Exhibit B SPECIFICATIONS
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Maintain (Paint) Exterior Metal Stairs at Buildings 209, 219
PROJECT
SPECIFICATIONS
ISSUE FOR CONSTRUCTION
911th Airlift Wing Pittsburgh IAP Air Force Reserve 911th Project No. JLSS 15-0013
04-05-16
911th AIRLIFT WING TABLE OF CONTENTS 911TH CIVIL ENGINEERING
MAINTAIN (PAINT) EXTERIOR METAL STAIRS 00110 - 1 1100 HERMAN AVE
AT BUILDINGS 209, 219 CORAOPOLIS, PA 15108
JLSS 15-0013
SECTION 00110 - TABLE OF CONTENTS
COVER SHEET
Section Section Title
Series 0 Subgroup
DIVISION 00 - PROCUREMENT AND CONTRACTING REQUIREMENTS
00110 TABLE OF CONTENTS
00115 DRAWING INDEX
General Requirements Subgroup
DIVISION 01 - GENERAL REQUIREMENTS
01010 SUMMARY OF WORK
01100 WORK RESTRICTIONS
01320 CONSTRUCTION PROGRESS DOCUMENTATION
01340 SUBMITTAL PROCEDURES
01400 QUALITY REQUIREMENTS
01410 ENVIRONMENTAL PROTECTION
01500 TEMPORARY FACILITIES AND CONTROLS
01595 SAFETY REQUIREMENTS
01600 PRODUCT REQUIREMENTS
01770 CLOSEOUT PROCEDURES
01813 GREEN PROCUREMENT REQUIREMENTS
Facility Construction Subgroup
DIVISION 02 - SITE CONSTRUCTION
02085 DISTURBANCE OF LEAD CONTAINING SURFACE COATINGS
DIVISION 09 - FINISHES
09910 PAINTING
ATTACHMENT
01 ASBESTOS CONTAINING MATERIALS AND LEAD BASED PAINT INSPECTION
FOR VISITING QUARTERS – BUILDING 209
02 ASBESTOS CONTAINING MATERIALS AND LEAD BASED PAINT INSPECTION
FOR VISITING QUARTERS – BUILDING 219
END OF SECTION 00110
911th AIRLIFT WING DRAWING INDEX 911TH CIVIL ENGINEERING
MAINTAIN (PAINT) EXTERIOR METAL STAIRS 00115 - 1 1100 HERMAN AVE
AT BUILDINGS 209, 219 CORAOPOLIS, PA 15108
SECTION 00115 - DRAWING INDEX
SHEET PLATE SHEET
NUMBER NUMBER TITLE
GENERAL
1 of 3 G-01 PROJECT LOCATION
CIVIL
2 of 3 A-01 ELEVATIONS 3 of 3 A-02 FIRE ESCAPE DETAILS
END OF SECTION 00115
911th AIRLIFT WING SUMMARY OF WORK 911TH CIVIL ENGINEERING
MAINTAIN (PAINT) EXTERIOR METAL STAIRS 01010 - 1 1100 HERMAN AVE
AT BUILDINGS 209, 219 CORAOPOLIS, PA 15108
JLSS 15-0013
SECTION 01010 - SUMMARY OF WORK
PART 1 - GENERAL
1.1 RELATED DOCUMENTS
A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and Division 01 Specification Sections, apply to this Section.
1.2 TITLE OF WORK
Maintain (Paint) Exterior Metal Stairs at Buildings 209, 219 911th Airlift Wing/LGC 2375 Defense Avenue Pittsburgh IAP ARS Moon Township, PA 15108-4495.
A. Government’s Project Number: JLSS 15-0013.
1.3 DEFINITIONS
A. Provide shall mean: to furnish all materials/equipment, to install all labor and services and to make the item of work or equipment fully complete, operable, and acceptable to intended use.
B. Words "Project Coordinator" used in some of these specifications shall refer to the "Contracting Officer".
C. Word “Owner” shall refer to the “Government”.
D. Any referenced standards used are to be the latest version at the time of bidding.
1.4 WORK COVERED BY CONTRACT DOCUMENTS
A. The following is a general project Summary of the Work: This project includes removing old lead contained paint off of the exterior metal stairs on building 209, 219 and repaint them to match . A general summary of the work includes:
1. General Construction Work:
a. The contractor shall remove all old paint/primer on the fire escape exterior metal stairs on buildings 209, 219 as show on drawings. Paint contains lead so contractor has to remove and dispose of paint according to Occupational Safety and Health Administration (OSHA), Resource Conservation and Recovery Act (RCRA), and the 911th health and safety rules and regulations. Removal method is up to contractor. Any materials used to remove the lead contaminated paint must be approved by the base
MAINTAIN (PAINT) EXTERIOR METAL STAIRS 01010 - 2 1100 HERMAN AVE
AT BUILDINGS 209, 219 CORAOPOLIS, PA 15108
JLSS 15-0013
Bio-Environmental before being brought onto the base. If at any time Bio believes a method/process will expose base personnel to lead contamination, it will be disapproved. Water blasting will not be allowed because of the overabundance in hazardous waste and no way to control or capture that waste.
b. Fire regulations require two (2) exits available at all times. Only one set of stairs may be blocked on a building at any given time; both buildings (one set of stairs per building) may be worked on at the same time.
c. Paint chips were taken to perform a lead paint chip survey and were conducted for the projects: Renovate Repair Visiting Quarters VQ 209, 219 in Nov 2009 by L. Robert Kimball and Associates Inc. Test results confirmed the presence of lead-containing paint. See attached test results. The project did not remove old paint but instead encapsulated it.
