1. CONTRACT NUMBER
on off
Arial bold
QUARTERLY ASSESSMENT REPORT
Arial bold left on
MONTHLY or on off off
Arial off global
CHECK8
Attach continuation sheet(s) if necessary
Arial plain center on
2. MONTH
on off
Arial
Times New Roman plain off
CHECK8
FIELD6
plain off
FIELD5
CHECK1
3. OVERALL PERFORMANCE SUMMARY
on off
Arial plain off
CHECK2
FIELD14
ACCEPTABLE
on off
Arial off
Helvetica plain
FIELD6
CHECK2
UNACCEPTABLE
on off
Arial off
Helvetica plain
CHECK1
FIELD9
TO: AFOTEC/A-7K
on off
Arial
Contractor:
on off
Arial plain off
FIELD9
CHECK3
5. Monthly Performance Assessment: (Utilize the Contractor Performance Assessment Reporting (CPAR) definitions and notes provided below.)
on off
Arial
6. ASSESSMENT SUMMARY: (Describe any performance issues noted during the month/quarter, any corrective actions taken. Reference PWS para for each issue.)
on off
Arial
EXCEPTIONAL
on off
Arial
VERY GOOD
on off
Arial
SATISFACTORY
on off
Arial
MARGINAL
on off
Arial
UNSATISFACTORY
on off
Arial off
Helvetica plain
FIELD14
CHECK4
off
Helvetica plain
CHECK3
CHECK5
off
Helvetica plain
CHECK4
CHECK6
off
Helvetica plain
CHECK5
CHECK7
off
Helvetica plain
CHECK6
FIELD27
Exceptional. Performance meets contractual requirements and exceeds many to the Government's benefit. The contractual performance of the element or sub-element being assessed was accomplished with few minor problems for which corrective actions taken by the contractor was highly effective.
Note: To justify an Exceptional rating, you should identify multiple significant events in each category and state how it was a benefit to the GOVERNMENT. However, a singular benefit could be of such magnitude that it alone constitutes an Exceptional rating. Also, there should have been NO significant weaknesses identified.
on off
Helvetica bold text/rtf {\rtf1\ansi\ansicpg1252\deff0\deflang1033{\fonttbl{\f0\fswiss\fprq2\fcharset0 Arial;}} {\colortbl ;\red0\green15\blue0;} \viewkind4\uc1\pard\cf1\b\f0\fs14 Exceptional. \b0 Performance meets contractual requirements and exceeds many to the Government's benefit. The contractual performance of the element or sub-element being assessed was accomplished with few minor problems for which corrective actions taken by the contractor was highly effective.\par \tab\i Note: To justify an Exceptional rating, you should identify \ul multiple\ulnone significant events in each category and state how it was a benefit to the GOVERNMENT. \ul However, a singular benefit could be of such magnitude that it alone constitutes an Exceptional rating\ulnone . Also, there should have been NO significant weaknesses identified.\par
Very Good. Performance meets contractual requirements and exceeds some to the Government's benefit. The contractual performance of the element or sub-element being assessed was accomplished with some minor problems for which corrective actions taken by the contractor was effective.
Note: To justify a Very Good rating, you should identify a significant event in each category and state how it was a benefit to the GOVERNMENT. Also, there should have been NO significant weaknesses identified.
on off
Helvetica bold text/rtf {\rtf1\ansi\ansicpg1252\deff0\deflang1033{\fonttbl{\f0\fswiss\fprq2\fcharset0 Arial;}} {\colortbl ;\red0\green0\blue0;} \viewkind4\uc1\pard\cf1\b\f0\fs14 Very Good. \b0 Performance meets contractual requirements and exceeds some to the Government's benefit. The contractual performance of the element or sub-element being assessed was accomplished with some minor problems for which corrective actions taken by the contractor was effective.\par \tab\i Note: To justify a Very Good rating, you should identify a significant event in each category and state how it was a benefit to the GOVERNMENT. Also, there should have been NO significant weaknesses identified.\par
Satisfactory. Performance meets contractual requirements. The contractual performance of the element or sub-element contains some minor problems for which corrective actions taken by the contractor appear or were satisfactory.
Note: To justify a Satisfactory rating, there should have been only minor problems, or major problems the contracotr recovered from without impact to the contract. Also, there should have been NO significant weaknesses identified. Per DoD policy, a fundamental principle of assigning ratings is that contractors will not be assessed a rating lower than Safisfactory solely for not performing beyond the requirements of the contract.
on off
Helvetica bold text/rtf {\rtf1\ansi\ansicpg1252\deff0\deflang1033{\fonttbl{\f0\fswiss\fprq2\fcharset0 Arial;}} {\colortbl ;\red0\green0\blue0;\red0\green15\blue0;} \viewkind4\uc1\pard\cf1\b\f0\fs14 Satisfactory.\b0 Performance meets contractual requirements. The contractual performance of the element or sub-element contains some minor problems for which corrective actions taken by the contractor appear or were satisfactory.\cf2\par \tab\cf1\i Note: To justify a Satisfactory rating, there should have been only minor problems, or major problems the contracotr recovered from without impact to the contract. Also, there should have been NO significant weaknesses identified. Per DoD policy, a fundamental principle of assigning ratings is that contractors will not be assessed a rating lower than Safisfactory solely for not performing beyond the requirements of the contract.\par
Unsatisfactory. Performance does not meet most contractual requirements and recovery is not likely in a timely manner. The contractual performance of the element or sub-element contains a serious problem(s) for which the contractor's corrective actions appear or were ineffective.
