Repair Small Arms Range, Bldg 701 Projects DZAQ 15‐0001A/B 1 18 November 2015

STATEMENT OF WORK

DESIGN‐BUILD

REPAIR SMALL ARMS RANGE, BLDG 701

Projects DZAQ 15‐0001A/B

911th Airlift Wing

Pittsburgh IAP

Air Force Reserve

PR ATTACHMENT 1

Projects DZAQ 15‐0001A/B 2 18 November 2015

Statement of Work Design-Build

Repair Small Arms Range, Bldg 701 Projects DZAQ 15-0001A/B

PITTSBURGH IAP ARS, PA

18 November 2015

1.1 BACKGROUND

This project focuses on Small Arms Range, Bldg 701 at the Clinton Training Area in Beaver County in the vicinity of the Pittsburgh Air Reserve Station (PARS) shown on the attached Project Location Maps (see Attachments 1 and 2). The range was built in 1997 as a “partially contained” range that has a covered firing line, side containment, 9 rows of overhead baffles, including one row that serves as the canopy baffle, that each spans the full 112’ width of the range, and a bullet trap/backstop. Each overhead baffle is 4’ wide and 8’ long and is constructed of two sheets of 3/8” thick steel plates, framed with wood 2x4s at 24” on center that are bolted to the steel plate to act as a substrate for the 3/4" thick plywood sheets that are covered with 1-1/2” thick eggcrate profiled acoustical foam. Individual baffles are butted together to form each set of the 9 rows of baffles that span the width of the range. Direct fire at the firing line is totally contained by the side containment, overhead baffles, and bullet trap, but direct fire forward of the firing line and ricochets are not totally contained, though reduced by the baffles and side containment. The foremost purpose of this project is to upgrade the range to a “fully contained” range that will totally contain both all direct fire and ricochets within the limits of the range by adding additional overhead baffles and supporting structures, in accordance with Air Force Engineering Technical Letter (ETL) 11-18: Small Arms Range Design and Construction (see Attachment 3). That ETL provides the minimum design criteria necessary for achieving a safe range design and shall be followed for this project in all aspects related to the baffles, unless modified by details of this Statement of Work (SOW). Since the range is being upgraded, it will be brought to that ETL’s standards for not only the baffles and other ballistic safety structures, but also for ventilation and noise control where feasible. It is the policy of the Air Force to use innovative and sustainable approaches to environmental management and technology to accomplish its mission. Sustainable projects do not deplete resources, cause environmental degradation, or impact to human health and may reduce the burden of compliance for the Air Force. Mission requirements are met while also balancing cost and environmental responsibility.

The Contractor shall incorporate pollution prevention and sustainability initiatives into all aspects of this contract.

1.2 SCOPE OF WORK

A. SUMMARY:

Repair Small Arms Range, Bldg 701, via a Design-Build (D-B) contract. This work consists of providing all design, materials, labor, and equipment necessary to Repair Small Arms Range, Bldg 701, by modifying or replacing existing overhead baffles and supporting structure and installing new additional overhead baffles and supporting structure; abating lead dust, lead bullet fragments and lead containing surface coatings; removing rubber panels from the firing range floor; repairing concrete floor; removing and refastening all existing rubber wall panels with

Projects DZAQ 15‐0001A/B 3 18 November 2015 approved adhesive after proper surface preparation of walls to ensure proper adhesion; installing additional ballistic rubber wall panels after proper surface preparation of walls to ensure proper adhesion; performing maintenance and repair to ventilation system; removing and reinstalling target retrieval system; removing and replacing baffle mounted lighting system and adding additional lighting; adding ducts though the wall to connect portable heater hoses; preparing and repainting exterior reinforced concrete walls; preparing and painting all existing and new exposed metal surfaces between firing line and front of bullet trap; preparing and painting all new panels on walls and all existing MEP panels and devices from the firing line back to including the back wall; replacing existing double doors with a roll-up coiling door; and repairing the gutter system on the roof over the bullet trap area of the range, all as detailed elsewhere in this SOW. This work is comprised of two repair projects, i.e., DZAQ 15-0001A and DZAQ 15-0001B, and costs related to those two projects must be separated in the Contractor’s bottom line proposed prices. Project DZAQ 15-0001A Small Arms Range, Bldg 701 Restoration and Modernization Repair is comprised of all work related to the existing and new overhead baffles, their supporting structures and their related painting; removal, storage, refurbishing mounting hardware and reinstallation of the target retrieval systems; removing and replacing baffle mounted lighting system and adding additional lighting; adding ducts though the wall to connect portable heater hoses; and installation of acoustic rubber panels on back and side walls behind the firing line where no panels are presently installed, along with the portions of all engineering and field overhead related to these tasks. Project DZAQ 15-0001B Small Arms Range, Bldg 701 Sustainment Repair is comprised of all remaining work specified in this SOW, including all abatement and disposal. Before submission of the proposal the Contractor shall address to the Contracting Officer (CO) any questions concerning whether specific tasks should be associated with either DZAQ 15-0001A or DZAQ 15-0001B. Contractor’s proposal shall reflect appropriate total price for each of the two projects, broken down further as construction cost and design cost for each project. Contractor’s proposal shall be submitted on Bid Schedule.

