ATTACHMENT_1-_SOW_Purchase-Install_Reciprocating_Compressor_with_Explosion_Proof_Motor.docx
DOCX document 85 KB Posted
- Attached to
- Purchase & Install Reciprocating Air Compressor with Explosion Proof Motor Federal contract opportunity
- Solicitation number
- FA6670-19-Q-A005
About this file
ATTACHMENT_1-_SOW_Purchase-Install Reciprocating Compressor with Explosion Proof Motor
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| BUILDING_621_FLOOR_PLAN.pdf | ||
| Building_621_-EAL-Form.docx | DOCX document | |
| FA6670-19-Q-A005_Quote_Sheet.docx | DOCX document | |
| RFQ-FA6670-19-Q-A005.pdf |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
STATEMENT OF WORK
RVKQ 13-0594 - Demolish Building 811
STATEMENT OF WORK
Purchase & Install Reciprocating Air Compressor with Explosion Proof Motor – Building 621
914 LRS/LGE
Niagara Falls Air Reserve Station 2250 Franklin Drive Niagara Falls, New York 14304-5063
STATEMENT OF WORK
Purchase & Install Reciprocating Air Compressor with Explosion Proof Motor, Building 621
01 May 2019
1. Summary of Work: The Contractor shall furnish and install all material, equipment, components, parts, tools, labor, transportation, hauling, disposal/recycling, cleaning, inspection, testing, commissioning, training, reporting, etc., necessary to perform this project as described in the contract-delivery order, including this Statement of Work and any/ all applicable federal, state and local law, regulation, standards. Unless otherwise stated, any/ all requirement for contractor to remove and properly dispose of/ recycle off base, and to furnish and install/ incorporate any/ all new materials/ equipment/ components needed to properly complete the work item; any Government furnished property and/ or reinstallation of existing materials/ equipment/ components shall be as stated/ specified herein. Contractor shall submit materials/ methods for approval prior to ordering and/ or incorporation into the work; as a minimum, submittals shall include product literature, MSDS, standard color, texture and style samples/ swatches/ boards, and place of origin/ manufacture. Demolished materials, waste/ debris is property of the contractor, unless otherwise stated herein; contractor is responsible for proper disposal/ recycling of such materials off base; such materials shall be promptly removed from the installation and shall not be stored/ stockpiled unless submitted and approved for such. Contractor is responsible for verification of all details, measurement, etc., prior to ordering materials and execution of work.
2. Maintenance Bay: Purchase & Install Reciprocating Air Compressor with Explosion Proof Motor.
a. 7.5 HP, 80 Gallon vertical Compressor, 208V/3PH/60Hz explosion proof motor.
b. Compressor to be locate on the north east corner of facility (see attached floor plan)
c. Additional options for 7.5HP compressor to include vibration pads, service valve and installed after-cooler.
d. STD starter box & pressure switch to be installed in electrical room
e. Wire compressor to existing disconnect and rework electric to electrical room
f. Install new air lines and associated fittings on east wall. Connect to existing air line on west wall.
3. A submittal of intended materials for the following items for review before installation: Reciprocating Air Compressor with Explosion Proof Motor.
4. All installation of materials shall be per manufacturer’s recommendations and local, state and federal building code requirements. All materials must meet NFPA Fire ratings and IAW current standards.
5. The Contractor shall be responsible for the proper disposal of all materials removed and shall ensure that the facility is secure at the end of each duty day.
6. The contractor shall be responsible for all contractor and sub-contractor employees wearing the correct PPE at all times while on the construction site. To include, but not limited to; hard hat, safety glasses, safety footwear, fall protection devices, etc.
7. Green Purchasing
a. Contractor shall comply with the Green Purchasing requirements of the contract. Known / possible EPA Comprehensive Procurement Guideline, USDA Biobased, Green Seal Energy Star, etc., items. Recycled materials must be used to fullest extent in accordance with Executive Order 13101. The EPA web-site, http://www.epa.gov/cpg, can be accessed for further instruction on what is an EPA-designated material.