This document is a Solicitation Amendment for a contract to fabricate five (5) B-52 Bomb Bay Stands, issued by the Air Force Sustainment Center at Tinker Air Force Base. The amendment extends the solicitation response deadline from 6 March 2025 to 24 March 2025 at 12:00 PM CDT and replaces the Statement of Work (SOW) and Attachment 1 drawing with updated versions. The procurement is a small business set-aside with a commercial firm fixed-price contract approach, targeting one vendor selection. Technical evaluation criteria include welding certification, manufacturing at the contractor's facility, disassembly and reassembly at Tinker AFB, specific painting requirements, and weld inspection by a Certified Weld Inspector.
The solicitation requires contractors to have an active DD Form 2345 through the Joint Certification Program to receive technical drawings, with award determination based on technically acceptable proposals at the lowest evaluated price. Vendors must provide a detailed written explanation of how they will meet technical evaluation criteria, with a simple "I concur" response being unacceptable. The government reserves the right to award no contract or conduct interchanges with vendors if deemed necessary, emphasizing the importance of submitting comprehensive initial proposals.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| A24-010 - B-52 Bomb Bay Stands -Statement of Work - Rev 4_Redacted.pdf | ||
| Solicitation - FA812525Q00310002.pdf | ||
| A24-010 - B-52 Bomb Bay Stands -Statement of Work - Rev 3_Redacted.pdf | ||
| Solicitation Amendment FA812525Q00310001 SF 30.pdf | ||
| Q and A Bomb Bay Stands_20Feb25.pdf | ||
| Solicitation - FA812525Q0031.pdf | ||
| A24-010 - B-52 Bomb Bay Stands-Statement of Work-Rev 2_Redacted.pdf |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
R
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers is extended. is not extended.
Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:
(a) By completing items 8 and 15, and returning copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;
or (c) By separate letter or electronic communication which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by letter or electronic communication, provided each letter or electronic communication makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
12. ACCOUNTING AND APPROPRIATION DATA (If required)
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.
IT MODIFIES THE CONTRACT/ORDER NUMBER AS DESCRIBED IN ITEM 14.
CHECK ONE A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT ORDER
NUMBER IN ITEM 10A.
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation data, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority)
E. IMPORTANT: Contractor is not is required to sign this document and return copies to the issuing office.
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15A. NAME AND TITLE OF SIGNER (Type or print) 16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)
15B. CONTRACTOR/OFFEROR
(Signature of person authorized to sign)
15C. DATE SIGNED 16B. UNITED STATES OF AMERICA
(Signature of Contracting Officer)
16C. DATE SIGNED
Previous edition unusable STANDARD FORM 30 (REV. 11/2016) Prescribed by GSA FAR (48 CFR) 53.243
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT 1. CONTRACT ID CODE PAGE OF PAGES
2. AMENDMENT/MODIFICATION NUMBER 3. EFFECTIVE DATE 4. REQUISITION/PURCHASE REQUISITION NUMBER 5. PROJECT NUMBER (If applicable)
6. ISSUED BY CODE 7. ADMINISTERED BY (If other than Item 6) CODE
8. NAME AND ADDRESS OF CONTRACTOR (Number, street, county, State and ZIP Code) (X) 9A. AMENDMENT OF SOLICITATION NUMBER
9B. DATED (SEE ITEM 11)
10A. MODIFICATION OF CONTRACT/ORDER NUMBE
10B. DATED (SEE ITEM 13)
CODE FACILITY CODE
SECTION SF 30 BLOCK 14 CONTINUATION PAGE
SUMMARY OF CHANGES
FIRST: The purpose of this amendment is to hereby replace the Statement of Work (SOW) in its entirety.Block 14 (Description of Amendment/Modification):
FROM: A24-010 - B-52 Bomb Bay Stands - Statement of Work - Rev 3_Redacted TO: A24-010 - B-52 Bomb Bay Stands - Statement of Work - Rev 4_Redacted SECOND: Update Clause 52.212-2 Evaluation to coincide with the updates made in the SOW.
THIRD: Replace the Attachment 1 Drawing in its entirety.
FROM: Attachment 1 - B52 Bomb Bay Stands Assembly Plans DWG X202316190, SH 1 thru 28 TO: Attachment 1 - B-52 BOMB BAY STAND Rev A - X202316190 FOURTH: Extend the closing date as follows:
FROM: 6 March 2025, 12:00 PM CST TO: 24 March 2025, 12:00 PM CDT FIFTH: All other terms and conditions remain unchanged and in full force and effect.