Any additional testing deemed necessary for worker protection shall be at the Contractor's expense.
d. Prime and paint all exterior surfaces of the exterior metal fire escape stairs attached to buildings 209 and 219 (indicated on drawing) to match the architectural standards at Pittsburgh ARS. Surfaces include metal.
e. The primer and paint must adhere to the surface, once applied and dry, without chipping and peeling. The primer and paint applied must meet 911th standards and must not be considered a lead-containing paint as defined by the Consumer Product Safety Commission, i.e. > 0.009 % by weight of the total nonvolatile content of the paint or the weight of the dried paint film.
f. The building will be occupied during construction. The contractor shall take extra precaution to ensure any potential dust and vapors from the lead based paint do not escape the work area into occupied areas. Before the contractor proceeds to remove the paint, the area has to be approved by the Government Bio-Engineering office.
g. Existing stair tread metal plates with non-slip grip will be replace with new stair tread non-slip grip metal plates that matches the color of the newly painted stairs.
h. Cutting, sawing, sanding, scraping, needlegunning, abrasive blasting, and other operations that disturb lead-containing painted materials may result in lead exposures in excess of OSHA limits. The Contractor is responsible for adhering to 29CFR1926.62 and for monitoring of all sub-systems and procedures affecting the safety of the Contractor’s employees. Safety of the Contractor’s employees and providing safe conditions inside the work area for all persons entering the work area is the exclusive responsibility of the Contractor. No one is permitted in the lead control area unless they have been appropriately trained and provided with personal protective equipment.
i. Protect and cover equipment that are attached to the building to include doors, frames, windows and anything else that might get overspray.
j. The contractor shall coordinate with the government to shut down any HVAC air handling systems. Ensure all vents are blocked that can circulate the air from the work areas, including any air handling system that could possibly draw the outside air into the building and could possibly draw in the dust and vapors generated during the work. The environment of the
MAINTAIN (PAINT) EXTERIOR METAL STAIRS 01010 - 3 1100 HERMAN AVE
AT BUILDINGS 209, 219 CORAOPOLIS, PA 15108
JLSS 15-0013
work area shall be completely isolated from all other air flows in the building.
k. Remove lead-containing paint in accordance with established procedures and equipment to limit occupational and environmental exposure to lead in accordance with 29CFR1926.62. Select procedures and equipment to minimize contamination of work areas with lead contaminated dust or other lead contaminated debris/waste. Utilize engineering and work practice controls to the extent practicable to reduce exposure hazards.
l. Maintain surfaces of the lead control area free of accumulations of paint chips and dust. Restrict the spread of dust and debris. Loose material, debris and dust shall be placed in leak-proof Department of Transportation approved containers for disposal and properly labeled. At the end of each shift, as a minimum, and after the paint removal operation has been completed, clean the area of visible lead paint contamination using a High Efficiency Particulate Air (HEPA) vacuum.
m. The Contractor shall use an independent industrial hygienist to perform air and dust sampling to monitor the potential for elevated lead concentrations in adjacent occupied areas daily throughout the duration of the lead-containing paint work. If elevated levels of lead contaminated air or dust are found to be migrating to adjacent occupied areas, the Contractor must notify the Contracting Officer immediately. The work must stop until adequate measures have been taken to correct deficiencies in order to reduce the amount of lead in the air and dust below required action levels and protect base personnel from further exposure. Work can resume only when approval is given by the Contracting Officer.
n. Provide warning signs that comply with the requirements of 29CFR1926.62 at approaches to lead control areas. Locate signs at such a distance that personnel may read the sign and take the necessary precautions before entering the area.
o. The Contractor shall make all efforts to segregate waste streams and use appropriate methods to mitigate the amount of lead waste produced to the lowest possible quantity to minimize hazardous waste disposal. The Contracting Officer or an authorized representative will assign an area for interim storage of the waste containers.
B. The work shall be performed in accordance with all federal, state, and local regulations, and Air Force standards including but not limited to Environmental Protection Agency (EPA), Occupational Safety and Health Administration (OSHA), Pennsylvania Department of Environmental Protection (PADEP), and Air Force Occupational Safety and Health (AFOSH).
1.5 CONTRACT METHOD
A. Construct the Work under a single lump sum, fixed price contract for all project work.
B. Identify proposal on the appropriate line of the Bid Form.
MAINTAIN (PAINT) EXTERIOR METAL STAIRS 01010 - 4 1100 HERMAN AVE
AT BUILDINGS 209, 219 CORAOPOLIS, PA 15108
JLSS 15-0013
1.6 CONTRACTOR USE OF PREMISES AND RESPONSIBILITIES
A. Coordinate use of premises under direction of Contracting Officer.
B. Assume full responsibility for protection and safekeeping of products under this Contract.
C. Work periods may be limited in duration without additional compensation to the Contractor aside from an extension to the performance period for lost time.
D. Contractor shall be responsible for protecting installed Work and existing adjacent building materials and systems that remain.
E. Work is prohibited on UTA training weekends, which typically occurs the first and third weekends each month.
F. Obtain and pay for use of additional storage or work areas needed for operations under this Contract. Refer to Division 01 Section “Temporary Facilities and Controls” for providing temporary trailers.
G. Refer to Division 01 Section “Work Restrictions” for additional project requirements.
1.7 WORK UNDER OTHER CONTRACTS
A. General: Cooperate fully with separate contractors so work on those contracts may be carried out smoothly, without interfering with or delaying work under this Contract.
Coordinate the Work of this Contract with work performed under separate contracts.
1.8 GOVERNMENT’S OCCUPANCY REQUIREMENTS
A. Government Occupancy: Government will occupy the building to which the work will be performed during the entire construction period.
