This Performance Work Statement (PWS) details the Air Force Technical Applications Center's (AFTAC) requirement for Geophysical Instrumentation Testbeds (GIT) development and operationalization. The project involves establishing 8 total testbeds - 4 seismic testbeds at Operating Location Boulder, WY (OL-BW) and 4 testbeds (2 digitizer and 2 infrasound) at AFTAC's Patrick Space Force Base location in Florida. Key contract deliverables include developing pass/fail requirement documents for digitizer, infrasound, and seismic tests, completing operational reports for both AFTAC and OL-BW testbeds, and providing comprehensive training for personnel at each location.

The contract will have a base period of 12 months with two additional 12-month option years. The contractor will be responsible for purchasing necessary materials, completing operational documentation, and training personnel to independently operate and maintain the geophysical testbeds. Reporting requirements include monthly financial and technical status reports, quarterly Technical Interchange Meetings, an Integrated Master Schedule, and specific deliverables like pass/fail requirement documents and operational reports. The effort aims to enable AFTAC and OL-BW to evaluate and characterize geophysical equipment of interest after contract completion.

View the file

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

PERFORMANCE WORK STATEMENT (PWS)

FOR

GEOPHYSICAL INSTRUMENTATION TESTBEDS

AFTAC/709th SAG

11 Apr 2025

1 DESCRIPTION OF SERVICES

1.1 INTRODUCTION

1.2 BACKGROUND

1.3 SCOPE

1.4 PERIOD OF PERFORMANCE

2 PERFORMANCE OBJECTIVES

2.1 PASS/FAIL REQUIREMENTS DOCUMENT

2.2 AFTAC OPERATIONAL REPORT

2.3 OL-BW OPERATIONAL REPORT

2.4 TRAINING FOR AFTAC AND OL-BW TESTBEDS

3 GOVERNMENT FURNISHED SUPPLIES AND SERVICES

3.1 SERVICES

3.2 FACILITIES

3.3 UTILITIES

3.4 EQUIPMENT

3.5 MATERIALS

4 SPECIAL REQUIREMENTS/INSTRUCTIONS

4.1 CONTRACTOR IDENTIFICATION IN THE GOVERNMENT WORKPLACE

4.2 INDUSTRIAL SECURITY

4.3 LOCATION(S) OF WORK

4.4 HOURS OF OPERATION

4.5 CONSERVATION OF UTILITIES

4.6 CONTRACTOR MANPOWER DATA REPORTING

4.7 ENVIRONMENTAL CONTROLS

4.8 SAFETY REQUIREMENTS (IF APPLICABLE)

4.9 KICK-OFF MEETING AND PERIODIC PROGRESS MEETINGS

4.10 CONTRACTOR TRAVEL

4.11 PROGRAM MANAGEMENT

5 DELIVERABLES

1 DESCRIPTION OF SERVICES.

1.1 Introduction.

This is a non-personal services contract. The Government will neither supervise contractor employees nor control the method by which the contractor performs the required tasks. The contractor shall manage its employees and guard against any actions that are of the nature of personal services, or give the perception of personal services. The contractor shall notify the Contracting Officer (CO) immediately if they perceive any actions constitute personal services. These services shall not be used to perform any Inherently Governmental Functions.

1.2 Background.

The primary purpose is to complete development and operationalization of AFTAC’s Geophysical Instrumentation Testbeds (GIT); 4 seismic testbeds located at the Operating Location of Boulder, WY (OL-BW) and 4 testbeds (2 digitizer and 2 infrasound), located at the Air Force Technical Applications Center (AFTAC), Patrick Space Force Base, FL. Deliverables include development of pass/fail requirement documents for digitizer, infrasound, and seismic tests, completion of the operational report for the AFTAC testbeds, and completion of the operational report for the OL-BW testbeds. Also, training will be provided at each location, AFTAC and OL-BW, so that personnel from each location will be able to use their knowledge of the GIT system and provided documentation to continue with the GIT effort. When the GIT effort is complete, the geophysical testbeds at OL-BW and AFTAC will be used to evaluate and characterize geophysical equipment of interest.

1.3 Scope.

The contractor shall be responsible for developing a pass/fail requirements document which will provide a requirement for each digitizer, infrasound, and seismic test.

The contractor will have the ability to purchase the necessary materials to meet the performance objectives listed below. The contractor shall complete the operational report for the AFTAC testbeds and complete the operational report for the OL-BW testbeds. Finally, the contractor shall provide training for each location, AFTAC and OL-BW, so that the personnel from each location will be able to run tests themselves using their knowledge of the GIT system.

