This pre-solicitation notice provides details for an upcoming firm fixed price construction contract to add a restroom and outside air inspection bay to Building 5305 at Westover Air Reserve Base. The work includes constructing a two-room addition with one room for mechanical equipment and an adjacent single-occupancy ADA compliant restroom. Additional work involves replacing lighting with LED fixtures, installing DDC controls, and connecting to existing utilities. The acquisition is set aside for small businesses and will use IFB procedures. The period of performance is one year excluding winter months. The estimated value is between $500,000 and $1,000,000. The solicitation and supporting documents will be available for download at SAM.gov where all interested contractors must register to receive amendments or award information. Funds are not presently available and no award will be made until funding is in place.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
SPECIFICATIONS
Volume 2
ADD RESTROOM AND OUTSIDE AIR
INSPECTION BAY, BLDG. 5305
WESTOVER ARB
YTPM 14-0014
FINAL DESIGN SUBMITTAL
FOR CONSTRUCTION
WALLER, TODD & SADLER ARCHITECTS, INC.
1909 CYPRESS AVENUE
VIRGINIA BEACH, VA 23451
TEL (757) 417-0140; FAX (757) 417-0144
E-mail: wts@wtsarch.com
JUNE 14
ADD RESTROOM AND OUTSIDE AIR INSPECTION BAY-BLDG 5305 YTPM140014
SECTION 09 22 00
SUPPORTS FOR PLASTER AND GYPSUM BOARD
02/10
PART 1 GENERAL
1.1 REFERENCES
The publications listed below form a part of this specification to the extent referenced. The publications are referred to within the text by the basic designation only.
ASTM INTERNATIONAL (ASTM)
ASTM A463/A463M (2010; R 2015) Standard Specification for Steel Sheet, Aluminum-Coated, by the Hot-Dip Process
ASTM A653/A653M (2015; E 2016) Standard Specification for Steel Sheet, Zinc-Coated (Galvanized) or Zinc-Iron Alloy-Coated (Galvannealed) by the Hot-Dip Process
ASTM C645 (2014; E 2015) Nonstructural Steel Framing Members
ASTM C754 (2015) Installation of Steel Framing Members to Receive Screw-Attached Gypsum Panel Products
ASTM C841 (2003; R 2013) Installation of Interior Lathing and Furring
ASTM C847 (2014a) Standard Specification for Metal Lath
NATIONAL ASSOCIATION OF ARCHITECTURAL METAL MANUFACTURERS (NAAMM)
NAAMM EMLA 920 (2009) Guide Specifications for Metal Lathing and Furring
UNDERWRITERS LABORATORIES (UL)
UL Fire Resistance (2014) Fire Resistance Directory
1.2 SUBMITTALS
Government approval is required for submittals with a "G" designation;
submittals not having a "G" designation are for Contractor Quality Control approval. Submit the following in accordance with Section 01 33 00.00 50
SUBMITTAL PROCEDURES:
SD-02 Shop Drawings
Metal support systems
Submit for the erection of metal framing, furring, and ceiling
SECTION 09 22 00 Page 1 suspension systems. Indicate materials, sizes, thicknesses, and fastenings.
1.3 DELIVERY, STORAGE, AND HANDLING
Deliver materials to the job site and store in ventilated dry locations.
Storage area shall permit easy access for inspection and handling. If materials are stored outdoors, stack materials off the ground, supported on a level platform, and fully protected from the weather. Handle materials carefully to prevent damage. Remove damaged items and provide new items.
PART 2 PRODUCTS
2.1 MATERIALS
Provide steel materials for metal support systems with galvanized coating ASTM A653/A653M , G-60 ; aluminum coating ASTM A463/A463M , T1-25 ; or a 55-percent aluminum-zinc coating.
2.1.1 Suspended and Furred Ceiling Systems and Wall Furring
ASTM C841, and ASTM C847.
2.1.2 Materials for Attachment of Gypsum Wallboard
2.1.2.1 Suspended and Furred Ceiling Systems
ASTM C645.
2.1.2.2 Nonload-Bearing Wall Framing and Furring
ASTM C645, but not thinner than 0.0179 inch thickness, with 0.0329 inch minimum thickness supporting wall hung items such as cabinetwork, equipment and fixtures.
2.1.2.3 Furring Structural Steel Columns
ASTM C645. Steel (furring) clips and support angles listed in UL Fire Resistance may be provided in lieu of steel studs for erection of gypsum wallboard around structural steel columns.
2.1.2.4 Z-Furring Channels with Wall Insulation
Not lighter than 26 gage galvanized steel, Z-shaped, with 1-1/4 inch and 3/4 inch flanges and 2 inch furring depth.
PART 3 EXECUTION
3.1 INSTALLATION
3.1.1 Systems for Attachment of Lath
3.1.1.1 Suspended and Furred Ceiling Systems and Wall Furring
ASTM C841, except as indicated otherwise.
SECTION 09 22 00 Page 2
3.1.1.2 Non-loadbearing Wall Framing
NAAMM EMLA 920, except provide framing members 16 inches o.c. unless indicated otherwise.
3.1.2 Systems for Attachment of Gypsum Wallboard
3.1.2.1 Suspended and Furred Ceiling Systems
ASTM C754, except provide framing members 16 inches o.c. unless indicated otherwise.
3.1.2.2 Non-loadbearing Wall Framing and Furring
ASTM C754, except as indicated otherwise.
3.1.2.3 Furring Structural Steel Columns
Install studs or galvanized steel clips and support angles for erection of gypsum wallboard around structural steel columns in accordance with the UL Fire Resistance , design number(s) indicated.
3.1.2.4 Z-Furring Channels with Wall Insulation
Install Z-furring channels vertically spaced not more than 24 inches o.c.
Locate Z-furring channels at interior and exterior corners in accordance with manufacturer's printed erection instructions. Fasten furring channels to masonry and concrete walls with powder-driven fasteners or hardened concrete steel nails through narrow flange of channel. Space fasteners not more than 24 inches o.c.
3.2 ERECTION TOLERANCES
Provide framing members which will be covered by finish materials such as wallboard, plaster, or ceramic tile set in a mortar setting bed, within the following limits:
a. Layout of walls and partitions: 1/4 inch from intended position;
b. Plates and runners: 1/4 inch in 8 feet from a straight line;
c. Studs: 1/4 inch in 8 feet out of plumb, not cumulative; and
d. Face of framing members: 1/4 inch in 8 feet from a true plane.