1. Cooperate with Contracting Officer during construction operations to minimize conflicts and facilitate Government usage within the existing building. Perform work to as much as possible not interfere with Government’s operations.
1.9 SUBMITTALS
A. BID SUBMITTALS
1. Submit the following evidence of qualifications. Ensure that all references are current and verifiable by phone numbers provided and documentation submitted.
a. Staff organization chart showing all persons to be employed and in what capacity.
MAINTAIN (PAINT) EXTERIOR METAL STAIRS 01010 - 5 1100 HERMAN AVE
AT BUILDINGS 209, 219 CORAOPOLIS, PA 15108
JLSS 15-0013
b. Licenses, certifications, and training certificates demonstrating the qualifications of the company and individuals performing this lead-containing paint work.
c. Project experience within the last 5 years, listing the top projects similar to this project.
d. A complete list of any lead-containing paint or material-related citations and violations.
e. Copy of the Contractor’s certificate of liability and lead or hazardous materials-specific insurance.
2. Submit a detailed work plan for government approval (including a building sketch indicating locations) describing details of the applicable plans, methods, procedures, equipment, materials, and chemicals in performance of the work for:
a. Paint removal.
b. Painting.
c. Housekeeping/cleanup.
d. Waste management.
3. Address in the detailed work plan the sequence of work, methods to be used to assure the health and safety of building occupants and visitors to the site, methods of removal to control the lead dust generated by the paint removal, methods to maintain all surfaces free of accumulations of lead, decontamination, containerization of lead-containing waste, and waste disposal.
PART 2 - PRODUCTS (Not Applicable)
PART 3 - EXECUTION (Not Applicable)
END OF SECTION 01010
911th AIRLIFT WING WORK RESTRICTIONS 911TH CIVIL ENGINEERING
MAINTAIN (PAINT) EXTERIOR METAL STAIRS 01100 - 1 1100 HERMAN AVE
AT BUILDINGS 209, 219 CORAOPOLIS, PA 15108
JLSS 15-0013
SECTION 01100 - WORK RESTRICTIONS
PART 1 - GENERAL
1.1 CONTRACTOR ACCESS TO AIR FORCE INSTALLATION
A. Access to Air Force installations in general and access to specific secured areas are subject to Air Force Regulations and procedures and shall be adhered to at all times.
B. Personnel Identification: Provide ID badges for all Contractor and Subcontractor personnel who make frequent visits to or perform work on the base.
1. Badges shall be hard paper stock (approx. 2 x 3 inches) and shall be enclosed by a plastic laminated cover.
2. The badge shall include a photo, employee’s name, employee’s signature, and Contractor’s company name.
3. The badge shall be worn by each employee such that it is visible at all times.
1.2 USE OF PREMISES
A. General: Contractor shall have use of premises indicated by Contracting Officer for construction operations, including use of Project site, during construction period.
1. Work periods may be limited in duration without additional compensation to the Contractor aside from an extension to the performance period for lost time. Work schedule shall be as follows:
a. Normal work hours shall be between 7:30 and 4:00 PM with no work on federal holidays.
b. Any deviation from the normal working hours shall be approved three (3) working days in advance by the Contracting Officer.
2. Work is prohibited on UTA Training Weekends which will occur two weekends per month, typically the first and third weekends of the month.
3. Comfort stations are not provided by 911th Air Wing.
4. Any type of advertising, including signs for advertising are not permitted on base.
5. Taking of photographs is prohibited except by the written permission coordinated through the Contracting Officer.
6. Firearms are not permitted on the base.
7. Contractor is to expect that the facility will be occupied during the entire project.
B. Use of Site: Limit use of premises to work in areas indicated by Contracting Officer.
Do not disturb portions of Project site beyond areas in which the Work is indicated.
1. Limits: Confine constructions operations to immediate areas of construction.
2. Owner Occupancy: Allow for Government occupancy of Project sites.
3. Driveways and Entrances: Keep driveways and entrances serving premises clear and available to Government, Government employees, and emergency vehicles at all times. Do not use these areas for parking or storage of materials.
911th AIRLIFT WING WORK RESTRICTIONS 911TH CIVIL ENGINEERING
MAINTAIN (PAINT) EXTERIOR METAL STAIRS 01100 - 2 1100 HERMAN AVE
AT BUILDINGS 209, 219 CORAOPOLIS, PA 15108
JLSS 15-0013
a. Schedule deliveries to minimize use of driveways and entrances.
b. Schedule deliveries to minimize space and time requirements for storage of materials and equipment on-site.
C. Use of Existing Buildings: Maintain existing buildings in a weather tight condition throughout construction period. Repair damage caused by construction operations.
Protect buildings and their occupants during construction period.
1. Avoid use of Base Facilities, including toilet facilities, unless approved in writing by Contracting Officer.
D. Contractor shall assume full responsibility for protection and safekeeping of products under this Contract.
E. Contractor shall be responsible for protecting all remaining permanent equipment.
F. Contractor shall obtain and pay for the use of additional storage or work areas needed for operation under this Contract.
END OF SECTION 01100
911th AIRLIFT WING CONSTRUCTION PROGRESS DOCUMENTATION 911TH CIVIL ENGINEERING
MAINTAIN (PAINT) EXTERIOR METAL STAIRS 01320 - 1 1100 HERMAN AVE
AT BUILDINGS 209, 219 CORAOPOLIS, PA 15108
JLSS 15-0013
SECTION 01320 - CONSTRUCTION PROGRESS DOCUMENTATION
PART 1 - GENERAL
1.1 RELATED DOCUMENTS
A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and other Division 01 Specification Sections, apply to this Section.
