and approval of this report. The estimated total price for this data item is $0.00, and the distribution statement is approved for public release with unlimited distribution.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| 309 MXSG SOW - Vandenburg Crane - Final (10-19-26).docx | DOCX document | |
| CDRL - A006.pdf | ||
| CDRL - A002.pdf | ||
| CDRL - A011.pdf | ||
| CDRL - A013.pdf | ||
| CDRL - A009.pdf | ||
| CDRL - A012.pdf | ||
| CDRL - A007.pdf | ||
| CDRL - A010.pdf | ||
| CDRL - A001.pdf | ||
| 15853 - Vandenberg Crane Replacement Combo.docx | DOCX document | |
| CDRL - A005.pdf | ||
| CDRL - A003.pdf | ||
| CDRL - A004.pdf |
Show all 14
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
PREVIOUS EDITION MAY BE USED.
DD FORM 1423, FEB 2024 Page 1 of 2
UNCLASSIFIED
UNCLASSIFIED
CONTRACT DATA REQUIREMENTS LIST
A. CONTRACT LINE ITEM NO.
TBD
B. EXHIBIT
A
C. CATEGORY:
TDP TM OTHER NDTI
D. SYSTEM/ITEM
Vandenberg Building 9320 Hoist/Crane Replacement
E. CONTRACT/PR NO.
TBD
F. CONTRACTOR
TBD
1. DATA ITEM NO.
A008
2. TITLE OF DATA ITEM
Test/Inspection Report
3. SUBTITLE
Final Test Reports & Crane Certification
4. AUTHORITY (Data Acquisition Document No.)
DI-NDTI-80809B
5. CONTRACT REFERENCE
SOW Paragraph 3.11.4
6. REQUIRING OFFICE
309 MXSG/MASO
7. DD 250 REQ
LT
8. APP CODE
A
9. DIST STATEMENT
REQUIRED
A
10. FREQUENCY
1/TIME (One time)
11. AS OF DATE
N/A
12. DATE OF FIRST SUBMISSION
Block 16
13. DATE OF SUBSEQUENT
SUBMISSION
N/A
14. DISTRIBUTION
a. ADDRESSEE
b. COPIES
Draft Final
Reg Repro
16. REMARKS
(9) DISTRIBUTION STATEMENT A: Approved for public release. Distribution is unlimited.
(12) Due within 10 calendar days of successful test completion; resubmittal only if required to correct deficiencies identified during Government review
(14) One (1) copy of each submittal shall be provided electronically to each addressee in block 16 in Microsoft Office compatible format.
Submit electronically per SOW 3.11.4. Reports and certifications shall be provided as searchable PDFs.
Content shall include written reports for static and dynamic proof load testing, final crane certification signed by a qualified person, and all NDE results and certifications required for inclusion in the final test report.
Final Government acceptance and warranty commencement will not occur until this report is reviewed and approved.
Addressees:
Alan Taylor 309 MMXG - EN alan.taylor.9@us.af.mil
DSN: 586-9298
COMM: 801-586-9298
Mason Figueroa 309 MXSS/MXDVAAC mason.figueroa.1@us.af.mil
DSN: 777-2545
COMM: 801-777-2545
Shane Weston MXSG/MXDEQ shane.weston@us.af.mil
DSN: 586-8624
COMM: 801-586-8624
John Pedri 309 MXSG - COR john.pedri.1@us.af.mil
DSN: 775-6122
COMM: 801-775-6122
15.TOTAL
17. PRICE GROUP
NSP
18. ESTIMATED
TOTAL PRICE
0.00
G. PREPARED BY
Paulette Johnson
H. SIGNATURE I. APPROVED BY J. SIGNATURE
INSTRUCTIONS FOR COMPLETING DD FORM 1423
(See DoDM 5010.12 for detailed instructions.)
DD FORM 1423, FEB 2024 Page 2 of 2
FOR GOVERNMENT PERSONNEL
Item A. Self-explanatory.
Item B. Self-explanatory.
Item C. Mark (X) appropriate category: TDP - Technical Data Package; TM - Technical Manual; Other - other category of data, such as "Provisioning," "Configuration Management," etc.