B. DESIGN:

1. The Contractor shall provide a complete Design with construction documents for the repair of the Small Arms Range, Bldg 701 as detailed elsewhere in this SOW. The Contractor shall be capable of addressing and interpreting all aspects of Unified Facilities Guide Specifications (UFGS) and the United Facilities Criteria (UFC) regarding this requirement. The Contractor shall provide Type A & B services. Type A services involve field investigations and surveys (topographic, geotechnical, etc.); similar fact finding surveys of the site essential to proper design; prepare reports and similar services not involved in the preparation of designs, plans, drawings, and specifications. Type B services include those items normally furnished by an A-E in the actual preparation of the design documents (plans, drawings, estimates, specifications, submittal register etc.) and include visual inspection of the site or facility for familiarization with scope, general conditions, and coordination with using activities. The Contractor shall complete the design in sufficient detail to enable construction operations inclusive of inspection validations and warranty mandates. Contractor shall provide design of all disciplines by licensed professional architects or engineers. The Contractor shall submit the design submittals as detailed elsewhere in this SOW. Final Design shall be stamped by a professional engineer licensed in the state of Pennsylvania, or in another state if approved by CO. The Contractor shall construct IAW approved drawings and specifications. Contractor shall not order any equipment or materials and shall not begin any phase of new construction

Projects DZAQ 15‐0001A/B 4 18 November 2015 until Government approves in writing the Final Design submittal. Contractor may not start any on site work prior to government approval of the Final Design.

2. Each iteration of the design shall be sent to the CO. These design drawings shall be well prepared, complete, and accomplished in accordance with the best professional practice to show clearly and concisely the type and extent of work to be performed based on the contract scope of work. These drawings and sketches shall be produced in AutoCAD. The drawings shall include the standard 911th signature block in the lower right-hand corner. The project title sheet shall have an index that lists the sheet number, sheet name, and CAD file name of each drawing in the set. Submit three full size hard copies and one electronic PDF copy of each iteration of the design.

3. Design Tasks.

a. Design Task 1: Site Visit/Kickoff/Investigation: The Contractor shall perform a site visit to gather data, investigate site conditions, and participate in a kickoff meeting with all pertinent installation organizations. Additional site investigation may be required based on the initial site visit. The Contractor will research all pertinent federal, state, and local environmental regulations and requirements and Air Force policies as they pertain to the project site and project concept.

b. Design Task 2: Contractor shall utilize the site visit assessment findings, investigation, research, and verification to produce design drawings, specifications, and design analysis.

c. Design Task 3: Design stages include the following:

Phase I (30%) Design Development Phase II (90%) Pre Final Review Final (100%) Final Issue/Construction Documents

5. Schedule: The design will be required to be accomplished to the schedule as shown below. A review meeting with the design architect/engineer will be scheduled once the Contractor has received comments from the Government and has had an opportunity to review the same. A review meeting shall occur at each phase.

a. Phase I of Design: (30%) Design Development Preliminary design development plans, outline specifications, and design analysis will be submitted 35 calendar days after notice to proceed. Government review comments on submission requirements on Phase I will be forwarded to the A-E within 21 calendar days after date of receipt from the A-E.

b. Phase II of Design: (90%) Pre Final Review Design development drawings, specifications, and design analysis will be submitted 35 calendar days after receipt of approval of Phase I. The design is to be 90% complete and fully detailed for technical review at this stage. Government review comments on submission requirements on Phase II will be forwarded to the A-E within 21 calendar days after date of receipt from the A-E.

c. Phase III of Design: (100%) Final Issue / Construction Documents Final submission of final drawings, specifications, and design analysis and calculations will be submitted 21 calendar days after receipt of approval of Phase II. If required, Government review comments on submission requirements on Phase III will be forwarded to the A-E within 14 calendar days after date of receipt from the A-E. All final drawings and specifications shall be clearly marked as “CONSTRUCTION SET” (or something similar). Final Mylar drawings, Projects DZAQ 15‐0001A/B 5 18 November 2015 specifications, and design analysis will be submitted 7 calendar days after receipt of the Government’s comments on the Submission of Phase III. The design is to be 100 percent complete at this stage.

6. Design Deliverables.

Provide submissions in hard copy (2 sets) full size and in electronic form on CD to the CO. In addition, at HQ AFRC, submittals are normally reviewed by four or five persons. In order to expedite the review process, provide one half-size drawing set, specifications, and design analysis, all hard copy only, for each submittal and send to: HQ AFRC/A7PM, Ed Rodgers, 549 Pine Street, Robins AFB GA 31098. Further, the Marine Corps Forces Reserve wishes to review the design. In order to expedite the review process, provide one half-size drawing set, specifications, and design analysis, all hard copy only, for each submittal and send to: Marine Corps Forces Reserve, Craig Monroe, 2000 Opelousas Ave., New Orleans, LA 70114.