1.2 SUMMARY
A. This Section includes administrative and procedural requirements for documenting the progress of construction during performance of the Work, including the following:
1. Construction Schedule.
2. Contract Progress Report.
3. Submittals Schedule.
4. Daily construction reports.
5. Field condition reports.
6. Special reports.
B. Related Sections include the following:
1. Division 01 Section "Submittal Procedures" for submitting schedules and reports.
2. Division 01 Section "Quality Requirements" for submitting a schedule of tests and inspections.
3. Division 01 Section "Closeout Procedures" for submitting photographic negatives as Project Record Documents at Project closeout.
1.3 SUBMITTALS
A. Submittals Schedule: Submit (4) four copies of schedule. Arrange the following information in a tabular format:
1. Scheduled date for first submittal.
2. Specification Section number and title.
3. Submittal category (action or informational).
MAINTAIN (PAINT) EXTERIOR METAL STAIRS 01320 - 2 1100 HERMAN AVE
4. Name of subcontractor.
5. Description of the Work covered.
6. Scheduled date for Contracting Officer’s final release or approval.
B. Construction Schedule: Submit (4) four printed copies.
C. Contract Progress Report: Submit (4) four printed copies.
D. Field Condition Reports: Submit (2) two copies at time of discovery of differing conditions.
E. Special Reports: Submit (2) two copies at time of unusual event.
1.4 COORDINATION
A. Coordinate preparation and processing of schedules and reports with performance of construction activities and with scheduling and reporting of separate contractors.
B. Coordinate Contractor's Construction Schedule with the Schedule of Values, list of subcontracts, Submittals Schedule, progress reports, payment requests, and other required schedules and reports.
1. Secure time commitments for performing critical elements of the Work from parties involved.
2. Coordinate each construction activity in the network with other activities and schedule them in proper sequence.
PART 2 - PRODUCTS
2.1 SUBMITTALS SCHEDULE
A. Preparation: Submit a schedule of submittals, arranged in chronological order by dates required by construction schedule. Include time required for review, resubmittal, ordering, manufacturing, fabrication, and delivery when establishing dates.
1. Coordinate Submittals Schedule with list of subcontracts, the Schedule of Values, and Contractor's Construction Schedule.
2. Initial Submittal: Submit concurrently with preliminary bar-chart schedule. Include submittals required during the first 60 days of construction. List those required to maintain orderly progress of the Work and those required early because of long lead time for manufacture or fabrication.
MAINTAIN (PAINT) EXTERIOR METAL STAIRS 01320 - 3 1100 HERMAN AVE
AT BUILDINGS 209, 219 CORAOPOLIS, PA 15108
JLSS 15-0013
3. Final Submittal: Submit concurrently with the first complete submittal of Contractor's Construction Schedule.
2.2 CONTRACTOR'S CONSTRUCTION SCHEDULE, GENERAL
A. Procedures: Comply with procedures contained in The Associated General Contractor’s Construction Planning and Scheduling.
B. Time Frame: Extend schedule from date established for the Notice to Proceed to date of Final Completion.
1. Contract completion date shall not be changed by submission of a schedule that shows an early completion date, unless specifically authorized by modification.
C. Activities: Treat each story or separate area as a separate numbered activity for each principal element of the Work. Comply with the following:
1. Activity Duration: Define activities in time frame coordinated with Contracting Officer.
2. Procurement Activities: Include procurement process activities for long lead items and major items, requiring a cycle of more than 60 days, as separate activities in schedule.
Procurement cycle activities include, but are not limited to, submittals, approvals, purchasing, fabrication, and delivery.
3. Submittal Review Time: Include review and resubmittal times indicated in Division 01 Section "Submittal Procedures" in schedule. Coordinate submittal review times in Contractor's Construction Schedule with Submittals Schedule.
4. Startup and Testing Time: Include not less than (10) ten days for startup and testing.
5. Substantial Completion: Indicate completion in advance of date established for Substantial Completion, and allow time for Contracting Officer’s administrative procedures necessary for certification of Substantial Completion.
D. Constraints: Include constraints and work restrictions indicated in the Contract Documents and as follows in schedule, and show how the sequence of the Work is affected.
1. Phasing: Arrange list of activities on schedule by phase.
2. Products Ordered in Advance: Include a separate activity for each product. Include delivery date indicated in Division 01 Section "Summary of Work." Delivery dates indicated stipulate the earliest possible delivery date.
3. Work Restrictions: Show the effect of the following items on the schedule:
a. Coordination with existing construction.
b. Limitations of continued occupancies.
MAINTAIN (PAINT) EXTERIOR METAL STAIRS 01320 - 4 1100 HERMAN AVE
AT BUILDINGS 209, 219 CORAOPOLIS, PA 15108
c. Uninterruptible services.
d. Partial occupancy before Substantial Completion.
e. Use of premises restrictions.
f. Seasonal variations.
g. Environmental control.
E. Contract Modifications: For each proposed contract modification and concurrent with its submission, prepare a time-impact analysis using fragnets to demonstrate the effect of the proposed change on the overall project schedule.
2.3 CONSTRUCTION SCHEDULE
A. Coordinate construction schedule with Contracting Officer. Prepare and submit within (7) seven calendar days after Notice to Proceed. Complete construction schedule on AF Form 3064, Contract Progress Schedule, as received from Contracting Officer.
B. Preparation: Follow the “Instructions to Contractor” on the back of AF Form 3064 when completing and updating that form.
