QUESTIONS AND ANSWERS

SOLICITATION # FA8132‐18‐R‐0013

ICE MACHINE & REVERSE OSMOSIS MACHINE MAINTENANCE

SERVICES

TINKER AFB, OK

QUESTION # 1: Do Personal Protective Equipment (PPE) requirements apply?

ANSWER # 1: No, the Contractor will not be working in an area which requires the use of PPE

QUESTION # 2: Does Tool Control apply?

ANSWER # 2: No, it does not apply to this requirement.