12238 SOO_v2.pdf
PDF 374 KB Posted
- Attached to
- AGM60/600 Battery Plant Replacements Federal contract opportunity
- Solicitation number
- FA822225QAMG6
About this file
This Statement of Objectives (SOO) outlines a requirement to replace obsolete AGM60/600 Battery Plants at five buildings located at Vandenberg Space Force Base, California. The project involves procuring, delivering, and installing new -48VDC power systems, with specific requirements including providing TAA-compliant power supplies (2 Kepco RA-60 enclosures with Kepco HSP 48-30RM DC Power Supplies), redlining product drawings, and completing installation within eleven to twelve months. The replacement is necessitated by diminishing manufacturer support and the risk of critical communications equipment losing functionality due to unavailable spare parts.
The SOO specifies that two buildings (907 and 1639) require mandatory replacements, while three others (510, 21200, and 518) are optional. Each site has varying DC load requirements ranging from 5.2 to 9.5 amps. The contractor must provide a comprehensive project management approach, including milestones like kickoff, design reviews, testing, and configuration audits. Additional requirements include providing a technical manual, spare parts listing, safety plan, training materials, and a warranty covering parts and labor for at least one year. The Space Force Project Manager for this effort is Kyrstynne Coleman, with contact information provided in the document.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| CDRLs All_v2.pdf | ||
| Amended - AGM Combined Synopsis Solicitation.pdf | ||
| DD 254.pdf | ||
| 12238 SOO.docx | DOCX document | |
| CLS Clauses Incorporated by Reference.pdf | ||
| AGM - Combined Synopsis Solicitation.docx | DOCX document | |
| 12238 CDRLs All.pdf |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
i
Statement of Objectives (SOO) For the Western Range AGM 60/600 Replacement
26 MAR 2025
Amended: 8 May 2025
SLD 30/RM
826 13th Street Bldg 7011
Vandenberg Space Force Base, CA 93437
1 BACKGROUND
The AGM-600 Power Plants are installed at numerous Instrumentation and Command system locations throughout the Western Range in support of communications requirements, including Range Safety Critical Command and Antenna pointing data circuits. These units provide 48 Volt Direct Current power for the communications equipment.
The AGM Power Plants have surpassed the end-of-life stage and onto the end of service stage whereby the vendor can no longer provide support. Additionally, there is difficulty finding another vendor to service replacement parts. The rectifiers, resistors and circuit card assemblies for the AGM Power Plants are no longer vendor supported for replacement of parts.
Diminishing Manufacturer Source Material Shortage (DMSMS) cases for modulators DM-09- 0069, for rectifiers DM-09-0152, for resistors DM-10-0015, and for circuit card assemblies DM- 10-0014 and DM-11-0059 are open to document these risks. Without spare parts, the power plants cannot be maintained.
2 SCOPE
2.1 The objective for this Statement of Objectives (SOO) is to procure, deliver, and install a technical replacement for the AGM60/600 Battery Plants at various buildings at Vandenberg Space Force Base (VSFB), CA.
2.2 The contractor shall provide all labor, materials, and incidentals to complete all requirements herein.
2.3 The contractor shall provide all new equipment and materials, free of corrosion, scratches, burrs, or any other such defects. No part shall be substituted or applied contrary to the manufacturer’s recommendations and standard practices.
2.4 The following product drawings shall be redlined with the installation details of the new
UPS for all five sites:
Building Description 510 • All rack elevations
• Parts lists to go with the rack elevations
• Floorplan
• Single line diagram
• Breaker Panel schedule
518 • All rack elevations
• Parts lists to go with the rack elevations
• Floorplan
• Single line diagram
• Breaker Panel schedule
907 • All rack elevations
• Parts lists to go with the rack elevations
• Floorplan
• Single line diagram
• Breaker Panel schedule
1639 • All rack elevations
• Parts lists to go with the rack elevations
• Floorplan
• Single line diagram
• Breaker Panel schedule
21200 • All rack elevations
• Parts lists to go with the rack elevations
• Floorplan
• Single line diagram
• Breaker Panel schedule
The drawings shall be delivered in DWG and PDF format.
CDRL A008, DI-DRPR-81680A, Engineering Documentation Product Drawings (Re-Procurement)
3 PERIOD OF PERFORMANCE: Eleven (11) Twelve (12) months for required replacements with an additional twelve (12) months for optional CLINs.