PART 3 - REPORTS
3.1 REPORTS
A. Field Condition Reports: Immediately on discovery of a difference between field conditions and the Contract Documents, prepare a detailed report. Submit with a request for information.
Include a detailed description of the differing conditions, together with recommendations for changing the Contract Documents.
B. Prepare and submit AF Form 3065, Contract Progress Report, as received from Contracting Officer. Coordinate preparation of AF 3065 with AF Form 3064. AF Form 3065 to be submitted twice monthly, with one report covering the period of the 1st to the 15th of each month, and the second report covering the period of the 16th to the last day of each month.
3.2 SPECIAL REPORTS
A. General: Submit special reports directly to Contracting Officer within one day of an occurrence. Distribute copies of report to parties affected by the occurrence.
B. Reporting Unusual Events: When an event of an unusual and significant nature occurs at Project site, whether or not related directly to the Work, prepare and submit a special report.
List chain of events, persons participating, response by Contractor's personnel, evaluation of
MAINTAIN (PAINT) EXTERIOR METAL STAIRS 01320 - 5 1100 HERMAN AVE
AT BUILDINGS 209, 219 CORAOPOLIS, PA 15108
JLSS 15-0013
results or effects, and similar pertinent information. Advise Contracting Officer in advance when these events are known or predictable.
PART 4 - EXECUTION
4.1 CONTRACTOR'S CONSTRUCTION SCHEDULE
A. Contractor's Construction Schedule Updating: At monthly intervals, update schedule to reflect actual construction progress and activities. Issue schedule one week before each regularly scheduled progress meeting.
1. Revise schedule immediately after each meeting or other activity where revisions have been recognized or made. Issue updated schedule concurrently with the report of each such meeting.
2. Include a report with updated schedule that indicates every change, including, but not limited to, changes in logic, durations, actual starts and finishes, and activity durations.
3. As the Work progresses, indicate Actual Completion percentage for each activity.
B. Distribution: Distribute copies of approved schedule to Contracting Officer, separate contractors, testing and inspecting agencies, and other parties identified by Contractor with a need-to-know schedule responsibility.
1. Post copies in Project meeting rooms and temporary field offices.
2. When revisions are made, distribute updated schedules to the same parties and post in the same locations. Delete parties from distribution when they have completed their assigned portion of the Work and are no longer involved in performance of construction activities.
END OF SECTION
911th AIRLIFT WING SUBMITTAL PROCEDURES 911TH CIVIL ENGINEERING
MAINTAIN (PAINT) EXTERIOR METAL STAIRS 01340 - 1 1100 HERMAN AVE
AT BUILDINGS 209, 219 CORAOPOLIS, PA 15108
JLSS 15-0013
SECTION 01340 - SUBMITTAL PROCEDURES
PART 1 - GENERAL
1.1 SUMMARY
A. This Section includes administrative and procedural requirements for submitting Shop Drawings, Product Data, Samples, and other submittals.
1.2 DEFINITIONS
A. Action Submittals: Written and graphic information that requires Contracting Officer's responsive action.
B. Informational Submittals: Written information that does not require Contracting Officer's responsive action. Submittals may be rejected for not complying with requirements.
1.3 SUBMITTAL PROCEDURES
A. Coordination: Coordinate preparation and processing of submittals with performance of construction activities.
1. Coordinate each submittal with fabrication, purchasing, testing, delivery, other submittals, and related activities that require sequential activity.
2. Coordinate transmittal of different types of submittals for related parts of the Work so processing will not be delayed because of need to review submittals concurrently for coordination.
a. Contracting Officer reserves the right to withhold action on a submittal requiring coordination with other submittals until related submittals are received.
B. Processing Time: Allow enough time for submittal review, including time for resubmittals, as follows. Time for review shall commence on Government's receipt of submittal. No extension of the Contract Time will be authorized because of failure to transmit submittals enough in advance of the Work to permit processing, including resubmittals.
1. Initial Review: Allow 14 calendar days for initial review of each submittal. Allow additional time if coordination with subsequent submittals is required.
Contracting Officer will advise Contractor when a submittal being processed must be delayed for coordination.
2. Resubmittal Review: Allow 10 calendar days for review of each resubmittal.
C. Identification: Place a permanent label or title block on each submittal for identification.
1. Indicate name of firm or entity that prepared each submittal on label or title block.
MAINTAIN (PAINT) EXTERIOR METAL STAIRS 01340 - 2 1100 HERMAN AVE
AT BUILDINGS 209, 219 CORAOPOLIS, PA 15108
JLSS 15-0013
2. Provide a space approximately 6 by 8 inches on label or beside title block to record Contractor's review and approval markings and action taken by Contracting Officer.
3. Include the following information on label for processing and recording action taken:
a. Project name.
b. Date.
c. Name and address of Government.
d. Name and address of Contractor.
e. Name and address of subcontractor.
f. Name and address of supplier.
g. Name of manufacturer.
h. Submittal number or other unique identifier, including revision identifier.
1) Submittal number shall use Specification Section number followed by a decimal point and then a sequential number (e.g., 06100.01).
Resubmittals shall include an alphabetic suffix after another decimal point (e.g., 06100.01.A).
i. Number and title of appropriate Specification Section.
j. Drawing number and detail references, as appropriate.
k. Location(s) where product is to be installed, as appropriate.
l. Other necessary identification.
D. Deviations: Highlight, encircle, or otherwise specifically identify deviations from the Contract Documents on submittals.
E. Transmittal: Package each submittal individually and appropriately for transmittal and handling. Transmit each submittal using a transmittal form. Contracting Officer will discard submittals received from sources other than Contractor.
