This is a pre-solicitation notice for an HVAC system project at Aviano Air Base in Italy. The project involves renovating and upgrading HVAC systems across multiple buildings in Areas F and C of the base. Work includes demolitions, new mechanical equipment such as air handlers and chillers, ductwork, controls, and electrical work. Estimated value is between $500,000 to $1 million. Interested vendors must have an active SAM registration and an adequate SOA certification in category OG11. A mandatory site visit will be held in November 2019 in advance of issuance of the solicitation later that month. The work must be performed according to Italian law. Questions should be directed to the website for notifications of solicitation changes. The Air Force is the contracting agency.
ASHE 18-1087 CCEB BLANK FY20
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
| CONSTRUCTION COST ESTIMATE BREAKDOWN | |
| CONTRACTOR | ADDRESS |
| CONTRACT FOR (Work to be performed) | PROPOSED TOTAL CONTRACT PRICE | |||||||||
| DESIGN FOR SUSTAIN HVAC SYSTEM MULTI - BLDG 410 | ||||||||||
| PURCHASE REQUEST NUMBER | PROJECT NUMBER | WORK LOCATION | ||||||||
| ASHE 18-1087 | AREA C, AVIANO AIR BASE, ITALY | |||||||||
| MATERIAL COSTS | LABOR COSTS | |||||||||
| LINE NO. | ITEM | UNIT OF MEASURE | QUANTITY | UNIT | TOTAL | MANHOURS MANDAYS | AVERAGE RATE | TOTAL | OTHER DIRECT COSTS | LINE TOTAL |
| (1) | (2) | (3) | (4) | (5) | (6) | (7) | (8) | (9) | (10) | |
| BLDG 410 | ||||||||||
| PART I - DEMOLITIONS, EXCAVATIONS AND REMOVALS / Parte I - Demolizioni, Scavi e Rimozioni |
| Ia Architectural Demolition - Ia Demolizioni Architettoniche | |||||||
| Not Applicable/Non applicabile | |||||||
| Ib Mechanical Demolitions - Demolizioni Meccaniche | |||||||
| 1 | REMOVAL OF EXISTING VERTICAL CABINET FANCOIL UNIT, MECHANICAL & ELECTRICAL CONNECTIONS AND FITTINGS | ||||||
| Rimozione del ventilconvettore a mobiletto esistente, connessioni meccaniche ed elettriche ed accessori | IT. No. Art. n. | 1 | LS/AC | 0.00 | 0.00 | ||
| 2 | REMOVAL OF EXISTING 4 WAY CASSETTE FANCOIL UNIT, MECHANICAL & ELECTRICAL CONNECTIONS AND FITTINGS | ||||||
| Rimozione del ventilconvettore a cassetta a 4 vie esistente, connessioni meccaniche ed elettriche ed accessori | IT. No. Art. n. | 2 | LS/AC | 0.00 | 0.00 | ||
| Total Mechanical - Totale Meccanico | 0.00 | ||||||
| Ic Electrical Demolitions - Ie Demolizioni Elettriche | |||||||
| 3 | REMOVE F/A SYSTEM | ||||||
| Rimozione Impianto Allarme Incendio | IT. No. Art. n. | 3 | LS/AC | 0.00 | 0 | 0.00 | |
| Total Electrical - Totale Elettrico |
| TOTAL PART I / Totale Parte I |
| PART II - ARCHITECTURAL, STRUCTURAL AND CIVIL WORK / Parte II - Lavori Architettonici, Strutturali e Civili |
| IIa Architectural - IIa Architettonico | ||||||||
| 4 | REMOVAL AND REINSTALLATION OF SUSPENDED CEILING PANELS | |||||||
| Rimozione e reinstallazione pannelli contrrosoffitto | IT. No. Art. n. | 1 | LS/AC | 0.00 | 0.00 | 0 | 0.00 | 0.00 |
| 5 | PREPAINTED GALVANIZED STEEL PIPING COVER | |||||||
| Carter in accio zincato preverniciatpo per protezione tubi | IT. No. Art. n. | 2 | EA/NO | 0.00 | 0.00 | 0 | 0.00 | 0.00 |
| Total Architectural - Totale Architettura |
| TOTAL PART II / Totale Parte II |
| PART III - MECHANICAL WORK / Parte III - Lavori Meccanici |
6 NEW VERTICAL CABINET ECM FANCOIL UNIT INCLUDING MECHANICAL AND ELECTRICAL CONNECTIONS,3-WAY ON/OFF CONTROL VALVE WITH ACTUATOR, SHUT-OFF VALVES, CONTROLLER, ROOM PANEL AND FITTINGS.
