Cyber Assessment Engineering and Technical Support Cost Model.xlsx
XLSX spreadsheet 25 KB Posted
- Solicitation number
- FA7037-11-R-0002
About this file
Cost Model
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Amendment 0002.docx | DOCX document | |
| Conformed Solicitation.docx | DOCX document | |
| LM Correlation Matrix - 19Jan11.xlsx | XLSX spreadsheet | |
| Amendment 0001.docx | DOCX document | |
| Q A -compiled-1-25-11.docx | DOCX document | |
| FA7037-11-R-0002 | — | |
| FA7037-11-R-0002 Atch 1.pdf | ||
| FA7037-11-R-0002 Atch 5.pdf | ||
| FA7037-11-R-0002 Atch 3.pdf | ||
| FA7037-11-R-0002 Atch 6.pdf | ||
| FA7037-11-R-0002 Atch 4.pdf | ||
| FA7037-11-R-0002 Atch 2.pdf | ||
| FA7037-11-R-0002 Atch 1.pdf | ||
| FA7037-11-R-0002 Atch 4.pdf | ||
| FA7037-11-R-0002 Atch 3.pdf | ||
| FA7037-11-R-0002 Atch 2.pdf | ||
| FA7037-11-R-0002 | — | |
| FA7037-11-R-0002 Atch 6.pdf | ||
| FA7037-11-R-0002 Atch 5.pdf | ||
| SOW - 92nd Cyber Assessment.pdf |
Show all 20
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Instructions The rates used in this cost model are for illustrative purposes only. They have been selected for no other reason than to indicate where the Contractor's rates should be entered into the spreadsheet. They are not target rates, and have no relation to the Government's Estimate. Each Contractor should overtype the existing rates with their own company rates. The rates that should be overtyped have been highlighted in yellow.
CPFF Basic
| CPFF RATES | ||||||||||
| The Offeror is Required to Enter their audited labor rates in Column B and company overhead rates, etc. in Row 3. The completed cost model will be used in the Cost or Price Evaluation as stated in the RFP. | Base Hourly Wage | Labor Overhead | Subtotal | Overhead | Subtotal | ODC | G&A | Subtotal | Fee | Loaded Wage |
| 10.00% | 10.00% | 0.50% | 10.00% | 5.00% | ||||||
| Technical Writer | 10 | 1 | 11 | 1.1 | 12.1 | 0.06 | 1.22 | 13.38 | 0.67 | 14.05 |
| Network Engineer (Intermediate) | 10 | 1 | 11 | 1.1 | 12.1 | 0.06 | 1.22 | 13.38 | 0.67 | 14.05 |
| Computer Security Systems Specialist (Intermediate) | 10 | 1 | 11 | 1.1 | 12.1 | 0.06 | 1.22 | 13.38 | 0.67 | 14.05 |
| Software Systems Engineer (Intermediate) | 10 | 1 | 11 | 1.1 | 12.1 | 0.06 | 1.22 | 13.38 | 0.67 | 14.05 |
| Training Specialist | 10 | 1 | 11 | 1.1 | 12.1 | 0.06 | 1.22 | 13.38 | 0.67 | 14.05 |
| Project Control Specialist | 10 | 1 | 11 | 1.1 | 12.1 | 0.06 | 1.22 | 13.38 | 0.67 | 14.05 |
| Configuration Management Specialist | 10 | 1 | 11 | 1.1 | 12.1 | 0.06 | 1.22 | 13.38 | 0.67 | 14.05 |
| Senior Engineer | 10 | 1 | 11 | 1.1 | 12.1 | 0.06 | 1.22 | 13.38 | 0.67 | 14.05 |
&F Contractor Name &A
CPFF 1st Option
| CPFF RATES | ||||||||||
| The Offeror is Required to Enter their audited labor rates in Column B and company overhead rates, etc. in Rows 3 and 44. The completed cost model will be used in the Cost or Price Evaluation as stated in the RFP. | Base Hourly Wage | Labor Overhead | Subtotal | Overhead | Subtotal | ODC | G&A | Subtotal | Fee | Loaded Wage |
| Escalation | 1.00% | 10.00% | 10.00% | 0.50% | 10.00% | 5.00% | ||||
| Technical Writer | 10.1 | 1.01 | 11.11 | 1.11 | 12.22 | 0.06 | 1.23 | 13.51 | 0.68 | 14.19 |
| Network Engineer (Intermediate) | 10.1 | 1.01 | 11.11 | 1.11 | 12.22 | 0.06 | 1.23 | 13.51 | 0.68 | 14.19 |
| Computer Security Systems Specialist (Intermediate) | 10.1 | 1.01 | 11.11 | 1.11 | 12.22 | 0.06 | 1.23 | 13.51 | 0.68 | 14.19 |
| Software Systems Engineer (Intermediate) | 10.1 | 1.01 | 11.11 | 1.11 | 12.22 | 0.06 | 1.23 | 13.51 | 0.68 | 14.19 |
| Training Specialist | 10.1 | 1.01 | 11.11 | 1.11 | 12.22 | 0.06 | 1.23 | 13.51 | 0.68 | 14.19 |