F. Resubmittals: Make resubmittals in same form and number of copies as initial submittal.
1. Note date and content of previous submittal.
2. Note date and content of revision in label or title block and clearly indicate extent of revision.
G. Distribution: Furnish copies of final submittals to manufacturers, subcontractors, suppliers, fabricators, installers, authorities having jurisdiction, and others as necessary for performance of construction activities. Show distribution on transmittal forms.
PART 2 - PRODUCTS
2.1 ACTION SUBMITTALS
A. General: Prepare and submit Action Submittals required by individual Specification Sections.
MAINTAIN (PAINT) EXTERIOR METAL STAIRS 01340 - 3 1100 HERMAN AVE
AT BUILDINGS 209, 219 CORAOPOLIS, PA 15108
JLSS 15-0013
B. Product Data: Collect information into a single submittal for each element of construction and type of product or equipment.
1. If information must be specially prepared for submittal because standard printed data are not suitable for use, submit as Shop Drawings, not as Product Data.
2. Mark each copy of each submittal to show which products and options are applicable.
3. Include the following information, as applicable:
a. Manufacturer's written recommendations.
b. Manufacturer's product specifications.
c. Manufacturer's installation instructions.
d. Manufacturer's catalog cuts.
e. Compliance with specified referenced standards.
f. Testing by recognized testing agency.
4. Number of Copies: Submit five copies of Product Data, unless otherwise indicated. Contracting Officer will return two copies. Mark up and retain one returned copy as a Project Record Document.
C. Samples: Submit Samples for review of kind, color, pattern, and texture for a check of these characteristics with other elements and for a comparison of these characteristics between submittal and actual component as delivered and installed.
1. Transmit Samples that contain multiple, related components such as accessories together in one submittal package.
2. Identification: Attach label on unexposed side of Samples that includes the following:
a. Generic description of Sample.
b. Product name and name of manufacturer.
c. Sample source.
d. Number and title of appropriate Specification Section.
3. Disposition: Maintain sets of approved Samples at Project site, available for quality-control comparisons throughout the course of construction activity.
Sample sets may be used to determine final acceptance of construction associated with each set.
4. Samples for Verification: Submit full-size units or Samples of size indicated, prepared from same material to be used for the Work, cured and finished in manner specified, and physically identical with material or product proposed for use, and that show full range of color and texture variations expected. Samples include, but are not limited to, the following: partial sections of manufactured or fabricated components; small cuts or containers of materials; complete units of repetitively used materials; swatches showing color, texture, and pattern; color range sets; and components used for independent testing and inspection.
MAINTAIN (PAINT) EXTERIOR METAL STAIRS 01340 - 4 1100 HERMAN AVE
AT BUILDINGS 209, 219 CORAOPOLIS, PA 15108
JLSS 15-0013
a. Number of Samples: Submit three sets of Samples, unless noted otherwise. Contracting Officer will retain two Sample sets; remainder will be returned.
D. Submittals Schedule: A "Submittal Register" for use by the Contractor in developing the Schedule of Submittals is attached to this Specification.
2.2 INFORMATIONAL SUBMITTALS
A. General: Prepare and submit Informational Submittals required by other Specification Sections.
1. Number of Copies: Submit two copies of each submittal, unless otherwise indicated. Contracting Officer will not return copies.
2. Certificates and Certifications: Provide a notarized statement that includes signature of entity responsible for preparing certification. Certificates and certifications shall be signed by an officer or other individual authorized to sign documents on behalf of that entity.
3. Test and Inspection Reports: Comply with requirements specified in Division 01 Section "Quality Requirements."
B. Qualification Data: Prepare written information that demonstrates capabilities and experience of firm or person. Include lists of completed projects with project names and addresses, names and addresses of the Government and other information specified.
C. Welding Certificates: Prepare written certification that welding procedures and personnel comply with requirements in the Contract Documents. Submit record of Welding Procedure Specification (WPS) and Procedure Qualification Record (PQR) on AWS forms. Include names of firms and personnel certified.
D. Installer Certificates: Prepare written statements on manufacturer's letterhead certifying that Installer complies with requirements in the Contract Documents and, where required, is authorized by manufacturer for this specific Project.
E. Manufacturer Certificates: Prepare written statements on manufacturer's letterhead certifying that manufacturer complies with requirements in the Contract Documents.
Include evidence of manufacturing experience where required.
F. Product Certificates: Prepare written statements on manufacturer's letterhead certifying that product complies with requirements in the Contract Documents.
G. Material Certificates: Prepare written statements on manufacturer's letterhead certifying that material complies with requirements in the Contract Documents.
H. Material Test Reports: Prepare reports written by a qualified testing agency, on testing agency's standard form, indicating and interpreting test results of material for compliance with requirements in the Contract Documents.
MAINTAIN (PAINT) EXTERIOR METAL STAIRS 01340 - 5 1100 HERMAN AVE
AT BUILDINGS 209, 219 CORAOPOLIS, PA 15108
JLSS 15-0013
I. Product Test Reports: Prepare written reports indicating current product produced by manufacturer complies with requirements in the Contract Documents. Base reports on evaluation of tests performed by manufacturer and witnessed by a qualified testing agency, or on comprehensive tests performed by a qualified testing agency.
J. Research/Evaluation Reports: Prepare written evidence, from a model code organization acceptable to authorities having jurisdiction, that product complies with building code in effect for Project.
K. Preconstruction Test Reports: Prepare reports written by a qualified testing agency, on testing agency's standard form, indicating and interpreting results of tests performed before installation of product, for compliance with performance requirements in the Contract Documents.
L. Compatibility Test Reports: Prepare reports written by a qualified testing agency, on testing agency's standard form, indicating and interpreting results of compatibility tests performed before installation of product. Include written recommendations for primers and substrate preparation needed for adhesion.