FCV-01
| Nuovo ventilconvettore a mobiletto ecm comprensivo di connessioni meccaniche ed elettriche, valvola di regolazione ON/OFF a 3 vie con attuatore, valvole di intercettazione, controllore, pannello di controllo ed accessori. FCV-01 | IT. No. Art. n. | 1a | EA/NO | 0.00 | 0.00 | 0.00 |
| 7 | NEW VERTICAL CABINET ECM FANCOIL UNIT INCLUDING MECHANICAL AND ELECTRICAL CONNECTIONS,3-WAY ON/OFF CONTROL VALVE WITH ACTUATOR, SHUT-OFF VALVES, CONTROLLER, ROOM PANEL AND FITTINGS. |
FCV-02
| Nuovo ventilconvettore a mobiletto ecm comprensivo di connessioni meccaniche ed elettriche, valvola di regolazione ON/OFF a 3 vie con attuatore, valvole di intercettazione, controllore, pannello di controllo ed accessori. FCV-02 | IT. No. Art. n. | 1b | EA/NO | 0.00 | 0.00 | 0.00 |
| 8 | NEW VERTICAL CABINET ECM FANCOIL UNIT INCLUDING MECHANICAL AND ELECTRICAL CONNECTIONS,3-WAY ON/OFF CONTROL VALVE WITH ACTUATOR, SHUT-OFF VALVES, CONTROLLER, ROOM PANEL AND FITTINGS. |
FCV-03
| Nuovo ventilconvettore a mobiletto ecm comprensivo di connessioni meccaniche ed elettriche, valvola di regolazione ON/OFF a 3 vie con attuatore, valvole di intercettazione, controllore, pannello di controllo ed accessori. FCV-03 | IT. No. Art. n. | 1c | EA/NO | 0.00 | 0.00 | 0.00 |
| 9 | NEW 4 WAY CASSETTE ECM FANCOIL UNIT INCLUDING MECHANICAL AND ELECTRICAL CONNECTIONS,3-WAY ON/OFF CONTROL VALVE WITH ACTUATOR, SHUT-OFF VALVES, CONTROLLER, ROOM PANEL AND FITTINGS. |
FCC-01
| Nuovo ventilconvettore a cessetta ecm comprensivo di connessioni meccaniche ed elettriche, valvola di regolazione ON/OFF a 3 vie con attuatore, valvole di intercettazione, controllore, pannello di controllo ed accessori.FCC-01 | IT. No. Art. n. | 2 | EA/NO | 0.00 | 0.00 | 0.00 | |
| 10 | SYSTEM BALANCING AND TECHNICAL TEST REPORT | ||||||
| bilanciamento del sistema e redazione report | IT. No. Art. n. | 3 | LS/AC | 0.00 | 0.00 | 0.00 | |
| Total Mechanical - Totale Meccanico |
| TOTAL PART III - Totale Parte III | |||||||||
| PART IV- ELECTRICAL WORK / Parte VI - Lavori Elettrici | |||||||||
| Fire Alarm System systems - Impianto Allarme Incedio | |||||||||
| 11 | SMOKE DETECTORS | ||||||||
| Rilevatori di fumo | IT. No. Art. n. | 1 | EA/NO | 0 | 0.00 | 0 | 0.00 | 0.00 | |
| 12 | HEAT DETECTORS | ||||||||
| Rilevarori di Calore | IT. No. Art. n. | 2 | EA/NO | 0 | 0.00 | 0 | 0.00 | 0.00 | |