7. Final documents will eventually serve as the basis for as-built documentation of the project and shall be provided electronically. In addition, provide compact discs (CDs) containing the following:

a. All updated Final Design AutoCAD drawing files (Drawings must be saved in compatible version with 2010 AutoCAD system – Contractor shall coordinate with CO prior to submission).

b. All updated Final Design (100%) drawings in .pdf format.

c. All analyses in .pdf format.

d. Entire compilation of specifications or Catalog Cut Sheets in .pdf format to clearly define types of materials and products used in Task 2.

8. Details of Design: Contractor shall repair the small arms range at the location shown in the attached Project Site Plan (see Attachment 4). Work involves lead abatement, demolition, repair and construction. The following details shall be included in the design and construction of this project:

a. Contractor shall field verify existing conditions prior to any construction activities. Contractor shall field verify all existing conditions, dimensions, and assemblies.

Include necessary exploratory work to verify concealed components deemed necessary.

Attached is a full set of the as-built drawings of the original construction of the Firing Range Complex in PDF format (see Attachment 5). The Government does not hold a CAD version of any of those drawings.

b. Review and evaluate existing electrical panel to determine what modifications or upgrades required to support replacement and additional lighting and roll-up coiling door electric motor operator to be installed.

c. Contractors that bring laser equipment onto Air Force installations shall comply with specifications Section 01410 Environmental Protection (see Attachment 6).

d. Contractor shall remove and dispose of all components of the firing range as required in the completion of work under this contract. All material that is removed shall become the property of the Contractor and removed from the site. Removed material leaving the site is to be weighed. The Air Reserve Station’s truck scale may be used for this purpose.

Contractor shall provide a report showing the amount of material removed from the site and to where it was transported. Material that can be recycled or is hazardous shall not be placed in a landfill.

Projects DZAQ 15‐0001A/B 6 18 November 2015

e. Work performed under this contract as described in this SOW may cause the disturbance of lead containing dust, bullet fragments and surface coatings. The Occupational Safety and Health Administration (OSHA) regulates worker lead exposure and has assigned a lead permissible exposure limit (PEL) of 50 micrograms per cubic meter (ug/m3) and an action level of 30 ug/m3 as an 8-hour time weighted average. Contractor assumes all risks in worker exposure to lead at the construction site. Contractors shall make their own assessment of the presence of lead and corresponding work practice for disturbance of lead coatings. Contractor shall ensure areas beyond work area are not contaminated as a result of work being performed.

f. Contractor is solely responsible for the health and safety of its workers during the execution of this contract. Work shall be conducted under the assumption that lead containing dust, bullet fragments and surface coatings will be encountered, and in accordance with all applicable local, state and federal regulations applicable to this work effort. The regulations and their successors shall be binding upon Contractor and considered part of this contract. The methods used to handle materials and precautions taken shall be determined by Contractor and responsibility for use of such methods shall be solely with the Contractor. All removed materials shall be placed in UN approved drums to be supplied by the Contractor. All waste materials, including incidental materials, contaminated with lead particulates or dust shall be removed or recycled if possible. Incidental materials may include HEPA-vacuumed dust or debris which may contain lead, filters containing lead, and personal protective clothing and equipment that has been contaminated with lead dust. All waste materials shall be properly containerized using UN approved drums. Comply with the following details related to handling, packaging, recycling, disposal, sampling, analysis, and additional requirement related to lead.

(1) Repackaging: Prior to shipping, recyclable material or waste such as the bullet particles from the collection canisters and lead dust from the hopper system should be consolidated and repackaged to the greatest extent possible. Material shall be repackaged for shipping in new contractor-supplied UN-approved drums or other packaging. Due to the high density of much of the waste, care shall be taken not to overfill drums past the allowable shipping or handling weight. During consolidation or transfer of lead particles from one container to another, dust control measures are required to prevent dust migration. Emptied containers that are not reusable shall be disposed of properly by the Contractor.

(2) Recycling: It is the intent of the contract to recycle all removed lead particulate and debris removed under the contract to the greatest extent possible; the Contractor may propose an alternate means of handling lead particulate and debris as needed for approval by the CO. The Contractor shall arrange for and coordinate recycling of all bullet fragments, dust, and incidental material to the greatest extent possible by: a. Verifying that the recycling facility specifically recycles lead fragments, dust, and other incidental materials. b. Verifying that the recycling facility has all required Federal, state, and local permits and approvals for lead recycling. c. Accomplishing all handling, transportation, disposal, and documentation requirements necessary, including loading material for transport if necessary. The Contractor shall comply with all DOT shipping requirements, including labeling, placarding, training, and manifesting. The Contractor shall weigh all filled containers prior to shipping off-site. d.

Coordinating loading and transportation of the shipment with the CO. Provide weight receipts from the recycling facility showing material acceptance. The receipts must be signed by an authorized employee of the recycling facility showing the facility received and processed the recyclable material.

(3) Disposal: The Contractor shall take care to segregate all removed materials properly and manage site work to minimize the amount of non-recyclable waste generated.