M. Field Test Reports: Prepare reports written by a qualified testing agency, on testing agency's standard form, indicating and interpreting results of field tests performed either during installation of product or after product is installed in its final location, for compliance with requirements in the Contract Documents.
N. Maintenance Data: Prepare written and graphic instructions and procedures for operation and normal maintenance of products and equipment. Comply with requirements specified in Division 01 Section "Project Record Documents."
O. Design Data: Prepare written and graphic information, including, but not limited to, performance and design criteria, list of applicable codes and regulations, and calculations. Include list of assumptions and other performance and design criteria and a summary of loads. Include load diagrams if applicable. Provide name and version of software, if any, used for calculations. Include page numbers.
P. Manufacturer's Instructions: Prepare written or published information that documents manufacturer's recommendations, guidelines, and procedures for installing or operating a product or equipment. Include name of product and name, address, and telephone number of manufacturer.
Q. Manufacturer's Field Reports: Prepare written information documenting factory-authorized service representative's tests and inspections. Include the following, as applicable:
1. Statement on condition of substrates and their acceptability for installation of product.
2. Summary of installation procedures being followed, whether they comply with requirements and, if not, what corrective action was taken.
3. Results of operational and other tests and a statement of whether observed performance complies with requirements.
MAINTAIN (PAINT) EXTERIOR METAL STAIRS 01340 - 6 1100 HERMAN AVE
AT BUILDINGS 209, 219 CORAOPOLIS, PA 15108
JLSS 15-0013
R. Material Safety Data Sheets (MSDSs): Submit information directly to Contracting Officer.
PART 3 - EXECUTION
3.1 CONTRACTOR'S REVIEW
A. Review each submittal and check for coordination with other Work of the Contract and for compliance with the Contract Documents. Note corrections and field dimensions.
Mark with approval stamp before submitting to Contracting Officer.
B. Approval Stamp: Stamp each submittal with a uniform, approval stamp. Include Project name and location, submittal number, Specification Section title and number, name of reviewer, date of Contractor's approval, and statement certifying that submittal has been reviewed, checked, and approved for compliance with the Contract Documents.
3.2 CONTRACTING OFFICER'S ACTION
A. General: Contracting Officer will not review submittals that do not bear Contractor's approval stamp and will return them without action.
B. Action Submittals: Contracting Officer will review each submittal, make marks to indicate corrections or modifications required, and return it. Contracting Officer will stamp each submittal with an action stamp and will mark stamp appropriately to indicate action taken.
C. Informational Submittals: Contracting Officer will review each submittal and will not return it, or will return it if it does not comply with requirements. Contracting Officer will forward each submittal to appropriate party.
D. Partial submittals are not acceptable, will be considered nonresponsive, and will be returned without review.
E. Submittals not required by the Contract Documents will be discarded and not reviewed and may be discarded.
END OF SECTION 01340
911th AIRLIFT WING QUALITY REQUIREMENTS 911TH CIVIL ENGINEERING
MAINTAIN (PAINT) EXTERIOR METAL STAIRS 01400 - 1 1100 HERMAN AVE
AT BUILDINGS 209, 219 CORAOPOLIS, PA 15108
JLSS 15-0013
SECTION 01400 - QUALITY REQUIREMENTS
PART 1 - GENERAL
1.1 SUMMARY
A. This Section includes administrative and procedural requirements for quality assurance and quality control.
B. Testing and inspecting services are required to verify compliance with requirements specified or indicated. These services do not relieve Contractor of responsibility for compliance with the Contract Document requirements.
1. Specified tests, inspections, and related actions do not limit Contractor's other quality-assurance and -control procedures that facilitate compliance with the Contract Document requirements.
2. Requirements for Contractor to provide quality-assurance and -control services required by Government or authorities having jurisdiction are not limited by provisions of this Section.
C. Tests and inspections are Contractor's responsibility
D. See individual Sections for specific test and inspection requirements.
1.2 DEFINITIONS
A. Quality-Assurance Services: Activities, actions, and procedures performed before and during execution of the Work to guard against defects and deficiencies and substantiate that proposed construction will comply with requirements.
B. Quality-Control Services: Tests, inspections, procedures, and related actions during and after execution of the Work to evaluate that actual products incorporated into the Work and completed construction comply with requirements. Delete first paragraph below if Project does not require mockups. Revise if any mockups are to be constructed at an off-site location.
C. Preconstruction Testing: Tests and inspections that are performed specifically for the Project before products and materials are incorporated into the Work to verify performance or compliance with specified criteria.
D. Product Testing: Tests and inspections that are performed by an NRTL, an NVLAP, or a testing agency qualified to conduct product testing and acceptable to authorities having jurisdiction, to establish product performance and compliance with industry standards.
E. Source Quality-Control Testing: Tests and inspections that are performed at the source, i.e., plant, mill, factory, or shop.
F. Field Quality-Control Testing: Tests and inspections that are performed on-site for installation of the Work and for completed Work.
MAINTAIN (PAINT) EXTERIOR METAL STAIRS 01400 - 2 1100 HERMAN AVE
AT BUILDINGS 209, 219 CORAOPOLIS, PA 15108
JLSS 15-0013
G. Testing Agency: An entity engaged to perform specific tests, inspections, or both.
Testing laboratory shall mean the same as testing agency.
H. Installer/Applicator/Erector: Contractor or another entity engaged by Contractor as an employee, Subcontractor, or Sub-subcontractor, to perform a particular construction operation, including installation, erection, application, and similar operations.