1.3.1 Contractor shall provide a pass/fail requirements document which covers each digitizer, infrasound, and seismic test.

1.3.2 Contractor shall provide an operational report for the AFTAC testbeds.

1.3.3 Contractor shall provide an operational report for the OL-BW testbeds.

1.3.4 Contractor shall provide testbed training for both the AFTAC and OL-BW testbeds.

1.4 Period of Performance.

The period of performance shall be for one (1) Base Year of 12 months and two (2) 12-month option years.

2 PERFORMANCE OBJECTIVES

2.1 Pass/Fail requirements document

The government will review and approve each requirements document (CDRL A005). The contractor shall use the government-approved document to provide:

The pass/fail requirements which will be applied to all digitizer tests.

The pass/fail requirements which will be applied to all infrasound tests.

The pass/fail requirements which will be applied to all seismic tests.

2.2 AFTAC Operational Report

The contractor shall provide an operational report for the AFTAC testbeds in accordance with government specifications (CDRL A006). The operational report will include the progress made to operationalize each AFTAC testbed. This will include which equipment was tested, how AFTAC personnel performed, and list any improvements to better the operational process.

2.3 OL-BW Operational Report

The contractor shall provide an operational report for the OL-BW testbeds in accordance with government specifications (CDRL A007). The operational report will include the progress made to operationalize each OL-BW testbed. This will include which equipment was tested, how OL-BW personnel performed, and list any improvements to better the operational process.

2.4 Training for AFTAC and OL-BW Testbeds

The contractor shall provide training, using the testbed specific Technical Instruction (TI) and Laboratory Procedure (LP), to the appropriate government and contract personnel at AFTAC and OL-BW. Three training sessions are anticipated for each location for each contract year. Training shall cover the operation and maintenance of the geophysical testbeds as well as how to perform the laboratory procedures using the geophysical testbeds. The contractor shall successfully demonstrate:

a) Qualification, troubleshooting, and maintenance of the testbed(s), and

b) RSQ, PFS, or PSS test for Government selected UUT(s), from start to finish, using the laboratory procedures.

3 GOVERNMENT FURNISHED SUPPLIES AND SERVICES.

3.1 Services.

The Government will provide support for the contractor to get base access for the AFTAC location. The Government will sponsor for the contractor to obtain a vehicle pass, obtain building access, and obtain access to room 1550 to perform the required tasks. For OL-BW, the POC will allow the contractor access to perform the required tasks.

3.2 Facilities.

The Government will provide the necessary workspace for the contractor to provide the support outlined in the PWS to include desk space, telephones, and computers.

3.3 Utilities.

The Government will provide all utilities in the facility for the contractir’s use in performance of tasks outlined in the PWS.

3.4 Equipment.

The Government will provide tools and UUT for each testbed location so the contractor can perform the assigned duties.

3.5 Materials.

The Government will provide the purchased materials at each location for the contractor to perform the required tasks.

4 SPECIAL REQUIREMENTS/INSTRUCTIONS.

4.1 Contractor Identification in the Government Workplace.

When conversing with Government personnel during business meetings, over the telephone or via electronic mail, the contractor shall identify themselves as such to avoid situations arising where topics might be better discussed solely between

Government employees. The contractor shall identify themselves on any attendance sheet or any coordination documents they may review. Electronic mail signature blocks shall identify their company affiliation.

4.2 Industrial Security.

This is an unclassified effort. The contract employee shall be a US citizen and able to access a military installation.

4.3 Location(s) of Work.

The work to be performed under this contract shall be performed at:

Albuquerque, NM and Melbourne, FL, contractor site(s) Boulder, WY, at OL-BW Patrick Space Force Base, FL at AFTAC

4.4 Hours of Operation.

4.4.1 Normal Hours of Operation. The contractor shall perform the services required under this contract during the following hours: Mon - Fri, 0800- 1700, except federal holidays.

4.4.2 Recognized Holidays. The contractor is not required to provide service on the following days:

New Year’s Day Labor Day Dr. Martin Luther King’s

Birthday Columbus Day

Presidents’ Day Veterans Day Memorial Day Thanksgiving Day

Juneteenth Independence Day

Christmas Day

4.4.2.1 If the holiday falls on Saturday, it is observed on Friday. If the holiday falls on a Sunday, it is observed on Monday.

4.4.2.2 The contractor shall not report for duty and will not be reimbursed by the Government when the Government facility is closed due to a Federal holiday, local or national emergencies, administrative closings, or similar Government directed facility closings.