Note: To justify an Unsatisfactory rating, you should identify multiple events in each category that the contractor had trouble overcoming and state how it impacted the GOVERNMENT. However, a singular problem could be of such serious magnitude that it alone constitutes an unsatisfactory rating. An unsatisfactory rating should be supported by referencing the management tools used to notify the contractor of the contractual deficiencies (e.g. Management, Quality, Safety, or Environmental Deficiency Reports, or letters).
on off
Helvetica bold text/rtf {\rtf1\ansi\ansicpg1252\deff0\deflang1033{\fonttbl{\f0\fswiss\fprq2\fcharset0 Arial;}} {\colortbl ;\red0\green15\blue0;} \viewkind4\uc1\pard\cf1\b\f0\fs14 Unsatisfactory. \b0 Performance does not meet most contractual requirements and recovery is not likely in a timely manner. The contractual performance of the element or sub-element contains a serious problem(s) for which the contractor's corrective actions appear or were ineffective.\par \tab\i Note: To justify an Unsatisfactory rating, you should identify \ul multiple\ulnone events in each category that the contractor had trouble overcoming and state how it impacted the GOVERNMENT. However, a singular problem could be of such serious magnitude that it alone constitutes an unsatisfactory rating. An unsatisfactory rating should be supported by referencing the management tools used to notify the contractor of the contractual deficiencies (e.g. Management, Quality, Safety, or Environmental Deficiency Reports, or letters). \par plain off
CHECK7
BUTTON1
RELEASABILITY: Access to this form is restricted: this form is For Official Use Only (FOUO) when filled in; requests for accessibility must be approved by the OPR.
Arial bold
AFOTEC Form 5 on off
Arial off off pagedone #PAGE2.global
4. FROM: (NAME OF COR)
on off
Arial off global
CHECK8
Performance does not meet some contractual requirements. The contractual performance of the element or sub-element being assessed was accomplished with some serious problems, but recovery was still possible. Corrective actions taken by the contractor were marginally effetive or were not fully implemented.
Arial
Marginal.
Arial
NOTE: To justify marginal performance, you should identify a significant event in each category that the contractor had trouble overcoming and state how it impacted the GOVERNMENT. A marginal rating should be supported by referencing the managment tool used to notify the contractor of the contractual deficiency (e.g. Managment, Quality, Safety, or Environmental Deficiency Report or letter).
Arial italic
882EE41B-CD74-4ED8-8455-D850DC93273D
960;1260
PAGE2
off off pagedone #PAGE1.global
FIELD7
AFOTEC Form 5, 20080301 (reverse) (Test Form) on off
Arial bold text/rtf {\rtf1\ansi\ansicpg1252\deff0\deflang1033{\fonttbl{\f0\fnil\fprq2\fcharset0 Arial;}} {\colortbl ;\red0\green15\blue0;} \viewkind4\uc1\pard\cf1\b\f0\fs16 AFOTEC Form 5, 20080301 \i (reverse)\i0 (Test Form)\par
7. POTENTIAL PROBLEM AREAS: (List areas of concern including the surveillance process now used, items should be discussed at next progress meeting.)
on off
Arial plain off fixed on global
FIELD2
8. CHANGES: (Upcoming personnel changes, contractor or SOW changes, contract modification.)
on off
Arial
RELEASABILITY: Access to this form is restricted: this form is For Official Use Only (FOUO) when filled in; requests for accessibility must be approved by the OPR.
on off
Arial bold left plain off fixed off
FIELD8
Functional Commander/Director (FC/FD) on off
Arial bold plain off date
Enter date as 31 JAN 1999
Signature_Button plain off off
FIELD2
Signature_Button string
PRINT NAME & INDICATE TITLE
on off
Arial plain center
Contracting Officer's Representative (COR) on off
Arial bold
SIGNATURE
on off
Arial plain
DATE
on off
Arial bold plain off date
Enter date as 31 JAN 1999
Signature_Button plain off off
FIELD2
Signature_Button string
Other files for this federal contract opportunity
Show all 50
OPERATIONAL TEST AND EVALUATION SERVICES (OTES) has more files on GovTribe.
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
File details come from the government source that posted it. Updated .