Projects DZAQ 15‐0001A/B 7 18 November 2015

Specific separate waste streams shall be identified in coordination with the Base Environmental Engineer. All waste shall be stored in new contractor-supplied UN-approved steel drums or containers. Containers shall only be opened to add waste and shall otherwise remain closed as waste accumulates. Full containers shall be stored at the job site in an area approved by the Base POC. All storage containers shall be labeled and/or marked properly to meet all Federal, State or local regulatory requirements. The Contractor shall be responsible for all proper labeling and marking and temporary storage in coordination with all pertinent regulations. All waste shall be properly disposed of by the Contractor in accordance with Federal and State regulations.

Certification of waste disposal including weights shall be provided to the CO. If required, the Contractor shall use EPA ID No. PAR000518688 for the facility to manifest hazardous waste from the site. Handling and disposition of hazardous waste shall be coordinated with the Base Environmental Engineer. All hazardous waste documents will be signed by the Base Environmental Engineer.

(4) Sampling and Analysis: Upon completion of the range cleaning and prior to clearance sampling, the Contractor shall conduct a visual inspection of areas potentially affected by the project. The purpose of the inspection is to determine whether the work was completed as required and whether visible settled dust or debris is present. The inspection shall include a surface-by-surface examination to determine if known or suspected lead dust surfaces are still present at the range. As required, the Contractor shall conduct Toxicity Characteristic Leaching Procedure (TCLP) analyses on each distinct waste stream to determine if hazardous wastes are present; samples shall be analyzed for metals in accordance with EPA test method 6010B.

(5) Additional Requirements: In the event of any hazardous material spill, the CO shall be notified immediately. The Contractor is entirely responsible for response actions, notifications, and cleanup of all spills resulting from his operations under this contract. All work performed under this contract must be performed by workers who are properly trained, and, where required by any Federal, state, or local laws or regulations, licensed or certified to perform the work required under this contract. The Contractor shall provide Safety Data Sheets (SDSs) to the CO for all hazardous materials used during the project. Usage of all hazardous materials shall be tracked and reported to the CO.

(6) Submittals: All required submittals shall be provided to the CO for approval. The Contractor shall submit for approval to the CO written evidence of training that demonstrates their personnel have been properly trained for lead abatement work (i.e. lead worker, lead supervisor, etc.) and 29CFR1926.62 Lead Safety and Health Regulations in Construction prior to commencement of work on-site. The Contractor shall provide certification to the CO that the recycling facility selected will, to the greatest extent practicable, recycle all bullet fragments, dust, filters and any other waste material generated under this contract. The Contractor shall provide a description of the method of recycling and information regarding the recycling facility along with documentation of proof of recycling. The Contractor shall provide copies of all required documentation regarding disposition of material including manifests, facility receipts, etc. to the CO. All shipping documents and manifests will be signed by the Base Environmental Engineer.

(7) Applicable Documents: The Contractor shall comply with all applicable federal, state, and local environmental statutes, instructions, manuals, handbooks, regulations, guidance, policy letters, and rules (including all changes and amendments in effect on the date of issuance of each TO). It is the Contractor's responsibility to identify all applicable federal, state, and local environmental statutes, instructions, manuals, handbooks, regulations, guidance, policy letters, and rules for all work performed and apply the procedures and protocols required.

Projects DZAQ 15‐0001A/B 8 18 November 2015

(8) Regulatory Interface: The Contractor shall assist in the application of general and site-specific regulatory requirements that pertain to the project and maintain currency with changing DOD, Federal, state, and local statutes and regulations as follows: The Contractor is not an employee of the government and shall not represent the government in an official or unofficial capacity without the express prior written permission from the CO. In the event that an unspecified regulatory representative approaches the Contractor with a stated intent to inspect the activities of the Contractor, the Contractor shall respectfully decline the inspection until the CO is properly notified and a duly appointed representative is present or other direction is issued by the CO. If this is not possible, due to project constraints, the Contractor shall notify the CO at the earliest possible time following the inspection.

(9) Health Risks: The Contractor shall immediately report to the CO and the Base POC, verbally by telephone or e-mail pursuant to the contract, any issues or incidents which may indicate potential imminent risk to contracted, federal, or local personnel, the public at large or the environment.

(10) Identification and Change of Critical Contractor Personnel: The Contractor shall immediately notify the CO of any changes in critical Contractor personnel. The Contractor shall obtain CO approval of any proposed changes in project personnel along with the steps taken/proposed to ensure there are no impacts to the schedule or costs associated with individual tasks. Identify to the CO all subcontractors to be used under contracts issued pursuant to this SOW, prior to signing any contract or initiating any work. Provide subcontractor qualifications to the CO prior to subcontractor utilization.

(11) Hazardous Waste Management: The Contractor shall comply with all regulations governing the control of hazardous waste from its origin to ultimate treatment, storage, or disposal, such as Resource Conservation and Recovery Act (RCRA), Hazardous and Solid Waste Act (HSWA), and AFI 32-7042, Solid and Hazardous Waste Management. Perform activities such as hazardous waste collection and accumulation site operations and management, sampling and analysis, The Contractor shall be responsible to ascertain and maintain documentation (including refresher courses as required) that all workers at a site have been properly trained in lead abatement verification.