| 13 | RED PILOT LIGHT | ||||||||
| Lampada spia rossa | IT. No. Art. n. | 3 | EA/NO | 0 | 0.00 | 0 | 0.00 | 0.00 | |
| 14 | PULL STATIONS | ||||||||
| Stazioni manuali | IT. No. Art. n. | 4 | EA/NO | 0 | 0.00 | 0 | 0.00 | 0.00 | |
| 15 | Audio/video devices | ||||||||
| Dispositivi audio/video | IT. No. Art. n. | 5 | EA/NO | 0 | 0.00 | 0 | 0.00 | 0.00 | |
| 16 | ADDREASSABLE FIRE ALARM CONTROL PANEL | ||||||||
| Centrale rivelazione incendi indirizzabile | IT. No. Art. n. | 6 | EA/NO | 0 | 0.00 | 0 | 0.00 | 0.00 | |
| 17 | ALARM BELL | ||||||||
| Campana di allarme | IT. No. Art. n. | 7 | EA/NO | 0 | 0.00 | 0 | 0.00 | 0.00 | |
| 18 | FTE40HM1 2X2,5 MMQ CABLE | ||||||||
| Cavo FTE40HM1 2X2,5 mmq | IT. No. Art. n. | 8 | LM/ML | 0 | 0.00 | 0 | 0.00 | 0.00 | |
| 19 | METAL CABLE TRAY 100x100 MM | ||||||||
| Canalina Metallica 100x100 mm | IT. No. Art. n. | 9 | LM/ML | 0 | 0.00 | 0 | 0.00 | 0.00 | |
| 20 | PVC RIGID CONDUIT DIAM. 40 MM | ||||||||
| Tubazione Rigida in PVC Diam. 40 mm | IT. No. Art. n. | 10a | LM/ML | 0 | 0.00 | 0 | 0.00 | 0.00 | |
| 21 | PVC RIGID CONDUIT DIAM. 25 MM | ||||||||
| Tubazione Rigida in PVC Diam. 25 mm | IT. No. Art. n. | 10b | LM/ML | 0 | 0.00 | 0 | 0.00 | 0.00 | |
| 22 | PVC FLEXIBLE CONDUIT DIAM. 25 MM | ||||||||
| Tubazione Flesibile in PVC Diam. 25 mm | IT. No. Art. n. | 11 | LM/ML | 0 | 0.00 | 0 | 0.00 | 0.00 | |
| 23 | JUNCTION BOX 80X80X40 MM | ||||||||
| Scatola di Derivazione 80x80x40 mm | IT. No. Art. n. | 12 | LM/ML | 0 | 0.00 | 0 | 0.00 | 0.00 | |
| 24 | F/A programmation | ||||||||
| Programmazione quadro F/A | IT. No. Art. n. | 13 | LS/AC | 0 | 0.00 | 0 | 0.00 | 0.00 | |
| Total Fire Alarm System - Totale Impianto Allarme Incendio | 0.00 |
TOTAL PART IV - Totale Parte IV
| SUMMARY / Riepilogo |
| PART I - DEMOLITIONS, EXCAVATIONS AND REMOVALS |
| PART II - ARCHITECTURAL, STRUCTURAL AND CIVIL WORK |
| PART III - MECHANICAL WORK |
| PART IV - ELECTRICAL WORK |
| TOTAL PRICE / Costo Totale |
OR US DOLLARS (RATE 1$ = ….................. €)
&"Arial,Grassetto"&12FOR OFFICIAL USE ONLY
&"Arial,Grassetto"&12FOR OFFICIAL USE ONLY Sheet &P of &N
| CONSTRUCTION COST ESTIMATE BREAKDOWN | |
| CONTRACTOR | ADDRESS |
| CONTRACT FOR (Work to be performed) | PROPOSED TOTAL CONTRACT PRICE | |||||||||
| DESIGN FOR SUSTAIN HVAC SYSTEM MULTI - BLDG 416 | ||||||||||