| Project Control Specialist | 10.1 | 1.01 | 11.11 | 1.11 | 12.22 | 0.06 | 1.23 | 13.51 | 0.68 | 14.19 |
| Configuration Management Specialist | 10.1 | 1.01 | 11.11 | 1.11 | 12.22 | 0.06 | 1.23 | 13.51 | 0.68 | 14.19 |
| Senior Engineer | 10.1 | 1.01 | 11.11 | 1.11 | 12.22 | 0.06 | 1.23 | 13.51 | 0.68 | 14.19 |
&F Contractor Name &A
CPFF 2nd Option
| CPFF RATES | ||||||||||
| The Offeror is Required to Enter their audited labor rates in Column B and company overhead rates, etc. in Rows 3 and 44. The completed cost model will be used in the Cost or Price Evaluation as stated in the RFP. | Base Hourly Wage | Labor Overhead | Subtotal | Overhead | Subtotal | ODC | G&A | Subtotal | Fee | Loaded Wage |
| Escalation | 1.10% | 10.00% | 10.00% | 0.50% | 10.00% | 5.00% | ||||
| Technical Writer | 10.21 | 1.02 | 11.23 | 1.12 | 12.35 | 0.06 | 1.24 | 13.65 | 0.68 | 14.33 |
| Network Engineer (Intermediate) | 10.21 | 1.02 | 11.23 | 1.12 | 12.35 | 0.06 | 1.24 | 13.65 | 0.68 | 14.33 |
| Computer Security Systems Specialist (Intermediate) | 10.21 | 1.02 | 11.23 | 1.12 | 12.35 | 0.06 | 1.24 | 13.65 | 0.68 | 14.33 |
| Software Systems Engineer (Intermediate) | 10.21 | 1.02 | 11.23 | 1.12 | 12.35 | 0.06 | 1.24 | 13.65 | 0.68 | 14.33 |
| Training Specialist | 10.21 | 1.02 | 11.23 | 1.12 | 12.35 | 0.06 | 1.24 | 13.65 | 0.68 | 14.33 |
| Project Control Specialist | 10.21 | 1.02 | 11.23 | 1.12 | 12.35 | 0.06 | 1.24 | 13.65 | 0.68 | 14.33 |
| Configuration Management Specialist | 10.21 | 1.02 | 11.23 | 1.12 | 12.35 | 0.06 | 1.24 | 13.65 | 0.68 | 14.33 |
| Senior Engineer | 10.21 | 1.02 | 11.23 | 1.12 | 12.35 | 0.06 | 1.24 | 13.65 | 0.68 | 14.33 |
&F Contractor Name &A
CPFF 3rd Option
| CPFF RATES | ||||||||||
| The Offeror is Required to Enter their audited labor rates in Column B and company overhead rates, etc. in Rows 3 and 44. The completed cost model will be used in the Cost or Price Evaluation as stated in the RFP. | Base Hourly Wage | Labor Overhead | Subtotal | Overhead | Subtotal | ODC | G&A | Subtotal | Fee | Loaded Wage |
| Escalation | 1.00% | 10.00% | 10.00% | 0.50% | 10.00% | 5.00% | ||||
| Technical Writer | 10.31 | 1.03 | 11.34 | 1.13 | 12.47 | 0.06 | 1.25 | 13.78 | 0.69 | 14.47 |
| Network Engineer (Intermediate) | 10.31 | 1.03 | 11.34 | 1.13 | 12.47 | 0.06 | 1.25 | 13.78 | 0.69 | 14.47 |
| Computer Security Systems Specialist (Intermediate) | 10.31 | 1.03 | 11.34 | 1.13 | 12.47 | 0.06 | 1.25 | 13.78 | 0.69 | 14.47 |
| Software Systems Engineer (Intermediate) | 10.31 | 1.03 | 11.34 | 1.13 | 12.47 | 0.06 | 1.25 | 13.78 | 0.69 | 14.47 |
| Training Specialist | 10.31 | 1.03 | 11.34 | 1.13 | 12.47 | 0.06 | 1.25 | 13.78 | 0.69 | 14.47 |
| Project Control Specialist | 10.31 | 1.03 | 11.34 | 1.13 | 12.47 | 0.06 | 1.25 | 13.78 | 0.69 | 14.47 |
| Configuration Management Specialist | 10.31 | 1.03 | 11.34 | 1.13 | 12.47 | 0.06 | 1.25 | 13.78 | 0.69 | 14.47 |
| Senior Engineer | 10.31 | 1.03 | 11.34 | 1.13 | 12.47 | 0.06 | 1.25 | 13.78 | 0.69 | 14.47 |
&F Contractor Name &A
Rate Table
| CPFF RATES | ||||
| Labor Category | Basic | First Option | Second Option | Third Option |
| Technical Writer | 14.05 | 14.19 | 14.33 | 14.47 |
| Network Engineer (Intermediate) | 14.05 | 14.19 | 14.33 | 14.47 |
| Computer Security Systems Specialist (Intermediate) | 14.05 | 14.19 | 14.33 | 14.47 |
| Software Systems Engineer (Intermediate) | 14.05 | 14.19 | 14.33 | 14.47 |
| Training Specialist | 14.05 | 14.19 | 14.33 | 14.47 |
| Project Control Specialist | 14.05 | 14.19 | 14.33 | 14.47 |
| Configuration Management Specialist | 14.05 | 14.19 | 14.33 | 14.47 |
| Senior Engineer | 14.05 | 14.19 | 14.33 | 14.47 |
&A, &F