Solicitation/Contract Form
The following changes have been made:
INFORMATION FROM TO
Response Due Date 06 Mar 2025 24 Mar 2025
List of Attachments
The following attachments were added:
A24-010 - B-52 Bomb Bay Stands -Statement of Work - Rev 4_Redacted
The following attachments were deleted:
A24-010 - B-52 Bomb Bay Stands -Statement of Work - Rev 3_Redacted
Evaluation Factors for Award
Miscellaneous text in this section has been modified to:
52.212-2 EVALUATION--COMMERCIAL PRODUCTS AND COMMERCIAL SERVICES) (NOV 2021)
(a) The Government will award a contract resulting from this solicitation to the responsible offeror whose offer conforming to the solicitation will be most advantageous to the Government; price and other factors considered. The following factors shall be used to evaluate offers:
1. Basis for Contract Award:
The acquisition will be conducted and evaluated under the provisions of FAR Part 12, Commercial Items and FAR Part 13, Simplified Acquisition Procedures. In accordance with FAR 13.106-2(b)(1), the evaluation procedures established herein are within the Contracting Officer's broad discretion as applied under FAR Part
13. This acquisition will utilize Technically Acceptable and price as evaluation factors. Technical tradeoffs will not be made, and no additional credit will be given for exceeding acceptability. Award will be made to the acceptable vendor who is technically acceptable with the lowest total evaluated price and whose proposal conforms to the solicitation requirements. The solicitation requirements include all stated terms, conditions, representations, certifications, and all other information required by FAR 52.212-1 of this solicitation. The Government reserves the right to award without interchanges. However, the Government reserves the right to conduct interchanges if determined necessary by the Contracting Officer.
The responsible vendor(s) must be registered in the System for Award Management (SAM) database (available at: https://www.sam.gov/portal/public/SAM/) and submit a completed copy of the Offeror Representations and Certifications - Commercial Items with their response. Lack of registration in SAM will disqualify the vendor and declare them ineligible for award.
The Oklahoma CityAir Logistics Center (AFSC/PZIMA) at Tinker Air Force Base Oklahoma intends to issue a commercial firm fixed price contract for this acquisition.
2. Number of Contracts to be Awarded:
The Government intends to select one vendor for contract award. However, the Government reserves the right to award no contract at all; depending on the quality of the proposals, prices submitted and the availability of funds, or other factors identified by the Contracting Officer.
3. Rejection of Unreasonable Offers:
The Government may reject any proposal that is evaluated to be unrealistic in terms of program commitments, including contract terms and conditions, or unrealistically high or low in cost/price when compared to Government estimates; such that the proposal is deemed to reflect an inherent lack of competence or
FA812525Q00310002
failure to comprehend the complexity and risks of the program, item, or service.
4. Correction Potential of Proposals:
The Government will consider, throughout the evaluation, the "correction potential" of any proposal uncertainty. The judgment of such "correction potential" is within the sole discretion of the Government. If an aspect of a vendor's proposal not meeting the Governments requirements is not considered correctable, the vendor may be eliminated.
5. Evaluation Factors
Factor 1--Technical Proposal Factor 2--Cost/Price
a. Evaluation Methodology:
The Government will evaluate all technical factors concurrently for the three (3) lowest priced proposals. Should one of those three (3) proposals not be found technically acceptable, the next one (1) lowest priced offeror will be reviewed for technical acceptance. Then, price will be evaluated and the lowest evaluated priced proposal will be selected, either initially or as a result of clarifications.
Award will be made to the lowest evaluated priced proposal meeting the acceptability standards for the non-cost factors.
b. Technical Factor:
Acceptable - The proposal meets specified minimum technical evaluation requirements necessary for acceptable contract performance.
Unacceptable - The proposal fails to meet specified minimum technical evaluation requirements necessary for contract performance. Proposals with an unacceptable rating are not awardable.
Technical acceptability will be based on an evaluation of proposals against the criteria stated below and other technical specifications in the Item Description.
Offerors are required to present all the information as stated in the Instructions to Offerors, FAR 52.212-1. The minimum technical evaluation requirement is met when the Offeror's proposal thoroughly substantiates all the following essential criteria:
"CONTRACTOR MUST PROVIDE A WRITTEN STATEMENT TO EXPLAIN HOW THEY ARE MEETING THE TECHNICAL EVALUATION CRITERIA LISTED BELOW. A STATEMENT OF "I CONCUR" OR "CONCUR" WILL NOT BE ACCEPTED AND COULD DEEM YOUR PROPOSAL TECHNICALLY UNACCEPTABLE. THE WRITTEN STATEMENT IS ESSENTIAL FOR YOUR QUOTE TO BE RESPONSIVE AND BE REFERRED FOR TECHNICAL REVIEW."
TECHNICAL EVALUATION CRITERIA
Fabrication of Five (5) B52 Bomb Bay Stands shall be constructed in accordance with the SOW and Attachment 1 - B-52 BOMB BAY STAND Rev A - X202316190.
The contractor shall provide 6G or D1.1 welding certification at time of proposal. In accordance with section 2.2 of the SOW.
The B-52 Bomb Bay Stands shall be built at manufacture's facility, disassembled, shipped, and re-assembled at Tinker AFB. In accordance with sections 2 and 3 of the SOW.