Provide framing members which will be covered by ceramic tile set in dry-set mortar, latex-portland cement mortar, or organic adhesive within the following limits:
a. Layout of walls and partitions: 1/4 inch from intended position;
b. Plates and runners: 1/8 inch in 8 feet from a straight line;
c. Studs: 1/8 inch in 8 feet out of plumb, not cumulative; and
d. Face of framing members: 1/8 inch in 8 feet from a true plane.
-- End of Section --
SECTION 09 22 00 Page 3
SECTION 09 29 00
GYPSUM BOARD
08/16
PART 1 GENERAL
1.1 REFERENCES
The publications listed below form a part of this specification to the extent referenced. The publications are referred to within the text by the basic designation only.
AMERICAN NATIONAL STANDARDS INSTITUTE (ANSI)
ANSI A108.11 (1992; Reaffirmed 2005) Specifications for Interior Installation of Cementitious Backer Units
ASTM INTERNATIONAL (ASTM)
ASTM C1002 (2014) Standard Specification for Steel Self-Piercing Tapping Screws for the Application of Gypsum Panel Products or Metal Plaster Bases to Wood Studs or Steel Studs
ASTM C1047 (2014a) Standard Specification for Accessories for Gypsum Wallboard and Gypsum Veneer Base
ASTM C1177/C1177M (2013) Standard Specification for Glass Mat Gypsum Substrate for Use as Sheathing
ASTM C1178/C1178M (2013) Standard Specification for Glass Mat Water-Resistant Gypsum Backing Panel
ASTM C1396/C1396M (2014a) Standard Specification for Gypsum Board
ASTM C475/C475M (2015) Joint Compound and Joint Tape for Finishing Gypsum Board
ASTM C514 (2004; R 2014) Standard Specification for Nails for the Application of Gypsum Board
ASTM C557 (2003; E 2009; R 2009) Adhesives for Fastening Gypsum Wallboard to Wood Framing
ASTM C840 (2016) Standard Specification for Application and Finishing of Gypsum Board
ASTM C954 (2015) Steel Drill Screws for the Application of Gypsum Panel Products or Metal Plaster Bases to Steel Studs from
0.033 in. (0.84 mm) to 0.112 in. (2.84 mm) in Thickness
SECTION 09 29 00 Page 1
ASTM D1149 (2007; R 2012) Standard Test Method for Rubber Deterioration - Surface Ozone Cracking in a Chamber
ASTM D226/D226M (2009) Standard Specification for Asphalt-Saturated Organic Felt Used in Roofing and Waterproofing
ASTM D3273 (2016) Standard Test Method for Resistance to Growth of Mold on the Surface of Interior Coatings in an Environmental Chamber
ASTM D412 (2016) Standard Test Methods for Vulcanized Rubber and Thermoplastic Elastomers - Tension
ASTM D624 (2000; R 2012) Tear Strength of Conventional Vulcanized Rubber and Thermoplastic Elastomers
GYPSUM ASSOCIATION (GA)
GA 214 (2010) Recommended Levels of Gypsum Board Finish
GA 216 (2010) Application and Finishing of Gypsum Panel Products
GA 253 (2012) Application of Gypsum Sheathing
1.2 SUBMITTALS
Government approval is required for submittals with a "G" designation;
submittals not having a "G" designation are for Contractor Quality Control approval.
SD-03 Product Data
Cementitious Backer Units
Glass Mat Covered or Reinforced Gypsum Sheathing
Glass Mat Covered or Reinforced Gypsum Sheathing Sealant
Accessories
Submit for each type of gypsum board and for cementitious backer units.
Glass Mat Water-Resistant Gypsum Tile Backing Board ; G
Water-Resistant Gypsum Backing Board ; G
Gypsum Board ; G
SD-07 Certificates
Asbestos Free Materials ; G
SECTION 09 29 00 Page 2
Certify that gypsum board types, gypsum backing board types, cementitious backer units, and joint treating materials do not contain asbestos.
SD-11 Closeout Submittals
VOC Content of Joint Compound
Indoor Air Quality for Non-aerosol Adhesives
Indoor Air Quality for Aerosol Adhesives
1.3 DELIVERY, STORAGE, AND HANDLING
1.3.1 Delivery
Deliver materials in the original packages, containers, or bundles with each bearing the brand name, applicable standard designation, and name of manufacturer, or supplier.
1.3.2 Storage
Keep materials dry by storing inside a sheltered building. Where necessary to store gypsum board and cementitious backer units outside, store off the ground, properly supported on a level platform, and protected from direct exposure to rain, snow, sunlight, and other extreme weather conditions. Provide adequate ventilation to prevent condensation. Store per manufacturer's recommendations for allowable temperature and humidity range. Do not store panels near materials that may offgas or emit harmful fumes, such as kerosene heaters, fresh paint, or adhesives. Do not use materials that have visible moisture or biological growth.
1.3.3 Handling
Neatly stack gypsum board and cementitious backer units flat to prevent sagging or damage to the edges, ends, and surfaces.
1.4 QUALIFICATIONS
Furnish type of gypsum board work specialized by the installer with a minimum of 5 years of documented successful experience.
1.5 ENVIRONMENTAL REQUIREMENTS
Do not expose the gypsum board to excessive sunlight prior to gypsum board application. Maintain a continuous uniform temperature of not less than 50 degrees F and not more than 80 degrees F for at least one week prior to the application of gypsum board work, while the gypsum board application is being done, and for at least one week after the gypsum board is set.
Shield air supply and distribution devices to prevent any uneven flow of air across the plastered surfaces. Provide ventilation to exhaust moist air to the outside during gypsum board application, set, and until gypsum board jointing is dry. In glazed areas, keep windows open top and bottom or side to side 3 to 4 inches . Reduce openings in cold weather to prevent freezing of joint compound when applied. For enclosed areas lacking natural ventilation, provide temporary mechanical means for ventilation.
In unglazed areas subjected to hot, dry winds or temperature differentials
SECTION 09 29 00 Page 3 from day to night of 20 degrees F or more, screen openings with cheesecloth or similar materials. Avoid rapid drying. During periods of low indoor humidity, provide minimum air circulation following gypsum boarding and until gypsum board jointing complete and is dry.
PART 2 PRODUCTS
2.1 MATERIALS
Conform to specifications, standards and requirements specified. Provide gypsum board types, gypsum backing board types, cementitious backing units, and joint treating materials manufactured from asbestos free materials only.
2.1.1 Gypsum Board
ASTM C1396/C1396M .
2.1.1.1 Regular
48 inch wide, 5/8 inch thick, tapered edges.
2.1.1.2 Type X (Special Fire-Resistant)
48 inch wide, 5/8 inch thick, tapered edges.