4 PROJECT DESCRIPTION
4.1 The Government’s intent is to procure, install and integrate a replacement of the AGM60/600 systems in the following locations at Vandenberg Space Force Base (VSFB):
4.2 Table 1 contains the reference Requirement Statement (RS) that providing Range-level justification for this effort:
Building System DC LOAD
(AMPS)
Replacement
510 AGM-600 System 5.7 Optional 518 AGM-60 System + AC UPS Unit 7.1 Optional 907 AGM-600 System 5.2 Required 1639 AGM-600 System 6.1 Required 21200 AGM-600 System 9.5 Optional
Requirement ID Requirement Title
RS1704063W,
Revision 0
Replace AGM Power Plants Modulators, rectifiers, resistors and circuit card assemblies for the AGM Power Plants are no longer vendor supported for replacement of parts.
Diminishing Manufacturer Source Material Shortage (DMSMS) cases for modulators DM-09-0069, for rectifiers DM-09-0152, for resistors DM-10-0015, and for circuit card assemblies DM-10-0014 and DM-11- 0059 are open to document these risks. Without spare parts, the power plants cannot be maintained. The AGM Power Plants provide power to communications equipment throughout different VAFB sites (each site configured for two or more power plants). The AGM Power Plants have surpassed the end of life stage and onto the end of service stage whereby the vendor can no longer provide support.
Additionally, there is difficulty finding another vendor to service replacement parts.
Table 1: Requirement Statement for AGM600 Systems
4.3 Description Of New Capability/Requirement:
Justification: The current AGM600 battery plants are obsolete and are no longer supported by the manufacturer. Diminishing Manufacturer Source Material Shortage (DMSMS) cases for modulators DM-09-0069, rectifiers DM-09-0152, resistors DM-10-0015, and for circuit card assemblies DM-10-0014 and DM-11-0059 are open to document these risks.
Impact/Risk: Without spare parts, the power plants cannot be maintained. LTRS equipment that relies on -48VDC power at instrumentation will eventually lose capability and cease to function.
5 REQUIREMENTS
5.1 The supplier shall provide all labor, materials, and incidentals to complete all requirements herein.
5.2 The supplier shall provide all new equipment and materials, free of corrosion, scratches, burrs, or any other such defects. No part shall be substituted or applied contrary to the manufacturer’s recommendations and standard practices.
5.3 All sites specified are backed up by generator and all sites, except for B518, are backed up by site UPS with a tech power bus. Therefore, only -48VDC battery sources are required without additional battery back-up for the DC power source, as would be supplied with a new battery plant. Additionally, B518 will require an AC UPS capable of supplying the site load for 5 minutes at the minimum.
5.4 The supplier shall complete a thorough evaluation of the Government’s legacy -48VDC battery system(s) and available technical documentation to confirm requirements, conduct early planning, address and plan for safety, and validate/invalidate technical and operational assumptions. During this initial site evaluation, the supplier shall develop and deliver a white paper that includes technical considerations for downtime required to replace the -48VDC Battery Plant, testing the new system and cutting over to full operation maintainability at each site.
CDRL A001, MIL-DTL-87929F, Technical Manual CDRL A002, DI-NDTI-80809B, Test/Inspect Report
5.5 The supplier shall provide an A/B DC distribution bus panel using GMT fuse panels if site is not designed for A/B power configuration. If additional fuse panels are required, the supplier shall wire units for A/B operation if equipped. The supplier shall cut over all new circuits to the DC fuse panel.
5.6 Table 2 has the site-specific load requirements:
BUILDING DC LOAD (AMPS)
510 5.7 518 7.1 907 5.2 1639 6.1 21200 9.5
Table 2: Site DC Load Requirements
5.7 The supplier shall plan to complete cut over in less than 8 hours.
The supplier shall provide TAA compliant -48VDC Power Supplies (2 (Two) each Kepco RA-60 enclosures containing 2 (Two) each Kepco HSP 48-30RM DC Power Supplies or equivalent.) Power supplies must be hot-swappable.
CDRL A009, DI-MISC-80508B, Product Indenture Report (PIR)
5.8 Each power supply shelf shall be powered from the Tech Bus panel at each site, where neither breaker is on the same phase.
5.9 Building 518 runs on generator only for backup power so there is no AC UPS Tech power panel. AC power for -48VDC Power Supplies must be supplied by 2 (Two) each UPS units.
These units must be powered from 2 separate phases. Power source can be 110 or 220 VAC.
Run time for full power should be at least 5 minutes.
5.10 The Contractor shall remove and legally dispose of the existing -48 DC Battery Plant systems at each site upon successful installation, testing and cutover.
5.11 The Contractor shall supply a manufacturer recommended spares kit for each site.
CDRL A003, DI-PSSS-80134B, Proposed Spare Parts Listing
5.12 The Contractor shall test the spares to verify their functionality and suitability for use as replacements.
5.13 The Contractor shall replace the AGM-600s in Buildings 907 and 1639. The contractor shall provide separate options to replace the AGM-600/60s in Buildings 510, 21200, and
518. The Government priorities for the replacements is:
Priority Building Option
1 907 No 2 1639 No 3 510 Yes 4 21200 Yes 5 518 Yes
5.14 The contractor shall provide training on the installed system to include the following:
• An overview of the system and its major components
• The operation of the system with all controls and indicators
• The startup and shut down of the system
• The maintenance of the system both preventive and corrective (removal and replacement of components).