1. Using a term such as "carpentry" does not imply that certain construction activities must be performed by accredited or unionized individuals of a corresponding generic name, such as "carpenter." It also does not imply that requirements specified apply exclusively to tradespeople of the corresponding generic name.
I. Experienced: When used with an entity, "experienced" means having successfully completed a minimum of five previous projects similar in size and scope to this Project;
being familiar with special requirements indicated; and having complied with requirements of authorities having jurisdiction.
1.3 CONFLICTING REQUIREMENTS
A. General: If compliance with two or more standards is specified and the standards establish different or conflicting requirements for minimum quantities or quality levels, comply with the most stringent requirement. Refer uncertainties and requirements that are different, but apparently equal, to Contracting Officer for a decision before proceeding.
B. Minimum Quantity or Quality Levels: The quantity or quality level shown or specified shall be the minimum provided or performed. The actual installation may comply exactly with the minimum quantity or quality specified, or it may exceed the minimum within reasonable limits. To comply with these requirements, indicated numeric values are minimum or maximum, as appropriate, for the context of requirements. Refer uncertainties to Contracting Officer for a decision before proceeding.
1.4 SUBMITTALS
A. Qualification Data: For testing agencies specified in "Quality Assurance" Article to demonstrate their capabilities and experience. Include proof of qualifications in the form of a recent report on the inspection of the testing agency by a recognized authority.
B. Reports: Prepare and submit certified written reports that include the following:
1. Date of issue.
2. Project title and number.
3. Name, address, and telephone number of testing agency.
4. Dates and locations of samples and tests or inspections.
5. Names of individuals making tests and inspections.
6. Description of the Work and test and inspection method.
7. Identification of product and Specification Section.
8. Complete test or inspection data.
MAINTAIN (PAINT) EXTERIOR METAL STAIRS 01400 - 3 1100 HERMAN AVE
9. Test and inspection results and an interpretation of test results.
10. Record of temperature and weather conditions at time of sample taking and testing and inspecting.
11. Comments or professional opinion on whether tested or inspected Work complies with the Contract Document requirements.
12. Name and signature of laboratory inspector.
13. Recommendations on retesting and reinspecting.
C. Permits, Licenses, and Certificates: For Government's records, submit copies of permits, licenses, certifications, inspection reports, releases, jurisdictional settlements, notices, receipts for fee payments, judgments, correspondence, records, and similar documents, established for compliance with standards and regulations bearing on performance of the Work.
1.5 QUALITY ASSURANCE
A. General: Qualifications paragraphs in this Article establish the minimum qualification levels required; individual Specification Sections specify additional requirements.
B. Installer Qualifications: A firm or individual experienced in installing, erecting, or assembling work similar in material, design, and extent to that indicated for this Project, whose work has resulted in construction with a record of successful in-service performance.
C. Manufacturer Qualifications: A firm experienced in manufacturing products or systems similar to those indicated for this Project and with a record of successful in-service performance, as well as sufficient production capacity to produce required units.
D. Fabricator Qualifications: A firm experienced in producing products similar to those indicated for this Project and with a record of successful in-service performance, as well as sufficient production capacity to produce required units.
E. Professional Engineer Qualifications: A professional engineer who is legally qualified to practice in jurisdiction where Project is located and who is experienced in providing engineering services of the kind indicated. Engineering services are defined as those performed for installations of the system, assembly, or products that are similar to those indicated for this Project in material, design, and extent.
F. Specialists: Certain sections of the Specifications require that specific construction activities shall be performed by entities who are recognized experts in those operations. Specialists shall satisfy qualification requirements indicated and shall be engaged for the activities indicated.
1. Requirement for specialists shall not supersede building codes and regulations governing the Work.
G. Testing Agency Qualifications: An NRTL, an NVLAP, or an independent agency with the experience and capability to conduct testing and inspecting indicated, as documented according to ASTM E 329; and with additional qualifications specified in
MAINTAIN (PAINT) EXTERIOR METAL STAIRS 01400 - 4 1100 HERMAN AVE
AT BUILDINGS 209, 219 CORAOPOLIS, PA 15108
JLSS 15-0013
individual Sections; and where required by authorities having jurisdiction, that is acceptable to authorities.
1. NRTL: A nationally recognized testing laboratory according to 29 CFR 1910.7.
2. NVLAP: A testing agency accredited according to NIST's National Voluntary
Laboratory Accreditation Program.
H. Factory-Authorized Service Representative Qualifications: An authorized representative of manufacturer who is trained and approved by manufacturer to inspect installation of manufacturer's products that are similar in material, design, and extent to those indicated for this Project.
1.6 QUALITY CONTROL
A. Tests and inspections are Contractor's responsibility. Provide quality-control services specified and those required by authorities having jurisdiction. Perform quality-control services required of Contractor by authorities having jurisdiction, whether specified or not.
1. Engage a qualified testing agency to perform these quality-control services.
2. Notify testing agencies at least 24 hours in advance of time when Work that requires testing or inspecting will be performed.
3. Submit a certified written report, in duplicate, of each quality-control service.
4. Testing and inspecting requested by Contractor and not required by the Contract
Documents are Contractor's responsibility.
5. Submit additional copies of each written report directly to authorities having jurisdiction, when they so direct.
B. Manufacturer's Field Services: Where indicated, engage a factory-authorized service representative to inspect field-assembled components and equipment installation, including service connections. Report results in writing as specified.
C. Retesting/Reinspecting: Regardless of whether original tests or inspections were Contractor's responsibility, provide quality-control services, including retesting and reinspecting, for construction that replaced Work that failed to comply with the Contract Documents.
D. Testing Agency…