2.1.1.3 Mold Resistant / Anti-Microbial Gypsum
ASTM D3273. 48 inch wide, 5/8 inch thick, tapered edges.
2.1.2 Regular Water-Resistant Gypsum Backing Board
ASTM C1396/C1396M .
2.1.2.1 Regular
48 inch wide, 5/8 inch thick, tapered edges.
2.1.2.2 Type X (Special Fire-Resistant)
48 inch wide, 5/8 inch thick, tapered edges.
2.1.3 Glass Mat Water-Resistant Gypsum Tile Backing Board
ASTM C1178/C1178M
2.1.3.1 Regular
48 inch wide, 5/8 inch thick, square edges.
2.1.3.2 Type X (Special Fire-Resistant)
48 inch wide, 5/8 inch thick, square edges.
2.1.4 Glass Mat Covered or Reinforced Gypsum Sheathing
Exceeds physical properties of ASTM C1396/C1396M and ASTM C1177/C1177M .
Provide 5/8 inch , gypsum sheathing. Provide gypsum board of with a noncombustible water-resistant core, with glass mat surfaces embedded to
SECTION 09 29 00 Page 4 the gypsum core or reinforcing embedded throughout the gypsum core.
Warrant gypsum sheathing board for at least twelve months against delamination due to direct weather exposure. Provide continuous, asphalt impregnated, building felt to cover exterior face of sheathing.
2.1.4.1 Glass Mat Covered or Reinforced Gypsum Sheathing Sealant
Provide sealant compatible with glass mat covered or reinforced gypsum sheathing, rubber washers for masonry veneer anchors, and other associated cavity wall components such as anchors and through wall flashing. Provide sealants for glass mat covered or reinforced gypsum sheathing board edge seams and veneer anchor penetrations recommended by the glass mat covered or reinforced gypsum sheathing manufacturer and have the following performance requirements:
a. ASTM D412: Tensile Strength, 80 psi
b. ASTM D412: Ultimate Tensile Strength (maximum elongation), 170 psi
c. ASTM D624: Tear Strength, dieB, 27 ppi
d. ASTM D1149: Joint Movement Capability after 14 Days cure, plus or minus 50 percent.
2.1.5 Cementitious Backer Units
In accordance with the Tile Council of America (TCA) Handbook.
2.1.6 Joint Treatment Materials
ASTM C475/C475M. Product must be low emitting VOC types with VOC limits not exceeding 50 g/L. Provide data identifying VOC content of joint compound . Use all purpose joint and texturing compound containing inert fillers and natural binders, including lime compound. Pre-mixed compounds must be free of antifreeze, vinyl adhesives, preservatives, biocides and other slow releasing compounds.
2.1.6.1 Embedding Compound
Specifically formulated and manufactured for use in embedding tape at gypsum board joints and compatible with tape, substrate and fasteners.
2.1.6.2 Finishing or Topping Compound
Specifically formulated and manufactured for use as a finishing compound.
2.1.6.3 All-Purpose Compound
Specifically formulated and manufactured to serve as both a taping and a finishing compound and compatible with tape, substrate and fasteners.
2.1.6.4 Setting or Hardening Type Compound
Specifically formulated and manufactured for use with fiber glass mesh tape.
2.1.6.5 Joint Tape
Use cross-laminated, tapered edge, reinforced paper, or fiber glass mesh tape recommended by the manufacturer.
SECTION 09 29 00 Page 5
2.1.7 Fasteners
2.1.7.1 Nails
ASTM C514. For predecorated gypsum board provide special nails with factory coated heads of color to match wall covering materials as recommended by the predecorated gypsum board manufacturer.
2.1.7.2 Screws
ASTM C1002, Type "G", Type "S" or Type "W" steel drill screws for fastening gypsum board to gypsum board, wood framing members and steel framing members less than 0.033 inch thick. ASTM C954 steel drill screws for fastening gypsum board to steel framing members 0.033 to 0.112 inch thick. Provide cementitious backer unit screws with a polymer coating.
2.1.7.3 Staples
No. 16 USS gage flattened galvanized wire staples with 7/16 inch wide crown outside measurement and divergent point for base ply of two-ply gypsum board application. Use as follows:
Length of Legs Thickness of Gypsum Board
1-1/8 inches 1/2 inch
1-1/4 inches 5/8 inch
2.1.8 Adhesives
Provide certification of indoor air quality for non-aerosol adhesives applied on the interior of the building (inside of the weatherproofing system). Provide certification of indoor air quality for aerosol adhesives used on the interior of the building (inside of the weatherproofing system).
2.1.8.1 Adhesive for Fastening Gypsum Board to Metal Framing
Not permitted.
2.1.8.2 Adhesive for Fastening Gypsum Board to Wood Framing
ASTM C557.
2.1.9 Accessories
ASTM C1047. Fabricate from corrosion protected steel or plastic designed for intended use. Accessories manufactured with paper flanges are not acceptable. Flanges must be free of dirt, grease, and other materials that may adversely affect bond of joint treatment. Provide prefinished or job decorated materials.
2.1.10 Asphalt Impregnated Building Felt
Provide a 15 lb asphalt moisture barrier over glass mat covered or reinforced gypsum sheathing. Conforming to ASTM D226/D226M Type 1 (No.
15) for asphalt impregnated building felt.
SECTION 09 29 00 Page 6
2.1.11 Water
Provide clean, fresh, and potable water.
PART 3 EXECUTION
3.1 EXAMINATION
3.1.1 Framing and Furring
Verify that framing and furring are securely attached and of sizes and spacing to provide a suitable substrate to receive gypsum board and cementitious backer units. Verify that all blocking, headers and supports are in place to support plumbing fixtures and to receive soap dishes, grab bars, towel racks, and similar items. Do not proceed with work until framing and furring are acceptable for application of gypsum board and cementitious backer units.
3.1.2 Masonry Walls
Verify that surfaces of masonry walls to receive gypsum board applied with adhesive are dry, free of dust, oil, form release agents, protrusions and voids, and any other foreign matter. Do not proceed with work until surfaces are acceptable for application of gypsum board with adhesive.
3.1.3 Building Construction Materials
Do not install building construction materials that show visual evidence of biological growth.
3.2 APPLICATION OF GYPSUM BOARD
Apply gypsum board to framing and furring members in accordance with ASTM C840 or GA 216 and the requirements specified. Apply gypsum board with separate panels in moderate contact; do not force in place. Stagger end joints of adjoining panels. Neatly fit abutting end and edge joints.