(12) Record Keeping: The Contractor shall create and maintain in one location written records sufficient to recreate each sampling, analytical, testing and monitoring event. The Contractor shall make these records available to the government upon request or as specified in this contract.

g. Prior to starting on-site work, Contractor shall submit a complete written environmental and safety work plan. Contractor shall allow 7 calendar days for Government review and approval of that plan. On-site work shall not commence until Contractor receives the CO’s approval of that plan. That plan needs to address how the Contractor plans to manage the waste generated from this contract by recycling and disposal, minimization of hazardous waste generated, methods of lead abatement and segregation of waste streams to minimize the amount of non-recyclable wastes generated, and a sampling and analysis plan. The plan shall provide a complete explanation of the methods, materials, equipment and control procedures that will be implemented to ensure that the subject work is performed according to the applicable regulations and to ensure the continuous protection of Contractor's and CO's personnel and facilities.

h. Contractor shall remove and properly dispose of all eggcrate acoustical foam material, all of which shall be assumed to be contaminated with lead, from all existing baffles, and elsewhere in the range as directed by the CO.

Projects DZAQ 15‐0001A/B 9 18 November 2015

i. Contractor shall perform lead abatement from remaining existing structurally and architecturally related materials that are being removed, prior to their removal. Appropriately clean, by HEPA filter vacuuming or other approved methods, all surfaces that will be disturbed by this construction that are potentially contaminated with lead dust or bullet fragments to include, but not limited to, portions of walls, floors, ceilings, baffles, target retrieval systems and structural support system.

j. Perform lead abatement from existing HVAC related equipment and materials, prior to their repair and servicing.

k. Prior to removal test each target retrieval system for proper operations and report any deficiencies or malfunctions. Any deficiencies or malfunctions, other than cables, shall be reported to the Contracting Officer. Any deficiencies or malfunctions, other than cables or rusted components and mounting hardware of retrieval system or its suspension system, reported prior to removal of the systems may be repaired under an in-scope modification to this contract if funds are available and work via a modification is considered in the Government’s best interest. Carefully remove all portions of the target retrieval systems that could be damaged during construction from the 22 firing lanes. Store retrieval system for reinstallation after completion of all work on baffles and supporting structures. Contractor shall store removed systems off site or in Contractor provided containers on-site. Contractor shall be responsible for any damage to the systems once removed. Target retrieval systems were manufactured by Action Target Company and the operations and maintenance (O&M) manual for the systems is provided as Attachment 7.

l. Remove existing lighting system mounted on back side of baffles in the vicinity of the target line. Remove relate conduit and wiring back to the lighting controls mounted in the Control Room.

m. Remove and properly dispose of all plywood and 2x4s on existing canopy and all other overhead baffles. Portions of the wood may be considered contaminated with lead dust and bullet fragments.

n. Remove at least 7 of the existing 9 sets of overhead baffle assemblies, related hardware, and support structures and reinstall or replace them at new locations per Final Design, and provide additional new overhead baffle assemblies supported by new structural systems in appropriate locations as required by the design to provide full containment. Any existing components that are reused and reinstalled shall be properly prepared and repainted. The existing set of baffles and/or steel truss support system located at the canopy baffle and immediately at the bullet trap may remain or may be replaced, but if they remain, those sets of baffles shall be modified as needed and faced with new approved ballistic panels to match the facing of all the other overhead baffles. Steel plate of existing baffles may be reused for modified baffles, provided that both layered sheets are used together, but structural analysis of existing walls may determine reuse of that steel plate not advisable. Recycle steel plates and other metal parts that are not to be reused.

o. Remove and properly dispose of approximately 15% of the existing 2” thick, 2’ by 2’ acoustic rubber wall panels that are severely damaged and any existing 1.5” thick 2’ by 2’ rubber floor panels that are not reused on the walls.

p. Repair concrete floor of range by providing a 3-inch bonded reinforced concrete overlay of the entire floor from the firing line to the bullet trap. Prepare surface of existing concrete floor by appropriate means to roughen its texture sufficiently to enable the new concrete layer to become bonded to the existing concrete as if both strata were a single structure.

Reinforcement shall be 6-inch by 6-inch, 8/8-gauge welded wire fabric or other designed reinforcement. Design and locate floor slab joints to coincide with joints in existing floor.