4.5 Conservation of Utilities.

The contractor shall operate under conditions which prevent the waste of utilities which include the following:

4.5.1 Lights shall be used only in areas where and when work is actually being performed.

4.5.2 Mechanical equipment controls for heating, ventilation, and air conditioning systems shall not be adjusted by the contractor unless authorized.

4.5.3 Water faucets or valves shall be turned off after the required use has been accomplished.

4.5.4 Government telephones shall be used only for official Government business.

4.6 Contractor Manpower Data Reporting.

4.6.1 Contractor shall be an entity registered in SAM, an individual SAM user account with the Entity Administrator, Entity Registration Representative, or Reporter role for that entity, and one or more contracts awarded to that entity which meet the SCR reporting thresholds.

4.6.2 Steps for Submitting a Service Contract Report (SCR).

4.6.2.1 Go to www.sam.gov and log in.

4.6.2.2 Select Entity Registrations and then select Service Contract Reporting.

4.6.2.3 SAM displays your entities which have service contracts and meet the reporting criteria. Select View by entity to see the service contracts for each entity.

4.6.2.4 Next, select Add for the service contract against which you want to create a Service Contract Report. Each service contract which meets the FAR Subpart 4.1703 reporting thresholds is displayed.

4.6.2.5 Next, the Complete Service Contract Report page will be displayed. SAM displays the contract details and allows you to report. Contractor is required to enter the following information:

4.6.2.5.1 Total Amount Invoiced: Total dollar amount invoiced for services performed during the previous Government fiscal year under the contract (this amount should include the prime and any subcontract amount).

4.6.2.5.2 Prime Contractor Hours Expended: Prime contractor direct labor hours expended on the services performed during the previous Government fiscal year. The amount you enter is automatically divided by 2,080 hours to calculate a Full Time Employee (FTE) equivalent, displayed under the Prime Contractor Hours Expended as Prime Contractor FTEs.

4.6.2.6 Report any required Tier 1 subcontractor information by selecting the Add Tier 1 Subcontract Information button.

4.6.2.7 When you are ready to submit the report, select Submit. This saves your report and returns you to the Select Service Contract page where you can create other SCRs or edit an existing SCR.

4.6.3 Annual Reporting. Reporting inputs will be for the direct labor executed during the period of performance (PoP) which runs 1 September through 31 August. While inputs may be reported any time during the FY, all data shall be reported no later than 30 September of each calendar year. The contractor shall provide reporting inputs for the final PoP of this contract no later than 30 calendar days after contract expiration. The contractor may direct technical questions about the SAM Service Contract Reporting tool to the Federal Service Desk FSD at https://www.fsd.gov/fsd-gov/home.do

4.7 Environmental Controls.

4.7.1 Compliance with Laws and Regulations. The contractor shall be knowledgeable of and comply with all applicable Interstate, Federal, State, and Local laws, regulations, and requirements regarding environmental protection. In the event environmental laws or regulations change during the term of this contract, the contractor shall comply as such laws come into effect. If there is an increase or decrease in cost as a result of the change, the contractor shall inform the CO pursuant to notice requirements and negotiate a modification to the contract.

4.7.2 Notification of Environmental Spills. If the contractor spills or releases any substance contained in 40 CFR 302 into the environment, the contractor shall immediately report the incident to the COR. The liability for the spill or release of such substances rests solely with the contractor.

4.8 Safety Requirements (If Applicable).

In performing work under this contract, the contractor shall:

4.8.1 Conform to the safety requirements contained in the contract for all activities related to the accomplishment of the work.

4.8.2 Take such additional immediate precautions as the CO may reasonably require for safety and mishap prevention purposes.

4.8.3 Record and report promptly (within one hour) to the CO or COR, all available facts relating to each instance of damage to Government property or injury to either contractor or Government personnel.

https://www.fsd.gov/fsd-gov/home.do

4.8.4 In the event of an accident/mishap, take reasonable and prudent action to establish control of the accident/mishap scene, prevent further damage to persons or property, and preserve evidence until released by the accident/mishap investigative authority through the CO.

4.8.5 If the Government elects to conduct an investigation of the accident/mishap, the contractor shall cooperate fully and support Government personnel conducting the investigation.

4.9 Kick-off Meeting and Periodic Progress Meetings.

The contractor shall attend an initial kick-off meeting 7 days after contract award.