Use gypsum board of maximum practical length; select panel sizes to minimize waste. Cut out gypsum board to make neat, close, and tight joints around openings. In vertical application of gypsum board, provide panels in lengths required to reach full height of vertical surfaces in one continuous piece. Lay out panels to minimize waste; reuse cutoffs whenever feasible. Surfaces of gypsum board and substrate members may not be bonded together with an adhesive, except where prohibited by fire rating(s). Treat edges of cutouts for plumbing pipes, screwheads, and joints with water-resistant compound as recommended by the gypsum board manufacturer. Provide type of gypsum board for use in each system specified herein as indicated.
3.2.1 Application of Two-Ply Gypsum Board to Wood Framing
Apply in accordance with ASTM C840, System II or GA 216 .
3.2.2 Adhesive Nail-On Application to Wood Framing
Apply in accordance with ASTM C840, System III or GA 216 . This method may be used in lieu of ASTM C840, System I at the option of the Contractor.
SECTION 09 29 00 Page 7
3.2.3 Adhesive Application to Interior Masonry or Concrete Walls
Apply in accordance with ASTM C840, System VI or GA 216 .
3.2.4 Application of Gypsum Board to Steel Framing and Furring
Apply in accordance with ASTM C840, System VIII or GA 216 .
3.2.5 Gypsum Board for Wall Tile or Tile Base Applied with Adhesive
In dry areas (areas other than tubs, shower enclosures, saunas, steam rooms, gang shower rooms), apply glass mat water-resistant gypsum tile backing board or water-resistant gypsum backing board in accordance with ASTM C840, System X or GA 216 .
3.2.6 Exterior Application
Apply exterior gypsum board (such as at soffits) in accordance with ASTM C840, System XI or GA 216 .
3.2.7 Glass Mat Covered or Fiber Reinforced Gypsum Sheathing
Apply glass mat covered or fiber reinforced gypsum sheathing in accordance to gypsum association publications GA 253 . Follow gypsum sheathing manufacturer's requirements of design details for joints and fasteners and be properly installed to protect the substrate from moisture intrusion.
Do not leave exposed surfaces of the glass mat covered or fiber reinforced gypsum sheathing beyond the manufacturer's recommendation without a weather barrier cladding. Provide continuous air and moisture barrier over sheathing surface in shingle fashion with edges and ends lapped a minimum of 6 inch . Properly flash the openings. Seal all joints, seams, and penetrations with a compatible sealant.
3.2.8 Control Joints
Install expansion and contraction joints in ceilings and walls in accordance with ASTM C840, System XIII or GA 216 . Fill control joints between studs in fire-rated construction with firesafing insulation to match the fire-rating of construction.
3.2.9 Application of Foil-Backed Gypsum Board
Apply foil-backed gypsum board in accordance with ASTM C840, System XIV or
GA 216 .
3.3 APPLICATION OF CEMENTITIOUS BACKER UNITS
3.3.1 Application
In wet areas (tubs, shower enclosures, saunas, steam rooms, gang shower rooms), apply cementitious backer units in accordance with ANSI A108.11 .
Place a 15 lb asphalt impregnated, continuous felt paper membrane behind cementitious backer units, between backer units and studs or base layer of gypsum board. Place membrane with a minimum 6 inch overlap of sheets laid shingle style.
3.3.2 Joint Treatment
ANSI A108.11 .
SECTION 09 29 00 Page 8
3.4 FINISHING OF GYPSUM BOARD
Tape and finish gypsum board in accordance with ASTM C840, GA 214 and GA 216 . Finish plenum areas above ceilings to Level 1 in accordance with GA 214 . Finish water resistant gypsum backing board, ASTM C1396/C1396M , to receive ceramic tile to Level 2 in accordance with GA 214 . Finish walls and ceilings to receive a heavy-grade wall covering or heave textured finish before painting to Level 3 in accordance with GA 214 .
Finish walls and ceilings without critical lighting to receive flat paints, light textures, or wall coverings to Level 4 in accordance with GA 214 . Unless otherwise specified, finish all gypsum board walls, partitions and ceilings to Level 5 in accordance with GA 214 . Provide joint, fastener depression, and corner treatment. Tool joints as smoothly as possible to minimize sanding and dust. Do not use self-adhering fiber glass mesh tape with conventional drying type joint compounds; use setting or hardening type compounds only. Provide treatment for water-resistant gypsum board as recommended by the gypsum board manufacturer. Protect workers, building occupants, and HVAC systems from gypsum dust.
3.4.1 Uniform Surface
Wherever gypsum board is to receive eggshell, semigloss or gloss paint finish, or where severe, up or down lighting conditions occur, finish gypsum wall surface in accordance to GA 214 Level 5. In accordance with GA 214 Level 5, apply a thin skim coat of joint compound to the entire gypsum board surface, after the two-coat joint and fastener treatment is complete and dry.
3.5 SEALING
Seal openings around pipes, fixtures, and other items projecting through gypsum board and cementitious backer units as specified in Section 07 92 00 JOINT SEALANTS. Apply material with exposed surface flush with gypsum board or cementitious backer units.
3.5.1 Sealing for Glass Mat or Reinforced Gypsum Board Sheathing
Apply silicone sealant in a 3/8 inch bead to all joints and trowel flat.
Apply enough of the same sealant to all fasteners penetrating through the glass mat gypsum board surface to completely cover the penetration when troweled flat. Do not place construction and materials behind sheathing until a visual inspection of sealed joints during daylight hours has been completed by Contracting Officer.
3.6 FIRE-RESISTANT ASSEMBLIES
Wherever fire-rated construction is indicated, provide materials and application methods, including types and spacing of fasteners, wall and ceiling framing in accordance with the specifications contained in for the Design Number(s) indicated. Joints of fire-rated gypsum board enclosures must be closed and sealed in accordance with UL test requirements or GA requirements. Seal penetrations through rated partitions and ceilings tight in accordance with tested systems.
3.7 PATCHING
Patch surface defects in gypsum board to a smooth, uniform appearance, ready to receive finishes. Provide new predecorated gypsum board.
SECTION 09 29 00 Page 9
SECTION 09 29 00 Page 10
SECTION 09 30 10
CERAMIC, QUARRY, AND GLASS TILING
11/13
PART 1 GENERAL
1.1 REFERENCES
The publications listed below form a part of this specification to the extent referenced. The publications are referred to within the text by the basic designation only.