| PURCHASE REQUEST NUMBER | PROJECT NUMBER | WORK LOCATION | ||||||||
| ASHE 18-1087 | AREA C, AVIANO AIR BASE, ITALY | |||||||||
| MATERIAL COSTS | LABOR COSTS | |||||||||
| LINE NO. | ITEM | UNIT OF MEASURE | QUANTITY | UNIT | TOTAL | MANHOURS MANDAYS | AVERAGE RATE | TOTAL | OTHER DIRECT COSTS | LINE TOTAL |
| (1) | (2) | (3) | (4) | (5) | (6) | (7) | (8) | (9) | (10) | |
| BLDG 416 | ||||||||||
| PART I - DEMOLITIONS, EXCAVATIONS AND REMOVALS / Parte I - Demolizioni, Scavi e Rimozioni |
| Ia Architectural Demolition - Ia Demolizioni Architettoniche | ||||||||
| Not Applicable/Non applicabile | ||||||||
| Ib Mechanical Demolitions - Demolizioni Meccaniche | ||||||||
| 1 | REMOVAL OF EXISTING FANCOIL UNIT, MECHANICAL & ELECTRICAL CONNECTIONS AND FITTINGS | |||||||
| Rimozione del ventilconvettore esistente, connessioni meccaniche ed elettriche ed accessori | IT. No. Art. n. | 1 | LS/AC | 0.00 | 0.00 | |||
| 2 | REMOVAL OF DX UNIT, MECHANICAL & ELECTRICAL CONNECTIONS AND FITTINGS | |||||||
| Rimozione dell'unità ad espansione diretta, connessioni meccaniche ed elettriche ed accessori | IT. No. Art. n. | 2 | LS/AC | 0.00 | 0.00 | |||
| Total Mechanical - Totale Meccanico | 0.00 | |||||||
| Ic Electrical Demolitions - Ie Demolizioni Elettriche | ||||||||
| 3 | REMOVE F/A SYSTEM | |||||||
| Rimozione Impianto Allarme Incendio | IT. No. Art. n. | 3 | LS/AC | 0.00 | 0 | 0.00 | 0.00 | |
| Total Electrical - Totale Elettrico |
| TOTAL PART I / Totale Parte I |
| PART II - ARCHITECTURAL, STRUCTURAL AND CIVIL WORK / Parte II - Lavori Architettonici, Strutturali e Civili |
| IIa Architectural - IIa Architettonico | ||||||||
| 4 | REMOVAL AND REINSTALLATION OF SUSPENDED CEILING PANELS | |||||||
| Rimozione e reinstallazione pannelli contrrosoffitto | IT. No. Art. n. | 1 | LS/AC | 0.00 | 0.00 | 0 | 0.00 | 0.00 |
| 5 | PREPAINTED GALVANIZED STEEL PIPING COVER | |||||||
| Carter in accio zincato preverniciatpo per protezione tubi | IT. No. Art. n. | 2 | EA/NO | 0.00 | 0.00 | 0 | 0.00 | 0.00 |
| Total Architectural - Totale Architettura |
| TOTAL PART II / Totale Parte II |
| PART III - MECHANICAL WORK / Parte III - Lavori Meccanici |
6 NEW VERTICAL CABINET ECM FANCOIL UNIT INCLUDING MECHANICAL AND ELECTRICAL CONNECTIONS,3-WAY ON/OFF CONTROL VALVE WITH ACTUATOR, SHUT-OFF VALVES, CONTROLLER, ROOM PANEL AND FITTINGS.