Projects DZAQ 15‐0001A/B 10 18 November 2015

Sawed control joints no more than 6 millimeters (0.25 inch) wide are permitted. Traditional chamfered construction joints are not permitted. Concrete used shall have a minimum compressive strength of 3500 pounds per square inch (psi) and be of a fine, uniform-aggregate mix. The overlay shall be constructed by using a single pour between existing expansion joints and must have a smooth, steel-trowel-finish. No protrusions from the floor that could be struck by bullets are permissible to minimize the potential for unpredictable ricochets. All joints shall be sealed flush with the floor with appropriate backer and field molded sealant materials. The concrete floor shall not be painted and must be protected with a waterproof sealant.

q. Provide and install overhead baffles and structural support systems per Final Design. The total number of sets of overhead baffles and structural support systems, including the canopy baffles, shall be increased from 9 sets to as many as 27 sets (if all remain 4’ high and all other than the set of baffles serving as the canopy baffles and the set of baffles located immediately at the bullet trap are sloped at approximately 25 degrees from the horizontal) and positioned to provide a minimum of 6” horizontal overlap between the trailing edge of any baffle and the leading edge of the next baffle downrange required to produce a “fully contained” range per Figure 8 of ETL 11-18 (see Attachment 8), approximately as shown in the attached Planned Firing Range Cross Section (see Attachment 9). Design, angle and size of the overhead baffles shall determine the exact number and locations of the overhead baffles required. All details and notes of that Figure 8 shall be considered in designing and positioning the baffle systems, except modifying the existing 4’ wide canopy baffle to meet the specified 5 meter minimum width, which is not considered feasible due to the installed ventilation system above the firing line.

Overhead baffles shall be installed sloped at an appropriate angle from the horizontal, with their high point closest to the firing line for all except the canopy baffles, which shall have their high point closest to the target line.

r. The structural support system for the new additional baffle assemblies sets shall be of the same design as the existing steel truss support system or of a new design proposed by the Contractor. Structural design shall require the lowest possible maintenance effort for the structure that can fully meet the need. Regardless if Contractor uses design of the existing support system or proposes a new design, the design shall be reviewed, approved, and stamped by a registered professional architect/engineer in Pennsylvania, or in another state if approved by CO, to confirm the structural adequacy of the existing and any new designed baffle support system to support the modified and new overhead baffle assemblies. That architect/ engineer shall further confirm the structural adequacy of the existing walls to support all the designed baffle support systems and baffles. If structural calculations and analysis determines the existing walls will not support additional baffles using an intended design, then walls shall be reinforced as deemed appropriate or structural support system for baffles shall be redesigned using lighter weight system. The redesigned support system shall adequately support all required baffles and shall be able to be adequately supported by existing walls with appropriate modifications if necessary.

s. Small gutters or channels shall be installed on back of each row of baffles to channel rain water to within 1 foot of supporting walls, vice dripping throughout range onto floor.

t. All support systems and overhead baffle assemblies, except the one located immediately at the bullet trap, shall be installed so the bottom of all baffles are on a uniform and level plane a minimum of 8’ above elevation of the firing platform. Existing overhead baffles are only about 7’- 4” above the firing platform elevation. Design and construction to include raising the bearing point of the structural system on the walls if necessary to accommodate the

Projects DZAQ 15‐0001A/B 11 18 November 2015 higher clearance of the baffles and providing as appropriate new steel connection at top of existing concrete bearing walls, bearing plates and new connections to secure structural supporting members to existing concrete walls.

u. Construction of overhead baffles, including canopy baffles if replaced, shall be minimum 10 mm (0.375 in) thick AR500 steel plates with a nominal 500 BHN covered on their bottom faces with approved ballistic panels, vice the plywood specified in the ETL 11-18. Steel plate of existing baffles may be reused for modified baffles, provided that both layered sheets are used together and the existing walls will support their weight. The only ballistic panels presently approved for use on Air Force ranges are the 2” thick Range Systems Dura-Panels and the Troy Acoustics Troy System Panels. Any ballistic products installed in strict conformance with the manufacturer’s installation requirements. Construct ballistic safety structures with attention to the quality of the fabricated parts. Baffle plates with butt joints must fit together closely to prevent any gaps more than 0.0625” wide. Secure set of baffles to concrete side walls with continuous steel angles covered with ballistic panel material to prevent bullet escapement.

v. Exposed surfaces of all new and existing steel components of the baffles and structural support system shall be properly prepared and coated per appropriate guidance and standards that have been proven satisfactory for the intended use. All shop-applied prime coatings shall be compatible with field-applied top coatings.

w. Remove all existing 2” thick ribbed acoustic ballistic wall panels on all walls between the firing line and bullet trap. Dispose of severely damaged wall panels. Reusable panels shall be stored within the range until reinstalled.

x. Remove paint on walls to bare concrete and prepare walls to ensure proper adhesion.

y. All removed acoustic panels shall be reinstalled on the walls between the firing line and bullet trap from floor level to a height even with the top of the new overhead baffles using Range Systems approved adhesive directly to the concrete walls after appropriate surface preparation. Install acoustic panels starting at the firing line and moving toward bullet trap on each wall. When the available quantity of reusable acoustic panels is exhausted, install useable non-acoustic panels removed from the floor to finish covering the remainder of the wall to the bullet trap. Break line between acoustic and non-acoustic panels shall run from floor to top panels on each wall and shall be at approximately the same distance from the bullet trap on each of the four walls. Location of break lines on our four walls may differ by 2’, the width of a row of panels.

z. Install new minimum 1.5” thick acoustic panels at the rear wall and sidewalls of the firing line area of the range, covering as much of concrete block as is possible. New acoustic panels on walls shall be Range Systems Acoustic Dura-Panels or Troy Acoustics Panels.