AMERICAN NATIONAL STANDARDS INSTITUTE (ANSI)
ANSI A137.1 (2012) American National Standards Specifications for Ceramic Tile
ASTM INTERNATIONAL (ASTM)
ASTM A1064/A1064M (2016b) Standard Specification for Carbon-Steel Wire and Welded Wire Reinforcement, Plain and Deformed, for Concrete
ASTM C144 (2011) Standard Specification for Aggregate for Masonry Mortar
ASTM C150/C150M (201 7) Standard Specification for Portland Cement
ASTM C206 (2014) Standard Specification for Finishing Hydrated Lime
ASTM C207 (2006; R 2011) Standard Specification for Hydrated Lime for Masonry Purposes
ASTM C33/C33M (2016) Standard Specification for Concrete Aggregates
ASTM C648 (2004; R 2009) Breaking Strength of Ceramic Tile
ASTM C847 (2014a) Standard Specification for Metal Lath
ASTM D2103 (2015) Standard Specification for Polyethylene Film and Sheeting
ASTM D226/D226M (2009) Standard Specification for Asphalt-Saturated Organic Felt Used in Roofing and Waterproofing
BAY AREA AIR QUALITY MANAGEMENT DISTRICT (BAAQMD)
BAAQMD Reg 8, Rule 51 (2002) Adhesive and Sealant Products
SECTION 09 30 10 Page 1
SOUTH COAST AIR QUALITY MANAGEMENT DISTRICT (SCAQMD)
SCAQMD Rule 1168 (1989; R 2005) Adhesive and Sealant Applications
TILE COUNCIL OF NORTH AMERICA (TCNA)
TCNA Hdbk (2013) Handbook for Ceramic, Glass, and Stone Tile Installation
1.2 SUBMITTALS
Government approval is required for submittals with a "G" designation;
submittals not having a "G" designation are for Contractor Quality Control approval.
SD-02 Shop Drawings
Detail Drawings ; G
SD-03 Product Data
Tile ; G
Setting-Bed ; G
Mortar, Grout, and Adhesive ; G
SD-04 Samples
Tile ; G
Grout ; G
SD-07 Certificates
Tile
Mortar, Grout, and Adhesive
SD-08 Manufacturer's Instructions
Maintenance Instructions
SD-10 Operation and Maintenance Data
Installation ; G
1.3 QUALITY ASSURANCE
Installers to be from a company specializing in performing this type of work and have a minimum of two years experience. Each type and color of tile to be provided from a single source. Each type and color of mortar, adhesive, and grout to be provided from the same source.
1.4 DELIVERY, STORAGE, AND HANDLING
Ship tiles in sealed packages and clearly marked with the grade, type of tile, producer identification, and country of origin. Deliver materials
SECTION 09 30 10 Page 2 to the project site in manufacturer's original unopened containers with seals unbroken and labels and hallmarks intact. Protect materials from weather, and store them under cover in accordance with manufacturer's printed instructions.
1.5 ENVIRONMENTAL REQUIREMENTS
Do not perform ceramic tile work unless the substrate and ambient temperature is at least 50 degrees F and rising. Maintain temperature above 50 degrees F while the work is being performed and for at least 7 days after completion of the work. When temporary heaters are used, ventilate the area to the outside to avoid carbon dioxide damage to new tilework.
1.6 WARRANTY
Provide manufacturer's standard performance guarantees or warranties that extend beyond a 1-year period.
1.7 EXTRA MATERIALS
Supply an extra 2 percent of each type tile used in clean and marked cartons.
PART 2 PRODUCTS
2.1 TILE
Furnish tiles that comply with ANSI A137.1 and are standard grade tiles.
Provide a minimum breaking strength of 125 lbs. for wall tile and 250 lbs.
for floor tile in accordance with ASTM C648. Submit samples of sufficient size to show color range, pattern, type and joints. Submit manufacturer's catalog data.
2.1.1 Glazed Wall Tile
Furnish glazed wall tile that has cushioned edges and trim with lead-free gloss finish. Provide nominal tile size(s) of 3 by 6 inch .
2.2 SETTING-BED
Submit manufacturer's catalog data. Compose the setting-bed of the following materials:
2.2.1 Aggregate for Concrete Fill
Conform to ASTM C33/C33M for aggregate fill. Do not exceed one-half the thickness of concrete fill for maximum size of coarse aggregate.
2.2.2 Portland Cement
Conform to ASTM C150/C150M for cement, Type I, white for wall mortar and gray for other uses.
2.2.3 Sand
Conform to ASTM C144 for sand.
SECTION 09 30 10 Page 3
2.2.4 Hydrated Lime
Conform to ASTM C206 for hydrated lime, Type S or ASTM C207, Type S.
2.2.5 Metal Lath
Conform to ASTM C847 for flat expanded type metal lath, and weighing a minimum 2.5 pound/square yard .
2.2.6 Reinforcing Wire Fabric
Conform to ASTM A1064/A1064M for wire fabric. Provide 2 by 2 inch mesh, 16/16 wire.
2.3 WATER
Provide potable water.
2.4 MORTAR, GROUT, AND ADHESIVE
Submit certificates indicating conformance with specified requirements.
Submit manufacturer's catalog data. Conform to SCAQMD Rule 1168 and BAAQMD Reg 8, Rule 51 , and to the following for mortar, grout , adhesive, and sealant:
2.4.1 Dry-Set Portland Cement Mortar
TCNA Hdbk. Medium bed mortar, large format tiles.
2.4.2 Latex-Portland Cement Mortar
TCNA Hdbk.
2.4.3 Ceramic Tile Grout
TCNA Hdbk; petroleum-free and plastic-free sand portland cement grout , latex-portland cement grout or commercial portland cement grout.
2.4.4 Sealants
Comply with applicable regulations regarding toxic and hazardous materials and as specified. Grout sealant must not change the color or alter the appearance of the grout.
2.4.5 Cementitious Backer Board
Provide cementitious backer units, for use as tile substrate over wood sub-floors, in accordance with TCNA Hdbk. Furnish 1/2 inch thick cementitious backer units.
2.5 WATERPROOFING AND CRACK-SUPPRESSION MEMBRANES FOR THIN-SET TILE
INSTALLATIONS
General: Manufacturer's product selected from the following, that complies with ANSI A118.10 and ANSI A118.12 for high (greater than 1/8 inch ) performance and is recommended by the manufacturer for the application indicated. Include reinforcement and accessories recommended by manufacturer.
SECTION 09 30 10 Page 4
a. Chlorinated-Polyethylene-Sheet Product: Nonplasticized, chlorinated polyethylene faced on both sides with high-strength, nonwoven polyester fabric, for adhering to latex-portland cement mortar; 60 inches wide by 0.030-inch nominal thickness.