The CO, COR, and other Government personnel, as appropriate, may meet periodically with the contractor to review the contractor's performance. At these meetings the CO will apprise the contractor of how the Government views the contractor's performance and the contractor will apprise the Government of problems, if any, being experienced. Appropriate action shall be taken to resolve outstanding issues. The contractor shall provide minutes of these meetings to the Government. (CDRL A003)

4.10 Contractor Travel.

Contractor shall be required to travel to other Government facilities during the performance of this contract in support of specific tasks to include attending meetings, perform duties, and to provide training. All travel requirements (including destination, purpose, plans, agenda, itinerary, number and names of personnel, and dates) shall be pre-approved by the COR. Contractor shall submit a trip report upon completion of travel. Any travel requirements not identified will need to be negotiated and the contract/order will need to be modified. (CDRL A008)

4.11 Program Management

The contractor shall provide financial status and technical status reports to project leads (CDRL A001 and CDRL A002). Quarterly Technical Interchange Meetings (TIMs) will be held at the contractor’s facility. The contractor shall provide meeting minutes after each TIM (CDRL A003). The contractor shall provide an IMS 30 days after contract award (CDRL A004) and update the IMS quarterly to indicate task progression.

5 DELIVERABLES.

Reports and other data required in this PWS shall be submitted IAW the Contract Data Requirements List (CDRL) listed below.

CDRL# Data Item Number

Data Item Description

PWS

Paragraph

Delivery Schedule

A001 DI-MGMT-

81468

Financial Status Report

4.11 Monthly

A002 DI-MISC-

80711A

Technical Status Report

4.11 Monthly

A003 DI-MISC-

80711A

TIM Minutes 4.11 Held quarterly; Due one week after each

TIM

A004 DI-MGMT-

81861 Integrated Master Schedule (IMS)

4.11 Within 30 calendar

days after contract award; updated quarterly; presented during the TIM

A005 DI-MISC-

80711A Pass/Fail requirement documents

2.1 Due NLT 30 days

prior to end of base year

A006 DI-MISC-

80711A Operational Report for AFTAC testbeds

2.2 Due NLT 30 days

prior to end of each contract year

A007 DI-MISC-

80711A Operational Report for OL-BW testbeds

2.3 Due NLT 30 days

prior to end of each contract year

A008 DI-MISC-

80711A Trip Report 4.10 Due one week after each trip

1 DESCRIPTION OF SERVICES.
1.1 Introduction.
1.2 Background.
1.3 Scope.
1.4 Period of Performance.
2 PERFORMANCE OBJECTIVES
2.1 Pass/Fail requirements document
2.2 AFTAC Operational Report
2.3 OL-BW Operational Report
2.4 Training for AFTAC and OL-BW Testbeds
3 GOVERNMENT FURNISHED SUPPLIES AND SERVICES.
3.1 Services.
3.2 Facilities.
3.3 Utilities.
3.4 Equipment.
3.5 Materials.
4 SPECIAL REQUIREMENTS/INSTRUCTIONS.
4.1 Contractor Identification in the Government Workplace.
4.2 Industrial Security.
4.3 Location(s) of Work.
4.4 Hours of Operation.
4.4.2.1 If the holiday falls on Saturday, it is observed on Friday. If the holiday falls on a Sunday, it is observed on Monday.
4.4.2.2 The contractor shall not report for duty and will not be reimbursed by the Government when the Government facility is closed due to a Federal holiday, local or national emergencies, administrative closings, or similar Government directed facil...
4.5 Conservation of Utilities.
4.6 Contractor Manpower Data Reporting.
4.6.2.1 Go to www.sam.gov and log in.
4.6.2.2 Select Entity Registrations and then select Service Contract Reporting.
4.6.2.3 SAM displays your entities which have service contracts and meet the reporting criteria. Select View by entity to see the service contracts for each entity.
4.6.2.4 Next, select Add for the service contract against which you want to create a Service Contract Report. Each service contract which meets the FAR Subpart 4.1703 reporting thresholds is displayed.
4.6.2.5 Next, the Complete Service Contract Report page will be displayed. SAM displays the contract details and allows you to report. Contractor is required to enter the following information:
4.6.2.5.1 Total Amount Invoiced: Total dollar amount invoiced for services performed during the previous Government fiscal year under the contract (this amount should include the prime and any subcontract amount).
4.6.2.5.2 Prime Contractor Hours Expended: Prime contractor direct labor hours expended on the services performed during the previous Government fiscal year. The amount you enter is automatically divided by 2,080 hours to calculate a Full Time Employe...
4.6.2.6 Report any required Tier 1 subcontractor information by selecting the Add Tier 1 Subcontract Information button.
4.6.2.7 When you are ready to submit the report, select Submit. This saves your report and returns you to the Select Service Contract page where you can create other SCRs or edit an existing SCR.
4.7 Environmental Controls.
4.8 Safety Requirements (If Applicable).
4.9 Kick-off Meeting and Periodic Progress Meetings.
4.10 Contractor Travel.
4.11 Program Management