FCV-01
| Nuovo ventilconvettore a mobiletto ecm comprensivo di connessioni meccaniche ed elettriche, valvola di regolazione ON/OFF a 3 vie con attuatore, valvole di intercettazione, controllore, pannello di controllo ed accessori. FCV-01 | IT. No. Art. n. | 1a | EA/NO | 0.00 | 0.00 | 0.00 |
| 7 | NEW VERTICAL CABINET ECM FANCOIL UNIT INCLUDING MECHANICAL AND ELECTRICAL CONNECTIONS,3-WAY ON/OFF CONTROL VALVE WITH ACTUATOR, SHUT-OFF VALVES, CONTROLLER, ROOM PANEL AND FITTINGS. |
FCV-02
| Nuovo ventilconvettore a mobiletto ecm comprensivo di connessioni meccaniche ed elettriche, valvola di regolazione ON/OFF a 3 vie con attuatore, valvole di intercettazione, controllore, pannello di controllo ed accessori. FCV-02 | IT. No. Art. n. | 1b | EA/NO | 0.00 | 0.00 | 0.00 |
| 8 | NEW VERTICAL CABINET ECM FANCOIL UNIT INCLUDING MECHANICAL AND ELECTRICAL CONNECTIONS,3-WAY ON/OFF CONTROL VALVE WITH ACTUATOR, SHUT-OFF VALVES, CONTROLLER, ROOM PANEL AND FITTINGS. |
FCV-03
| Nuovo ventilconvettore a mobiletto ecm comprensivo di connessioni meccaniche ed elettriche, valvola di regolazione ON/OFF a 3 vie con attuatore, valvole di intercettazione, controllore, pannello di controllo ed accessori. FCV-03 | IT. No. Art. n. | 1c | EA/NO | 0.00 | 0.00 | 0.00 | |
| 9 | SYSTEM BALANCING AND TECHNICAL TEST REPORT | ||||||
| bilanciamento del sistema e redazione report | IT. No. Art. n. | 3 | LS/AC | 0.00 | 0.00 | ||
| Total Mechanical - Totale Meccanico |
| TOTAL PART III - Totale Parte III | |||||||||
| PART IV- ELECTRICAL WORK / Parte VI - Lavori Elettrici | |||||||||
| Fire Alarm System systems - Impianto Allarme Incedio | |||||||||
| 10 | SMOKE DETECTORS | ||||||||
| Rilevatori di fumo | IT. No. Art. n. | 1 | EA/NO | 0 | 0.00 | 0 | 0.00 | 0.00 | |
| 11 | HEAT DETECTORS | ||||||||
| Rilevarori di Calore | IT. No. Art. n. | 2 | EA/NO | 0 | 0.00 | 0 | 0.00 | 0.00 | |
| 12 | RED PILOT LIGHT | ||||||||
| Lampada spia rossa | IT. No. Art. n. | 3 | EA/NO | 0 | 0.00 | 0 | 0.00 | 0.00 | |
| 13 | PULL STATIONS | ||||||||
| Stazioni manuali | IT. No. Art. n. | 4 | EA/NO | 0 | 0.00 | 0 | 0.00 | 0.00 | |
| 14 | Audio/video devices | ||||||||
| Dispositivi audio/video | IT. No. Art. n. | 5 | EA/NO | 0 | 0.00 | 0 | 0.00 | 0.00 | |
| 15 | CONVENTIONAL FIRE ALARM CONTROL PANEL | ||||||||
| Centrale Rivelazione Incendi Convenzionale | IT. No. Art. n. | 6 | EA/NO | 0 | 0.00 | 0 | 0.00 | 0.00 | |
| 16 | FTE40HM1 2X1,5 MMQ CABLE | ||||||||
| Cavo FTE40HM1 2X1,5 mmq | IT. No. Art. n. | 7 | LM/ML | 0 | 0.00 | 0 | 0.00 | 0.00 | |
| 17 | METAL CABLE TRAY 100x100 MM | ||||||||
