QuestionsAnswers.pdf
PDF 87 KB Posted
- Attached to
- Ramp Surveliiance
- Solicitation number
- FA8126-11-Q-0075
About this file
Questions/Answers
View the file
Other files
| File | Type | Posted |
|---|---|---|
| 11-Q-0075-0006.pdf | ||
| Amendment 0006.pdf | ||
| SOW Revision .pdf | ||
| Amendment -0005.pdf | ||
| FA8126-11-Q-0075-U00004.pdf | ||
| Correct Amendment for FA8126-11-Q-0075.pdf | ||
| Basemap.pdf | ||
| Bldg935.pdf | ||
| Amendment.pdf | ||
| Revised SOW.pdf | ||
| Bldg260.pdf | ||
| East Ramp area.pdf | ||
| Questions Answers.pdf | ||
| Amendment-0002.pdf | ||
| 11-Q-0075-0001.pdf | ||
| 5 jan 11 SOW 11-Q-0075.pdf | ||
| SOO 11-Q-0075.pdf | ||
| Combined Synopsis 11-Q-0075 .docx | DOCX document |
Show all 18
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Questions – FA8126-11-Q-0075
1. What government person will the contractor be coordinating with to complete DIACAP?
Winning bidder will have the capability to directly submit documentation for approval; project manager may review periodically to identify progress.
2. What templates will be provided to the contractor (winning bidder) to complete the DIACAP documentation package?
There are no specific templates for doing a DIACAP package. A spreadsheet of the controls is available which has been pulled from the system that the DIACAP packages are done in.
2. Who is the Designated Approving Authority (DAA) for the system?
DAA is the current Commander, AFNIC/EV, and is not at this base.
3. Who is the Certifying Authority (CA) for the system?
Same answer as #2
4. What government representative will act as the Certifying Agent responsible for validating the system controls?
Susan McClintick, 72 ABW/SCXS
6. Who is the government System Owner (Project Manager)?
This project will be supporting the aircraft maintenance group. A project manager will be provided to the winning bidder.
7. Has the government determined the Mission Assurance Level (MAC) and Confidentiality Level (CL) for the system?
Yes, MAC III, sensitive
8. Besides the DoD 8500.2, what component level (Air Force) or local security policies are required to be integrated into the system?
We only have AF level security policies, none locally.
9. What system will be used to register and track the DIACAP project?
EITDR until 1 March 2011, then eMASS thereafter.