Properly prepare concrete block walls prior to application of new acoustic panels.

aa. Replace existing double doors with a roll-up coiling door of approximate same size that will fit opening of removed doors. Door shall be equipped with electric motor operator and manual crank operator for use during power outage.

ab. Prepare and repaint exterior reinforced concrete walls, all exterior doors and frames, all supports for outdoor air louvers/hoods of supply fans, new rubber panels on walls and all existing MEP panels and devices from the firing line back to including the back wall. Paint color to be used is Sherwin Williams "copper haze" or comparable color from other manufacturers for all items except doors and frames. Paint color of doors and frames shall be Sherwin Williams "quail brown" or comparable color from other manufacturers.

Projects DZAQ 15‐0001A/B 12 18 November 2015

ac. Target retrieval systems shall be reinstalled on all 22 firing lanes. All rusted or corroded components and mounting hardware of retrieval system or its suspension system shall be prepared and repainted or replaced with new. Contractor shall reuse existing electrical wiring for target retrieval system unless previously noted as nonfunctional during testing before removal. All new wiring shall match existing.

ad. Install all new cables on the target retrieval systems of the 22 firing lanes. Test each retrieval system for proper operations and adjust as required. Any deficiencies that are discovered that were not reported prior to removal of the retrieval system shall be repaired by the Contractor at no additional cost to the Government.

ae. Modify or upgrade existing electrical panel as required to support replacement and additional lighting and roll-up coiling door electric motor operator to be installed.

af. Install replacement lighting system mounted on back side of baffles in the vicinity of the target line. Replace all wiring and conduit to replaced lights. New lighting shall meet the requirements of ETL 11-18 paragraph 7.2.11.3. New lighting shall be LED and if appropriate may reuse existing controls.

ag. Install new lighting system mounted on back side of baffles a second row of baffles in front of the firing line. Exact location to be determined during design. Lighting shall meet the requirements of ETL 11-18 paragraph 7.2.11.3. New lighting shall be LED and shall be on a separate circuit with new controls mounted in the Control Room.

ah. Remove and replace bullet trap acoustical quilts with comparable material and position and fasten new quilts or panels as appropriate without compromising integrity of the bullet trap.

ai. Remove and reinstall existing gutter at rear of the facility. When reinstalled it shall slope from center to both ends. Replace existing downspout at east end and construct new downspout at west end with extension under concrete sidewalk to drainage ditch north of the sidewalk. Provide splash block at the end of each downspout.

aj. Install four 11.75” OD round galvanized steel or PVC ducts with caps through wall for connection of trailer mounted portable heater flexible hoses (see Attachment 10 for approximate locations). Top of ducts shall be no higher than the top of the second course of CMU blocks.

ak. Recondition 11 existing supply fans and 11 existing exhaust fans by replacing the belts and cleaning the fan blades of each and by providing new supply air discharge grilles to avoid high velocity jets and initiate a laminar flow pattern. Install electronic speed controls or replace supply fan motors to make each variable speed, since full speed fan in winter makes it too cold at the firing line. Allow the fan speeds to run at maximum speed within noise limits discussed below. The supply fans are located in the rear wall behind the firing line and deliver 8,400 CFM each of supply air to push unconditioned outdoor air through the firing line, across the shooters, and out to the exhaust fans. The supply fans are standard wall propeller type equipped with an outdoor air louver on the fan upstream side and a supply air grille located flush with the interior surface of the wall on the fan discharge side. The fans are belt driven and are served by ¾ HP, 480 volt, 3 phase, 60 hertz motors. The fan located in the center of the building has a ducted discharge directing the supply air under the Observation Platform. This fan is equipped with a 1-1/2 HP 480 volt, 3 phase, 60 hertz motor. The fan motors are controlled by combination across the line motor starters with integral disconnects. The exhaust fans are located on the sloped roof above the firing line. These fans exhaust 76,230 CFM to atmosphere.

These fans are what are commonly called “Mushroom” fans. The roof curbs are equipped with gravity back draft dampers that close when the fan stops. The fans are belt driven and each is

Projects DZAQ 15‐0001A/B 13 18 November 2015 served by a 1 HP, 480 volt, 3 phase, 60 hertz motor. The fan motors are also controlled by combination across the line starters and are interlocked to run when the supply fans run.

al. Range ventilation performance will need to be validated prior to final inspection to ensure that proper ventilation is provided within the range. At the firing line, the air velocity must be a minimum of 23 meters per minute (mpm) (75 feet per minute [fpm]), ±4.6 mpm (15 fpm). Airflow should be evenly distributed across the firing line ±4.6 mpm (15 fpm). Noise from the ventilation system will not exceed 85 decibels (dBA) behind the firing line. Test and report speed and air flow delivery rate after fan modification and installation of additional acoustic baffles are completed. Adjust fans as necessary to achieve a minimum required air flow and speed across the firing line, even distribution, and noise within limits. The Contractor shall provide, prior to final inspection, a full testing and balancing report for all supply and exhaust equipment that was repaired.