Item D. Enter name of system/item being acquired that data will support (e.g., Mission Design Series (MDS) designator).
Item E. Self-explanatory (to be filled in after contract award).
Item F. Self-explanatory (to be filled in after contract award).
Item G. Name of preparer of CDRL.
Item H. Date CDRL was prepared and signature of preparer of CDRL.
Item I. Name of CDRL approval authority.
Item J. Date CDRL was approved and signature of CDRL approval authority.
Item 1. See DFARS Subpart 204.71 for proper numbering. To add or delete additional data items, point and click the plus or minus sign to the right of Block J.
Item 2. Enter title as it appears on data acquisition document cited in Item 4.
Item 3. Enter subtitle of data item for further definition of data item (optional entry).
Item 4. Identify only one Data Acquisition Document No. If a single work task generates more than one deliverable data product, prepare a separate data item for each deliverable data product.
Item 5. Enter reference to tasking in contract that generates requirement for the data item (e.g., Statement of Work/Performance Work Statement paragraph number).
Item 6. Enter technical office responsible for ensuring adequacy of the data item.
Item 7. Specify requirement for inspection/acceptance of the data item by the Government.
Item 8. Specify requirement for approval of a draft before preparation of the final data item.
Item 9. For technical data and computer software, specify the contractor's requirement to mark the appropriate distribution statement on the technical data or computer software (ref. DoDI 5230.24).
Item 10. Specify number of times data items are to be delivered.
Item 11. Specify as-of date of data item, when applicable.
Item 12. Specify when first submittal is required.
Item 13. Specify when subsequent submittals are required, when applicable.
Item 14. Enter addressees and number of draft/final copies to be delivered to each addressee. Explain reproducible copies in Item 16.
Item 15. Enter total number of draft/final copies to be delivered.
Item 16. Use for additional/clarifying information for Items 1 through 15.
Examples are: Tailoring of documents cited in Item 4; Clarification of submittal dates in Items 12 and 13; Explanation of reproducible copies in Item 14; Desired medium for delivery of the data item.
Identify for which data item additional remarks are provided. When tailoring the Data Acquisition Document invoked in Item 4, identify which portions of that Document are being tailored.
Identify any referenced attachments to the form. Attachments can be added using the button at the bottom of page 1.
FOR THE CONTRACTOR
Item 17. Specify appropriate price group from one of the following groups of effort in developing estimated prices for each data item listed on the DD Form 1423.
a. Group I. Definition - Data which is not otherwise essential to the contractor's performance of the primary contracted effort (production, development, testing, and administration) but which is required by DD Form 1423.
Estimated Price - Costs to be included under Group I are those applicable to preparing and assembling the data item in conformance with Government requirements, and the administration and other expenses related to reproducing and delivering such data items to the Government.
b. Group II. Definition - Data which is essential to the performance of the primary contracted effort but the contractor is required to perform additional work to conform to Government requirements with regard to depth of content, format, frequency of submittal, preparation, control, or quality of the data item.
Estimated Price - Costs to be included under Group II are those incurred over and above the cost of the essential data item without conforming to Government requirements, and the administrative and other expenses related to reproducing and delivering such data item to the Government.
c. Group III. Definition - Data which the contractor must develop for his internal use in performance of the primary contracted effort and does not require any substantial change to conform to Government requirements with regard to depth of content, format, frequency of submittal, preparation, control, and quality of the data item.
Estimated Price - Costs to be included under Group III are the administrative and other expenses related to reproducing and delivering such data item to the Government.
d. Group IV. Definition - Data which is developed by the contractor as part of his normal operating procedures and his effort in supplying these data to the Government is minimal.
Estimated Price - Group IV items should normally be shown on the DD Form 1423 at no cost.
Item 18. For each data item, enter an amount equal to that portion of the total price which is estimated to be attributable to the production or development for the Government of that item of data.
These estimated data prices shall be developed only from those costs which will be incurred as a direct result of the requirement to supply the data, over and above those costs which would otherwise be incurred in performance of the contract if no data were required. The estimated data prices shall not include any amount for rights in data. The Government’s rights to use the data shall be governed by the pertinent provisions of the contract.
File details come from the government source that posted it. Updated .