This document is a Questions and Answers file for Solicitation FA670325R0003, addressing a fiber optic cable installation project at Dobbins Air Reserve Base in Georgia. The Q&A covers technical specifications for the project, including requirements for fiber optic cable installation, underground conduit systems, and site-specific installation details. Key technical clarifications include: a mandate for blown fiber installation, use of crushed stone (#57/#5) for drainage in handholes, specific underground conduit depth requirements (36" beneath roads/parking areas, 12" cover of clean fill), and use of PVC spacers for conduit support. Additional guidance from Dobbins Civil Engineering specifies concrete encasement for conductors under streets or parking lots, underground marker tape requirements, and mandates for manhole stabilization with crushed stone. The project is 100% set aside for small businesses and involves installing two 12-strand Single Mode Fiber Optic Cables from Information Transfer Building 700 to Hangar 5 and Building 404.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Solicitation Amendment FA670325R00030002 SF 30.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
The quesƟons and answers for solicitaƟon FA670325R0003 are listed as follows:
1) Do cables need to be blown, or can they also be pulled? Is there a mandate on which process we use?
Answer: Fiber OpƟc Cable - site mandate is to have blown fiber installed
2) Please confirm the type of gravel that needs to be placed in handholes for drainage.
Answer: Gravel Type - Crushed Stone facilitaƟng appropriate drainage for Georgia (#57/#5)
3) Is the minimum height coverage for installaƟon 12" and minimum height coverage going below hard surfaces 36"? Please confirm.
Answer: See references within SOO below:
2.2.3.12.2 InstallaƟon
Ducts installed beneath roads, sidewalks, parking areas, other paved surfaces or areas to be paved, etc. shall be installed a minimum of 36" below grade. Ducts installed beneath roads and parking areas shall be protected.
Ducts not installed across roads, sidewalks, parking areas, or areas to be paved, etc. shall have a minimum of 36 inches ground cover, where possible. The Contractor shall provide other protecƟve measures, concrete cap, etc., in those areas where the minimum ground cover cannot be achieved.
2.2.3.12 Underground Conduit System
Provide a minimum of 12" cover of clean fill above the conduit. Backfill material shall be clean and free from all organic material, clay, marl or unstable materials, debris, lumps, or broken paving. No rocks or stones larger than 3 inches in diameter shall be allowed in backfill. Material for backfill may be material resulƟng from excavaƟon if it meets the above requirements.
4) What type of spacers are being used in the trenching process? Are the spacers used only for pipe separaƟon?
Answer: PVC spacers are used to support conduit along the run and provide separaƟon.
5) Do we need to install warning tape for boring work?
Answer: ) Warning tape is required with boring work.
6) Is Visio the required program to produce updated drawings or can another be used?
Answer: Contractor will provide visio and pdf files as indicated in 2.2.12.1, 2.2.12.2 and GeospaƟal Deliverables (Shape files) for the conduit duct and MHs placed along the route as specified in 2.2.13 of the SOO.
AddiƟonally, Dobbins Civil Engineering provided the following input regarding these quesƟons
-Buried Conductors Below Traffic: All conduit containing conductors of any voltage including communicaƟon circuits that run under streets or parking lots shall be concrete encased minimum of 3 inches thick on all sides.
-Provide underground marker tapes for all underground conductors. If underground conductors are not in metallic conduit, provide marker tape with foiled backing to facilitate detecƟon.
-Manholes shall be stabilized with a minimum of 6 inches of crushed stone under the base.
A site visit was conducted on 17 June 2025 on Dobbins ARB with the following aƩendees:
1) Aios Group
2) Top Rate Xpress Services