am. After all repairs and construction have been completed, and before conducting training and qualification operations, Government Combat Arms (CA) personnel will conduct controlled test-firing using ball ammunition with witness screens as detailed in the ETL 11-18 as appropriate. Contractor shall provide witness screens and be present during test-firing, but Government CA personnel will do the firing and provide the weapons and ammunition required for the test. Any additional work determined to be required from the results of the test-firing, that are considered to be of no fault of the Contractor, may be accomplished under an in-scope modification to the contract if funds are available and work via a modification is considered in the Government’s best interest. Any rework or additional work deemed to be the responsibility of the Contractor shall be accomplished at no additional expense to the Government.

an. The Contractor will incorporate, to the realistic extent possible, guidelines and recommendations included in the revised "Federal Green Construction Guide for Specifiers" on the Whole Building Design Guide. http://fedgreenspecs.wbdg.org.

ao. Sustainable principles, to include Life Cycle cost-effective practices, will be integrated into the design, development, and construction of the project in accordance with Executive Order 13423, 10 USC 2802 (c), and other applicable laws and Executive Orders.

ap. The work site is to be well maintained and orderly. Excavated/demolished materials are to be removed from the Small Arms Range and the Clinton Training Area to an approved landfill or recycle location (as appropriate) as part of this contract in Contractor provided containers/trucks.

aq. Restore any disturbed turf areas with grass seed wherever they are disturbed by this project. Seed shall be fresh, clean, dry, new crop seed “Park West Premium Mix” or “Park West Maintenance Mix” supplied by Park West Supply, 729 Aten Road, Coraopolis, PA 15108, Tel 412-787-8235.

C. CONSTRUCTION:

The Contractor shall construct improvements as per the CO, approved in the Final Design.

Permitted deviations from the government-approved Final Design, due to unforeseen/ undocumented field conditions, shall be brought to the attention of, and approved by, the CO before any changes are made in the field during construction.

1. Construction activities will take place in the area shown in Attachments 1, 2 and 4.

The Contractor shall coordinate construction activities with the CO to ensure that the primary mission of Pittsburgh ARS is not compromised at any time during construction. Work hours are

Projects DZAQ 15‐0001A/B 14 18 November 2015

7:00 AM to 4:00 PM, Monday through Friday, excluding federal holidays. Gates to the work site will only remain open during normal work hours. Contractor will work under Air Force Occupational Safety and Health (AFOSH) and OSHA regulations. The small arms range will not be used by the Government during the period of construction. The Contractor is not responsible to provide alternate facilities. Contractor shall minimize down time of the range, so no lead remediation or demolition work shall be accomplished until Contractor is prepared to immediately follow the demolition work with new construction work. Contractor shall submit written notification not less than 30 calendar days in advance of the start of on-site construction and closure of the facility.

2. Contractor shall review and comply with all applicable requirements of specifications

Section 01410 Environmental Protection (see Attachment 6). That section discusses Safety Data Sheets (SDS). SDS will be required for any other Hazardous Materials (HAZMAT) brought on the Clinton Training Area. Due to the amount of lead dust and lead fragment remediation that will be required, careful attention must be given to preventing a lead dust hazard. Dust control shall be performed as the work proceeds and whenever a dust nuisance or hazard occurs.

3. All installation of materials shall be per manufacturers’ recommendations; UFC guidance; federal, state, and local building and electrical code requirements.

4. Construction Schedule. The Contractor shall provide a detailed construction schedule.

All items in this task are to be completed within 180 calendar days after government approval of the Final Design. Construction schedule shall be submitted and approved by the CO prior to construction.

1.3 GENERAL

A. All approvals and coordination for this scope of work shall be handled through the CO or their designated representative. No on-site work may begin until authorized by the CO.

B. Contract Changes/Modifications. Notwithstanding any provisions of this contract, the

CO will be the only individual authorized to in any way amend or modify the terms of this contract.

C. Progress Review Meetings. The Contractor shall hold progress review meetings and shall coordinate these meetings with the CO. Meetings may be held via telecon. The initial Progress Review Meeting will be held within 30 days of contract award. Subsequent meetings will be held at 30 day intervals and will continue until the project is closed out. These meetings will be a review of work performed, issues, schedules, milestones, and current status. The schedule of the progress review meeting may be modified by the CO with notification to the Contractor. The Contractor shall record and provide copies of all meeting minutes to POCs no later than 2 working days following meeting dates.

D. Contracting Officer’s Technical Representative. The Base Civil Engineer, 911 Airlift Wing, or his designated representative, is designated the Technical Representative of the CO for the purpose of technical supervision, inspection, and acceptance of services to be rendered under this contract.

Projects DZAQ 15‐0001A/B 15 18 November 2015

E. Storage on Site. Submit proposed location for material storage/staging/job trailer. Do not block access or roadways around the facility.

F. Contractor shall provide…