All Stands shall be painted with OSHA Safety 13591 YELLOW or Equivalent IAW FED STD 595C and a Safety Data Sheet (SDS) will be provided to the SME at time of final acceptance. In accordance with sections 2 and 3 of the SOW.
Certified Weld Inspector (CWI) shall inspect all welds for cracks. In accordance with section 2 and 3 of the SOW.
c. Cost/Price Factor:
Cost/Price Evaluation: The vendor's cost/price proposal will be evaluated for award purposes by adding the total price for basic requirements (basic award).
Total Evaluated Price: Price analysis will be performed to determine the reasonableness of the vendor's price proposal. Reasonableness will be based on the total evaluated price. The total evaluated price will be calculated as the sum of the Contract Line Item Numbers (CLINs) unit/extended prices plus other associated factors such as: first article testing costs, transportation costs, price evaluation adjustments for Small Disadvantaged Business Concerns, and application of labor hours to labor hour rates, etc.
Unreasonably Low Costs or Prices: Unreasonably low proposed costs or prices, initially or subsequently, may be grounds for eliminating a proposal from competition either on the basis that the offeror does not understand the requirement or the offeror has made an unrealistic proposal.
Unbalanced Pricing: Vendors are cautioned against submitting an offer that contains unbalanced pricing. Unbalanced pricing may increase performance risk and could result in payment of unreasonably high prices. Unbalanced pricing exists when, despite an acceptable total evaluated price, the price of one or more contract line items is significantly over or understated as indicated by the application of cost or price analysis techniques. The Government shall analyze offers to determine whether they are unbalanced with respect to separately priced line items or subline items. Offers that are determined to be unbalanced may be rejected if the contracting officer determines that the lack of balance poses an unacceptable risk to the Government.
6. Determination of Contractor Responsibility
To be eligible for award, a vendor must be determined responsible. A Determination of Contractor Responsibility will be conducted in accordance with FAR 9.1 (SAM and FAPIIS). A vendor who receives a determination of non-responsibility will not be eligible to receive the contract award.
7. Interchanges:
In accordance with FAR 1.102-2(c)(3) the Government shall exercise discretion, use sound business judgement, and comply with applicable laws and regulations during the course of this acquisition. It is the Government's intent to award without interchanges; therefore, it is imperative that vendors submit their best terms initially. However, if during the evaluation period; it is determined to be in the best interest of the Government to hold interchanges, the Government may conduct interchanges with one, some, or all vendors before issuing any purchase order.
Interchanges are information sharing between the Government and vendors after receipt of quotations which can be conducted to address any aspect of the quotation. Interchanges may be oral or written. Written interchanges take the form of Interchange Notices (IN)s. INs are used to accurately capture contemporaneous sharing of information. If interchanges are conducted, the Government may request final quotation revisions at the conclusion of interchanges.
8. SOLICITATION REQUIREMENTS, TERMS AND CONDITIONS
Vendors are required to meet all solicitation requirements, such as terms and conditions, representations and certifications, and technical requirements, in addition to those identified as evaluation factors or sub-factors, and all technical specifications of the item description, performance work statement or statement of work.
Failure to meet a requirement may result in an offer being ineligible for award. Vendors must clearly identify any exception to the solicitation terms and conditions and provide complete accompanying rationale. In the case that a discrepancy exist between the Instruction to Offerors (ITO) and the evaluation factors for award, the evaluation criteria in 52.212-2 will take precedence.
(End of provision)
| SUMMARY OF CHANGES |
| Solicitation/Contract Form |
| List of Attachments |
| Evaluation Factors for Award |
| IDCode: J |
| Page: 1 |
| Pages: 4 |
| AmendNo: 0002 |
| EffDate: 13 Mar 2025 |
| ReqNo: |
| ProjNo: |
| IssCode: FA8125 |
| AdmCode: |
| IssuedBy: FA8125 AFSC PZIMA |
3001 STAFF DR STE 2S76, CP 405 734 9107
TINKER AFB, OK 73145-3303
UNITED STATES
Linsey Laird, Email: linsey.laird@us.af.mil Telephone: 405-739-9117 AdminBy:
SCD: PAS:
| ContractorNameAdd: |
| Code: |
| FacCode: |
| SolChg: 1 |
| SolNo: FA812525Q0031 |
| SolDate: 04 Feb 2025 |
| AwardChg: Off |
| AwardNo: |
| AwardDate: |
| Amended: 1 |
| OffrExt: 1 |
| OffrNoEx: Off |
| NoCopies: 1 |
| ApprData: See Section G - Contract Administration Data |
| ChgeOrd: Off |
| ChgeOrder: |
| Modify: Off |
| SuppAgre: Off |
| SuppAuth: |
| ModOthr: Off |
| OthrSpec: |
| NoReq: Off |
| Require: Off |
| Copies: |
| Descript: See Schedule |
| ContNameTitle: |
| CoNameTitle: Jason Shirazi |
| ContDate: |
| CODate: 13 Mar 2025 |
File details come from the government source that posted it. Updated .