1. Product: Noble Company (The); Nobleseal CIS.
b. PVC-Sheet Product: Two layers of PVC sheet heat-fused together and to facings of bondable nonwoven polyester, for adhering to latex-portland cement mortar; 60 inches wide by 0.040-inch nominal thickness.
c. Fabric-Reinforced, Modified-Bituminous-Sheet Product: Self-adhering SBS-modified-bituminous sheet with woven reinforcement facing for adhering to latex-portland cement mortar; 36 inches wide by 0.040-inch nominal thickness.
d. Fabric-Reinforced, Fluid-Applied Membrane: System consisting of liquid-latex rubber or elastomeric polymer and fabric reinforcement.
2.6 CRACK-SUPPRESSION MEMBRANE
General: Manufacturer's product selected from the following, that complies with ANSI A118.12 for high (greater than 1/8 inch ) performance and is recommended by the manufacturer for the application indicated.
a. Fabric-Reinforced Modified-Bituminous Sheet
b. Fabric-Reinforced, Fluid-Applied Membrane
c. Fluid-Applied Membrane
2.7 WATERPROOFING ONLY MEMBRANES FOR TILE INSTALLATIONS
General: Manufacturer's standard product, selected from the following that complies with ANSI A118.10 and is recommended by the manufacturer for the application indicated. Include reinforcement and accessories recommended by manufacturer.
a. Chlorinated Polyethylene Sheet: Nonplasticized, chlorinated polyethylene faced on both sides with nonwoven polyester fabric;
0.030-inch nominal thickness.
b. PVC Sheet: Two layers of PVC sheet heat-fused together and facings of nonwoven polyester; 0.040-inch nominal thickness.
c. Fabric-Reinforced, Modified-Bituminous Sheet; Self-adhering, SBS-modified-bituminous sheet with woven reinforcement facing;
0.040-inch nominal thickness.
d. Fabric-Reinforced, Fluid-Applied Membrane: System consisting of liquid-latex rubber or elastomeric polymer and continuous fabric reinforcement.
e. Fluid-Applied Membrane: Liquid-latex rubber or elastomeric polymer.
2.8 MEMBRANE MATERIALS
Conform to ASTM D226/D226M, Type 1 for 15 pound waterproofing membrane, asphalt-saturated building felt. Conform to ASTM D2103, 4 mil for
SECTION 09 30 10 Page 5 polyethylene film.
2.9 COLOR, TEXTURE, AND PATTERN
Provide color, pattern and texture as indicated. Provide floor patterns as specified on the drawings.
PART 3 EXECUTION
3.1 PREPARATORY WORK AND WORKMANSHIP
Inspect surface to receive tile in conformance to the requirements of TCNA Hdbk for surface conditions for the type setting bed specified and for workmanship. Provide variations of tiled surfaces that fall within maximum values shown below:
TYPE WALLS FLOORS
Dry-Set Mortar 1/8 inch in 8 ft. 1/8 inch in 10 ft.
Organic Adhesives 1/8 inch in 8 ft. 1/16 inch in 3 ft.
Latex Portland Cement Mortar 1/8 inch in 8 ft. 1/8 inch in 10 ft.
Epoxy 1/8 inch in 8 ft. 1/8 inch in 10 ft.
3.2 GENERAL INSTALLATION REQUIREMENTS
Do not start tile work until roughing in for mechanical and electrical work has been completed and tested, and built-in items requiring membrane waterproofing have been installed and tested. Close space, in which tile is being set, to traffic and other work. Keep closed until tile is firmly set. Do not start floor tile installation in spaces requiring wall tile until after wall tile has been installed. Apply tile in colors and patterns indicated in the area shown on the drawings. Install tile with the respective surfaces in true even planes to the elevations and grades shown. Provide special shapes as required for sills, jambs, recesses, offsets, external corners, and other conditions to provide a complete and neatly finished installation. Solidly back tile bases and coves with mortar. Do not walk or work on newly tiled floors without using kneeling boards or equivalent protection of the tiled surface. Keep traffic off horizontal portland cement mortar installations for at least 72 hours.
Keep all traffic off epoxy installed floors for at least 40 hours after grouting, and heavy traffic off for at least 7 days, unless otherwise specifically authorized by manufacturer. Dimension and draw detail drawings at a minimum scale of 1/4 inch = 1 foot . Include drawings of pattern at inside corners, outside corners, termination points and location of all equipment items such as thermostats, switch plates, mirrors and toilet accessories mounted on surface. Submit drawings showing ceramic tile pattern elevations and floor plans. Submit manufacturer's preprinted installation instructions.
3.3 INSTALLATION OF WALL TILE
Install wall tile in accordance with the TCNA Hdbk, method W2021 - Masonry, W244C - Cement Board, W245 - Water Resistant Glass Mat Board, and with grout joints as recommended by the manufacturer for the type of tile.
SECTION 09 30 10 Page 6
3.3.1 Latex-Portland Cement Mortar
Use Latex-Portland Cement to install tile in accordance with TCNA Hdbk.
Use Latex Portland Cement when installing porcelain ceramic tile.
3.3.2 Ceramic Tile Grout
Prepare and install ceramic tile grout in accordance with TCNA Hdbk.
Provide and apply manufacturer's standard product for sealing grout joints in accordance with manufacturer's recommendations.
3.4 WALLS
Provide expansion joints at control joints in backing material. Wherever backing material changes, install an expansion joint to separate the different materials.
3.5 CLEANING AND PROTECTING
Upon completion, thoroughly clean tile surfaces in accordance with manufacturer's approved cleaning instructions. Do not use acid for cleaning glazed tile. Clean floor tile with resinous grout or with factory mixed grout in accordance with printed instructions of the grout manufacturer. After the grout has set, provide a protective coat of a noncorrosive soap or other approved method of protection for tile wall surfaces. Cover tiled floor areas with building paper before foot traffic is permitted over the finished tile floors. Provide board walkways on tiled floors that are to be continuously used as passageways by workmen.
Replace damaged or defective tiles. Submit copy of manufacturer's printed maintenance instructions .
SECTION 09 30 10 Page 7
SECTION 09 67 23.13
STANDARD RESINOUS FLOORING
11/15
PART 1 GENERAL
1.1 REFERENCES
The publications listed below form a part of this specification to the extent referenced. The publications are referred to within the text by the basic designation only.