CDRL A013, DII-ILSS-80872, Training materials
5.15 The Contractor shall provide a warranty covering parts and labor on the system for a minimum of one (1) year or the manufacturer’s warranty whichever is longer.
5.16 The Contractor shall provide an optional service level agreement (SLA) to begin the day after installation is completed for one year and optional annual renewal for three years.
5.17 The Contractor shall supply an electronic copy and one hard copy of the vendor manuals applicable to the supplied system.
6 GOVERNMENT-PROVIDED SUPPORT
6.1 Vandenberg SFB SLD 30/RM will coordinate access to the sites.
7 OBJECTIVES
7.1 As part of the required testing for this effort, the supplier shall conduct installation and checkout that will demonstrate that all functional requirements have been completed.
CDRL A004, DI- MISC-80508B, Post-Installation Checkout and Operational Acceptance.
CDRL A009, DI- MISC-80508B, Product Indenture Report (PIR)
8 DELIVERABLES
8.1 An Integrated Master Schedule (IMS) shall be provided to the government NLT 5 days prior to project kickoff.
CDRL A005, DI-IPSC-82297, Production Roadmap/Integrated Master Schedule
8.2 If any milestones cannot be met on time, the supplier shall send a notice to the Space Force Program Manager (SFPM) with an explanation for the delay and an updated schedule.
9 General Information
9.1 Place of Performance and Hours of Work. The Contractor shall perform tasks primarily at buildings listed in Section 2.1. Normal operating hours are 7:00 am to 5:00 pm (Eastern Time) Monday through Friday. Local and/or Vandenberg Space Force Base procedures will be followed during inclement weather.
9.2 Recognized Holidays. Unless otherwise required by the Government, the Contractor shall not have access to Government facilities to work or telework on all federal holidays or during facility closings as authorized by the Government. All federal holidays will be observed including New Year’s Day, Martin Luther King’s Birthday, Washington’s Birthday, Memorial Day, Juneteenth, Independence Day, Labor Day, Columbus Day, Veteran’s Day, Thanksgiving Day, Christmas Day, and any other day designated by Federal
Law, Executive Order, or Presidential Proclamation, including energy days. If the holiday falls on Saturday, it is observed on Friday. If the holiday falls on a Sunday, it is observed on Monday.
9.3 Operations Security (OPSEC). The purpose of OPSEC is to reduce the vulnerability of USAF missions to adversary collection and exploitation of critical information. The Contractor shall comply with DoDD 5205.02E “DoD Operations Security”, DoD Manual 5205.02-M and AFI 10-701 “Operations Security” to protect United States (U.S.
Government interest. The Contractor shall ensure compliance with OPSEC requirements including procedures to protect classified and/or sensitive, but unclassified, Government projects and/or programs.
9.4 Contractor Identification. Contractor personnel shall wear visible identification designating them as contractors at all times while on Vandeburg Space Force Base.
9.5 Contractor Vehicle Entry. The Contractor shall contact the Vandeburg Space Force Base Visitor's Center to and comply with local procedures for obtaining credentials and vehicle entry.
9.6 Contractor’s Safety Program. The Contractor shall establish and maintain an acceptable safety program in accordance with their accepted Safety and Health Plan. The Air Force is part of the OSHA Voluntary Protection Program (VPP). All shall familiarize themselves with the requirements of VPP. Information on the VPP can be accessed at http://www.osha.gov/dcsp/vpp/index.html. Additionally, the Contractor is responsible for the safety and health of all subcontractor employees. No more than two Class C mishaps per contract year and Zero Class A or B mishaps will be tolerated. All changes to the plan must also be submitted in writing and approved by the Government.
• Safety and Health Plan: Within 10 calendar days after contract award, the contractor shall email a copy of their company Safety Plan that is required to ensure compliance with the Occupational Safety and Health Act (OSHA) (Public Law 91-596). The Safety Plan will be provided to the Safety Office for review. The Safety Office will provide acceptance or non-acceptance within 5 working days of receipt to the government point-of-contact who will notify the CO.
