Answers_to_Questions.docx

DOCX document 14 KB Posted

Attached to
Clearing & Grubbing Federal contract opportunity
Solicitation number
FA6648-16-T-0002
Issued by
Department of the Air Force Reserve Command

About this file

Questions from Contractor

View the file

Other files for this federal contract opportunity

Other files attached to Clearing & Grubbing, newest first.
File Type Posted
Site_Visit_Attendees.pdf PDF
Homestead_CG_PWS_9_Mar_2016.doc DOC document
SE_Clearing.pdf PDF
FANG_AREA.pdf PDF
BX_MART_AREA.pdf PDF
CLEARING_AND_GRUBBING_JAN2016.pdf PDF

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

1st Question: Can you provide any and all additional information about the project site visitation like questions from contractors and answers by the department?

Answer: As we went through the meeting before heading over to the sites, some of the minutes that were discussed are as followed.

The services are for Clearing & Grubbing only The award contract is based on Lowest Price Technically Acceptable It will 100% small Business Set-aside NAICS Code for this requirement is 561730 The contract will be Firm Fixed Price Registered in SAM is required Period of Performance (POP) will be for 90 days (from the initial start of the contract date) All proposals are to be emailed ONLY Proposal are due on the 6th of Sep, by 2:30 pm eastern time 2nd Question: List of attendees.

Answer: Attached is the list of attendees

3rd Question: If there are any photographs that you can share showing the density of trees and vegetations at these locations?

Answer: No photos available due to base flight line restrictions and base commander directive.

4th Question: Are we required to cut on the Army side of the fence around OU-18 old site.

Answer: No, you will only be responsible for the Air Force side of clearing and grubbing.

5th Question: Is any grinding/chipping permitted on site and if some of this grinding piles can be left at designated locations at the base?

Answer: Detailed grinding/chipping plan may be submitted (upon award of contract), however, it will require the approval of the government.

6th Question: Are these work site locations fully accessible with trucking and heavy equipment?

Answer: For most of the sites (YES), however, we have two sites that are only accessible by watercraft.