ASTM INTERNATIONAL (ASTM)
ASTM A990/A990M (2014a) Standard Specification for Castings, Iron-Nickel-Chromium and Nickel Alloys, Specially Controlled for Pressure Retaining Parts for Corrosive Service
ASTM C881/C881M (2015) Standard Specification for Epoxy-Resin-Base Bonding Systems for Concrete
ASTM D1475 (2013) Standard Test Method for Density of Liquid Coatings, Inks, and Related Products
ASTM D1544 (2004; R 2010) Standard Test Method for Color of Transparent Liquids (Gardner Color Scale)
ASTM D1652 (2011; E 2012) Standard Test Method for Epoxy Content of Epoxy Resins
ASTM D2240 (2015) Standard Test Method for Rubber Property - Durometer Hardness
ASTM D2471 (1999) Standard Test Method for Gel Time and Peak Exothermic Temperature of Reacting Thermosetting Resins
ASTM D445 (2015a) Standard Test Method for Kinematic Viscosity of Transparent and Opaque Liquids (and the Calculation of Dynamic Viscosity)
ASTM D523 (2014) Standard Test Method for Specular Gloss
ASTM D570 (1998; E 2010; R 2010) Standard Test Method for Water Absorption of Plastics
ASTM D638 (2014) Standard Test Method for Tensile Properties of Plastics
ASTM D696 (2016) Standard Test Method for Coefficient of Linear Thermal Expansion of Plastics Between -30 degrees C and 30
SECTION 09 67 23.13 Page 1 degrees C With a Vitreous Silica Dilatometer
1.2 ADMINISTRATIVE REQUIREMENTS
1.2.1 Product Data
Within 30 days of contract award, submit manufacturer's catalog data for the following items:
a. Epoxy-Resin Binder/Matrix
b. Cured Epoxy Binder
c. Aggregate
d. Surface Sealing Coat
1.2.2 Design Mix Data
Within 30 days of contract award, submit design mix data for the following items, including a complete list of ingredients and admixtures:
a. Epoxy-Resin Binder/Matrix
b. Cured Epoxy Binder
c. Surface Sealing Coat
Ensure applicable test reports verify the mix has been successfully tested and meets design requirements.
1.3 SUBMITTALS
Government approval is required for submittals with a "G" designation;
submittals not having a "G" designation are for Contractor Quality Control approval. Submit the following in accordance with Section 01 33 00.00 50
SUBMITTAL PROCEDURES:
SD-02 Shop Drawings
Installation Drawings ; G
SD-03 Product Data
Manufacturer's Catalog Data ; G
SD-04 Samples
Hardboard Mounted Epoxy Flooring ; G
Floor Topping ; G
SD-05 Design Data
Design Mix Data ; G
SD-07 Certificates
SECTION 09 67 23.13 Page 2
Listing of Product Installations ; G
Referenced Standards Certificates ; G
SD-11 Closeout Submittals
Warranty ; G
1.4 DELIVERY, STORAGE, AND HANDLING
Protect materials from weather, soil, and damage during delivery, storage, and construction. Deliver materials in original packages, containers, or bundles bearing brand name and name of material.
Maintain materials used in the installation of floor topping at a temperature between 65 and 85 degrees F .
1.5 QUALITY CONTROL
Prior to commencement of work, submit referenced standards certificates for the following, showing conformance with the referenced standards contained in this section:
a. Epoxy-Resin Binder/Matrix
b. Cured Epoxy Binder
c. Aggregate
d. Surface Sealing Coat
1.5.1 Qualifications
Submit a listing of product installations for heavy duty epoxy flooring including identification of at least 5 units, similar to those proposed for use, that have been in successful service for a minimum period of 5 years. Identify purchaser, address of installation, service organization, and date of installation.
Ensure floor system applicators are experienced in the application of troweled aggregate thin-set floor topping.
1.5.2 Sampling
Submit hardboard mounted epoxy flooring samples not less than 12-inch square for each required color.
Provide panels showing nominal thickness of finished toppings, color, and texture of finished surfaces. Finished floor toppings and the approved samples are to match in color and texture.
1.6 WARRANTY
Submit a 2 year written warranty for all materials and installation work.
SECTION 09 67 23.13 Page 3
PART 2 PRODUCTS
2.1 SYSTEM DESCRIPTION
Submit installation drawings for heavy duty epoxy flooring systems clearly designating the areas of application and the installation plan. Include in the installation plan, methods to control sand and dust if sand blasting is required.
2.2 MATERIALS
2.2.1 Mixes
2.2.1.1 Epoxy-Resin Binder/Matrix
Provide a clear two-component compatible system epoxy resin binder consisting of: (1) a liquid blend of a biphenyl-based epoxy resin and an aliphatic polyglyceride ether, and (2) a liquid blend of two modified amine curing agents, which individually cures the epoxy resin at room temperature to a glossy smooth film. Ensure the two components and the cured epoxy binder have the following physical properties:
PROPERTY TEST METHOD REQUIREMENT
COMPONENT A (EPOXY RESIN)
Viscosity (kinematic), at 77 degrees F, centipoises
ASTM D445 3000 to 5000
Weight per epoxide, grams ASTM D1652 205 to 225
Color (Gardner Color Scale), maximum
ASTM D1544 5
Weight per gallon, pounds ASTM D1475 9.46 - 9.56
COMPONENT B (CURING AGENT)
Viscosity (kinematic), at 77 degrees F, centistokes
ASTM D445 75 to 125
Weight per gallon, pounds ASTM D1475 7.50 to 7.60
Color (Gardner Color Scale), maximum
ASTM D1544 8
2.2.1.2 Cured Epoxy Binder
Provide a cured epoxy binder with the following properties.
PROPERTY TEST METHOD REQUIREMENT
Tensile strength, psi* at test temperature:
77 degrees F
ASTM D638 4500 to 6500
SECTION 09 67 23.13 Page 4
PROPERTY TEST METHOD REQUIREMENT
Tensile elongation, percent* at test temperature: 77 degrees F
ASTM D638 20 to 40
Water absorption, percent 24 hours at 77 degrees F, maximum
ASTM D570 0.40
Hardness, Shore D ASTM D2240 74 to 82
Linear shrinkage, inch/inch maximum
ASTM C881/C881M 0.006
Shrinkage, glass bow, inch divergence, maximum
ASTM A990/A990M 0.016
Coefficient of linear thermal expansion, inch/inch/degree C, maximum
ASTM D696
0 degrees C to 40 degrees C
200 X 10-6
Gel time/peak exotherm at 77 degrees F, 100 gm mass in 4-ounce metal container
ASTM D2471 20 to 40 minutes at 300 degrees F, maximum
*1/8 inch thick castings
**1/8 by 1 by 3 inch castings, aged in forced draft oven
2.2.1.3 Aggregate
Provide aggregate recommended by the resinous flooring manufacturer and approved by the Contracting Officer. Deliver aggregate to the site in three separate package gradations for blending. Gradations are:
PERCENT
SIEVE SIZE MAXIMUM MINIMUM
GRADUATION NO. 1
Retained on No. 6 0.0 -
Passing No. 6, retained on No. 8 5.0 0.0
Passing No. 8, retained on No. 12 100.0 74.0
Passing No. 20 1.0 -
GRADATION NO. 2
SECTION 09 67 23.13 Page 5
PERCENT
SIEVE SIZE MAXIMUM MINIMUM
Retained on No. 16 0.0 -
Passing No. 16, retained on No. 18 5.0 0.0
Passing No. 18, retained on No. 40 100.0 85.0
Passing No. 40, retained on No. 60 9.0 0.0
Passing No. 60 1.0 -
GRADATION NO. 3
Retained on No. 20 0.0 -
Passing No. 20, retained on No. 35 5.0 0.0
Passing No. 35, retained on No. 60 100.0 80.0
Passing No. 60, retained on No. 100 13.0 0.0
Passing No. 100 2.0 -
2.2.1.4 Surface Sealing Coat
Provide nonambering aliphatic or aromatic moisture-curing polyurethane surface sealer into which has been incorporated a flatting agent. Add flatting agent not more than 24 hours prior to actual application of the coating. Ensure cured coating with flatting agent yields 60-degree specular gloss of 10 to 20 when tested in accordance with ASTM D523.