CDRL A006, DI-SAFT-82080, Contractor's Safety Plan
9.7 Mishap Notification. The Contractor shall notify the Vandenberg SFB Safety Office telephonically at (805) 606-8806 and the Chief of Safety (805) 605-7250, within four (4) hours after initial notification of all mishaps or incidents for damage to DoD property (material plus labor) entrusted by this contract and employee injuries as a result of the contract operation. A follow-up (written or e-mail) of this mishap/incident notification shall be sent within three calendar days to the Government Representative, the Procurement Contracting Officer (PCO) or the Administrative Contracting Officer (ACO) (with a copy to program manager), who will forward it to the Safety Office. The information that is not available at the time of the initial notification shall be provided within 20 calendar days after the mishap. Mishap notification shall contain, at a minimum, the following information:
http://www.osha.gov/dcsp/vpp/index.html
a. Contract, Contract Number, Name and Title of Person(s) Reporting
b. Date, Time and exact location of accident/incident
c. Brief Narrative of accident/incident (Events leading to accident/incident)
d. Cause of accident/incident, if known
e. Estimated cost of accident/incident (material and labor to repair/replace)
f. Impound Authority Name and Phone Number (as applicable)
g. Nomenclature of equipment and personnel involved in accident/incident
h. Corrective actions (taken or proposed)
i. Other pertinent information
CDRL A007, DI-SAFT-81563, Accident/Incident Report
10. CDRLs
Exhibit Title SOO Para
Delivery
A001 Technical Manual 5.4 No Later Than (NLT) Ten (10) Calendar days following initial evaluation
A002 Test/Inspect Report 5.4 No Later Than (NLT) Ten (10) Calendar days following initial evaluation
A003 Proposed Spare Parts Listing 5.11 No Later Than (NLT) Ten (10) Calendar days following completion
A004 Post-Installation Checkout and Operational Acceptance.
7.1 No Later Than (NLT) Ten (10) Calendar days
following initial evaluation
A005 Production Roadmap/Integrated Master Schedule
8.1 No Later Than (NLT) Ten (10) Calendar days
following initial evaluation
A006 Contractor's Safety Plan 9.6 No Later Than (NLT) Ten (10) Calendar days following contract award
A007 Accident/Incident Report 9.7 Three (3) calendar days after mishap A008 Engineering Documentation Product
Drawings (Re-Procurement)
2.4 No Later Than (NLT) Ten (10) Calendar days
following initial evaluation A009 Technical Report - Product Indenture
Report (PIR)
7.1 No Later Than (NLT) 10 days before the No Later
Than (NLT) Ten (10) Calendar days following initial evaluation / Site Survey Design TIM
A010 Meeting Agenda 11.0 No Later Than (NLT) Three (3) Calendar days prior to scheduled meeting.
A011 Meeting Presentation 11.0 No Later Than (NLT) Three (3) Calendar days prior to scheduled meeting.
A012 Meeting Minutes 11.0 No Later Than (NLT) Three (3) Calendar days following scheduled meeting.
A013 Training Materials 5.13 No Later Than (NLT) 10 days before the scheduled training.
11. PROJECT MANAGEMENT APPROACH
The supplier shall create a project management approach that will provide the government with sufficient insight into schedule and performance for the duration of the project. The project management approach should include the following milestones:
• Kickoff
• Information Assurance (IA) Working Group
• Design TIM with PIR and RSPR
• Integrated Logistics Support (ILS) TIM
• Installation Readiness Review (IRR) TIM Checklist
• Functional/OA Testing
• Combined Validation/Verification
• Functional/Physical Configuration Audit Report
• Product Support Plan (PSP)
• Readiness Review Board (RRB) Checklist
CDRL A010, DI-ADMN-81249C, Meeting Agenda CDRL A011, DI-ADMN-81373, Meeting Presentation CDRL A012, DI-ADMN-81250C, Meeting Minutes CDRL A009, DI-MISC-80508B, Product Indenture Report (PIR)
12. GOVERNMENT POINTS OF CONTACT
The Space Force Project Manager is Kyrstynne Coleman
Commercial: 805-605-2420 DSN: 275-2420
Email: Kyrstynne.Coleman.1@spaceforce.mil
| 1 BACKGROUND |
| 2 SCOPE |
| 3 PERIOD OF PERFORMANCE: Eleven (11) Twelve (12) months for required replacements with an additional twelve (12) months for optional CLINs. |
| 4 PROJECT DESCRIPTION |
| 4.2 Table 1 contains the reference Requirement Statement (RS) that providing Range-level justification for this effort: |
| 4.3 Description Of New Capability/Requirement: |
| Justification: The current AGM600 battery plants are obsolete and are no longer supported by the manufacturer. Diminishing Manufacturer Source Material Shortage (DMSMS) cases for modulators DM-09-0069, rectifiers DM-09-0152, resistors DM-10-0015, and... |
| Impact/Risk: Without spare parts, the power plants cannot be maintained. LTRS equipment that relies on -48VDC power at instrumentation will eventually lose capability and cease to function. |