This Statement of Objectives (SOO) outlines requirements for installing a new Self-Contained Breathing Apparatus (SCBA) bottle filling station at Westover Air Reserve Base Fire Department. The primary objective is to provide a code-compliant air bottle filling station capable of refilling/reservicing the department's current SCBA air bottles used for fire and emergency responses.
The system must comply with NFPA 1989 standards and include: a carbon monoxide monitoring system, RFID reader for cylinder tracking, virus-free air intake system, remote fill hose connection for ARFF vehicles, capability to fill 3 SCBA bottles simultaneously, and fit within a 101"x38"x78" space. The contractor must provide all equipment, materials and labor for installation, including removal of existing equipment. Key components include the main filling unit with compressor, CO monitor with calibration kit, remote fill connection, 25 RFID tags, and virus-free air intake system. Installation requirements specify certified technicians, comprehensive testing, air quality verification, and training for personnel. The installation timeframe cannot exceed 90 days, with work to be performed Monday-Friday 0700-1630 excluding federal holidays. All equipment and installation must include a minimum one-year warranty with 24-hour repair service.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| 439AW FORM 1_b.pdf | ||
| 439AW FORM 1 SITE VISIT.pdf | ||
| FA660625Q0001 Clause Set.pdf | ||
| 439AW FORM 1.pdf | ||
| CLIN Schedule FA660625Q0001 SCBA BOTTLE BILLING STATION.docx | DOCX document | |
| Performance Work Statement PWS SCBA Bottle Filling Station 1-30-2025.docx | DOCX document |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Statement of Objectives (SOO) Westover Air Reserve Base Self Contained Breathing Apparatus (SCBA) Fill Station
Install
Installation Fire Department New SCBA Fill Station
Scope
The contractor shall provide all personnel, equipment, tools, materials, supervision, and quality control necessary to perform the installation and testing of a new SCBA (self-contained breathing apparatus) air bottle filling station and compressor.
The primary objective is to provide the Westover Fire Department a new, code compliant, air bottle filling station capable of refilling/reservicing the Departments current SCBA air bottles used for fire and emergency responses.
Specific objectives include:
1. Comply with NFPA 1989 standards.
2. Have a carbon monoxide monitoring system.
3. Have an RFID reader that records data from the RFID equipped cylinders for record keeping.
4. Have a virus free air intake system.
5. Have a remote fill hose connection to re-service ARFF vehicles on board air systems.
6. Refill current SCBA air bottles for fire and emergency services use.
7. Be able to fit in a space 101”x 38”x 78”.
8. Be able to fill 3 SCBA bottles simultaneously.
9. Removal of existing unit and compressor including disposal and cleanup of worksite.
10. Provide 24-hour repair in the event of machine malfunction per applicable warranty.
Equipment and Components:
1. Main SCBA bottle filling unit complete with compressor
2. CO monitor w/calibration kit
3. Remote fill hose connection
4. RFID tags for current SCBA bottles (25)
5. Virus free air intake system
6. Installation, calibration, air quality test, training, NFPA compliant fill log installation requirements, removal of current equipment, cleanup of worksite
Installation and Training:
1. Installation: Certified technicians will be responsible for the physical installation of all equipment, systems and its components at the designated location building 7084 installation Fire Department of the SCBA filling station.
2. Calibration: The system will be calibrated to ensure proper control functionality between the unit and SCBA bottle filling process.
3. Testing: Comprehensive testing will be conducted to verify the proper operation of all system components and functionalities.
4. Air quality test: An air sample will be conducted to ensure safe breathing air is being supplied to the SCBA bottles for firefighter use.
5. Training: Training sessions will be conducted for designated personnel to familiarize them with the operation, maintenance, and troubleshooting of all systems and components with the unit.
Project Considerations
Any proposal which does not include all component parts included in this specification or incomplete in any way will be considered non-responsive and rejected immediately. Quoted prices shall be guaranteed for one year from date of installation-plus freight and installation-in any quantity.
1. Time of installation shall not exceed 90 days.
2. To ensure successful installation, the contractor is accountable for supplying adequate manpower, equipment, necessary tools, required materials, appropriate supervision, and stringent quality control measures.
3. The contractor is responsible for training base personnel in the operation and maintenance of all communication devices and their components.
4. All installed systems and components must have a minimum of a one-year warranty on the equipment and installation.
5. Delivery and installation will take place at Westover ARB. between the hours of 0700- 1630 on Monday-Friday. Excluding holidays: New Years Day, Birthday of Martin Luther King Jr., Washington's Birthday, Memorial Day, Juneteenth National Independence Day, Independence Day, Labor Day, Columbus Day, Veterans Day, Thanksgiving Day, and Christmas Day.
6. Overall, the objective of this project is to successfully install all system components and features to refill Fire Department SCBA bottles, track their use, comply with current NFPA standards, have a carbon monoxide monitoring system and virus free air intake system, and provide a remote fill hose connection.
7. By achieving these objectives, we aim to improve SCBA bottle filling and tracking as required by NFPA standards and provide a more reliable system to the Fire Department, ultimately enhancing the overall safety and efficiency of our emergency operations.
| Statement of Objectives (SOO) |
| Westover Air Reserve Base Self Contained Breathing Apparatus (SCBA) Fill Station Install |
File details come from the government source that posted it. Updated .