PART 3 EXECUTION
3.1 PREPARATION
Prior to applying resinous flooring material, inspect substrate and immediately report any unsatisfactory conditions that exist and repair.
3.1.1 Safety Precautions
Prior to application in confined spaces of toppings and coatings containing flammable or toxic properties, institute safety precautions recommended by the manufacturer of the product.
Erect "NO SMOKING" signs, and prohibit smoking or use of spark- or flame-producing devices within 50 feet of any mixing or placing operation involving flammable materials.
Provide personnel required to handle, mix, or apply toppings containing toxic or flammable properties with such items of personal protective equipment and apparel for eye, skin, and respiratory protection as are recommended by the manufacturer of the product. Ensure all personnel are
SECTION 09 67 23.13 Page 6 trained in the appropriate use and wearing of personal protection equipment.
3.1.2 Protection of Adjacent Surfaces
In addition to the protection of adjacent surfaces during installation, provide areas used to store and mix materials with a protective covering under the materials. After application of the sealer coats, protect finished flooring during the remainder of the construction period. In areas of expected minimum or moderate traffic, cover floors with a 30-30-30 waterproof kraft paper, with strips taped together and edges secured to prevent roll-up. Place vegetable fiberboard, plywood, or other suitable material that does not mar the flooring over the paper to protect areas used as passages by workmen and areas subject to floor damage because of subsequent building operations. Upon completion of construction, remove the protection, clean flooring and, where necessary, repair, reseal, or both, at no additional cost to the Government.
3.1.3 Concrete Subfloor
3.1.3.1 New Concrete Floors
Do not commence installation of floor topping until concrete has cured a minimum of 28 calendar days. Verify concrete floor is straight, properly sloped, and has broom type finish. Ensure concrete is moist cured with burlap or polyethylene. Prior to applying the prime coat, clean concrete surface by an approved method.
3.1.4 Mixing Of Materials
Select job mix proportions on the trial batch proportions used to prepare the floor topping samples as submitted and approved.
Use mechanical equipment for mixing of materials in accordance with the manufacturer's instructions.
Use rotating paddle-type masonry mortar mixers for preblending the three sizes and color pigment, if any, of the walnut shell aggregate and addition of the mixed epoxy resin binder. Ensure mixing times are as recommended by the materials supplier(s), provided mixing times result in homogeneous mixtures. Limit quantity of material mixed at one time to that which can be applied and finished within the working life of the mixtures. Verify temperature of materials at the time of mixing are between 65 and 85 degrees F .
3.2 APPLICATION
3.2.1 Areas of Application
Anchor plates set with the top surface at or above the finished epoxy floor level do not require coverage with this flooring material. Extend flooring under equipment, except when the equipment base is indicated to be flush against the structural floor. Cover and/or mask surfaces not to receive the epoxy floor topping, such as equipment or cabinets installed prior to surface-preparation efforts and adjacent to the flooring installation.
SECTION 09 67 23.13 Page 7
3.2.2 Application of Prime Coat and Troweling
Combine the epoxy binder components A and B in the proportions specified by the manufacturer to form a clear compatible system immediately on mixing. Cure combined components to a clear film possessing a glossy, non-greasy surface at relative humidities less than 80 percent, having the following properties after curing 24 hours at 77 degrees F , followed by 24 hours at 125 degrees F :
Ensure prepared subfloor surface is dry and at a temperature of not less than 60 degrees F when application of the floor topping is initiated.
Immediately prior to application of the prime/scratch coat on the prepared surface, remove dust or other loose particles by blowing with compressed air or vacuum cleaned. Use only an air compressor equipped with an efficient oil-water trap to prevent oil contamination or wetting of surface.
Apply a thin roller coat of the epoxy binder specified to the prepared subfloor as a prime coat. As an aid to placing, compacting, and finishing the floor topping, form a scratch coat by sprinkling a minimum quantity of the walnut shell aggregate on the prime coat surface immediately following the prime coat application. Prior to application of the prime/scratch coat, fill cracks in the concrete, and make provisions to keep control or expansion joints open.
Place the floor topping prior to final gelling of the prime/scratch coat.
Immediately after the materials are mixed as specified, dump the mixture in the placement area and spread to prolong troweling life. Screed or rough trowel placed materials to the specified thickness and then compact by the use of a smooth roller prior to finish troweling to a nominal thickness of 3/16-inch plus or minus 1/16-inch . Ensure all finished surfaces are free of ridges, hollows (bird-baths), trowel marks, and smoothness varies no more than 1/8-inch when tested with an 8-foot straightedge. Make provisions to maintain the work areas in a relatively dust-free environment during curing of the topping.
3.2.3 Sealer Coat
After the floor topping has set firmly (approximately 6 to 16 hours depending on subfloor temperature) in a relatively dust-free environment, apply two thin coats of the sealer coat, by means of brush, roller, squeegee, or notched trowel to provide a pore-free, easy-to-clean surface. At the time of sealer application, ensure the surface is dust-free. Depending on relative humidity, allow the applied sealer to cure to a tack-free condition in 2 to 4 hours. Do not apply second coat until after the initial coat has cured to a tack-free, hard film.
Maintain topping areas in a relatively dust-free environment during curing of the sealer coats.
3.2.4 Integral Cove Base
Provide a 4-inch high cove base to all wall surfaces as indicated on the drawings. Install so as to provide a 1/2-inch radius at the juncture of the floor and the…
This is the start of the file's text. The full file is on GovTribe.
File details come from the government source that posted it. Updated .