| Canalina Metallica 100x100 mm | IT. No. Art. n. | 8 | LM/ML | 0 | 0.00 | 0 | 0.00 | 0.00 | |
| 18 | PVC RIGID CONDUIT DIAM. 40 MM | ||||||||
| Tubazione Rigida in PVC Diam. 40 mm | IT. No. Art. n. | 9a | LM/ML | 0 | 0.00 | 0 | 0.00 | 0.00 | |
| 19 | PVC RIGID CONDUIT DIAM. 25 MM | ||||||||
| Tubazione Rigida in PVC Diam. 25 mm | IT. No. Art. n. | 9b | LM/ML | 0 | 0.00 | 0 | 0.00 | 0.00 | |
| 20 | PVC FLEXIBLE CONDUIT DIAM. 25 MM | ||||||||
| Tubazione Flesibile in PVC Diam. 25 mm | IT. No. Art. n. | 10 | LM/ML | 0 | 0.00 | 0 | 0.00 | 0.00 | |
| 21 | JUNCTION BOX 80X80X40 MM | ||||||||
| Scatola di Derivazione 80x80x40 mm | IT. No. Art. n. | 11 | LM/ML | 0 | 0.00 | 0 | 0.00 | 0.00 | |
| 22 | F/A programmation | ||||||||
| Programmazione quadro F/A | IT. No. Art. n. | 12 | LS/AC | 0 | 0.00 | 0 | 0.00 | 0.00 | |
| Total Fire Alarm System - Totale Impianto Allarme Incendio | 0.00 |
TOTAL PART IV - Totale Parte IV
| SUMMARY / Riepilogo | |
| PART I - DEMOLITIONS, EXCAVATIONS AND REMOVALS | |
| PART II - ARCHITECTURAL, STRUCTURAL AND CIVIL WORK | |
| PART III - MECHANICAL WORK | € - 0 |
| PART IV - ELECTRICAL WORK | € - 0 |
| TOTAL PRICE / Costo Totale |
OR US DOLLARS (RATE 1$ = ….................. €)
&"Arial,Grassetto"&12FOR OFFICIAL USE ONLY
&"Arial,Grassetto"&12FOR OFFICIAL USE ONLY Sheet &P of &N
| CONSTRUCTION COST ESTIMATE BREAKDOWN | |
| CONTRACTOR | ADDRESS |
| CONTRACT FOR (Work to be performed) | PROPOSED TOTAL CONTRACT PRICE | ||||||||||||
| DESIGN FOR SUSTAIN HVAC SYSTEM MULTI - BLDG 907 | |||||||||||||
| PURCHASE REQUEST NUMBER | PROJECT NUMBER | WORK LOCATION | |||||||||||
| ASHE 18-1087 | AREA F, AVIANO AIR BASE, ITALY | ||||||||||||
| MATERIAL COSTS | LABOR COSTS | ||||||||||||
| LINE NO. | ITEM | UNIT OF MEASURE | QUANTITY | UNIT | TOTAL | MANHOURS MANDAYS | AVERAGE RATE | TOTAL | OTHER DIRECT COSTS | LINE TOTAL | |||
| (1) | (2) | (3) | (4) | (5) | (6) | (7) | (8) | (9) | (10) | ||||
| BLDG 907 | |||||||||||||
| PART I - DEMOLITIONS, EXCAVATIONS AND REMOVALS / Parte I - Demolizioni, Scavi e Rimozioni | |||||||||||||
| Ia Architectural Demolition - Ia Demolizioni Architettoniche | |||||||||||||
| Not Applicable/Non applicabile | |||||||||||||
| Ib Mechanical Demolitions - Demolizioni Meccaniche | |||||||||||||
| 1 | REMOVAL OF EXISTING AIR HANDLING UNIT AHU-01, INCLUDING MECHANICAL AND ELECTRICAL CONNECTIONS, ACTUTATORS, SENSORS, DDC UNIT AND FITTINGS. | ||||||||||||
| Rimozione dell'unità di trattamento aria esistente AHU-01, comprese le connessioni meccaniche ed elettriche, attuatori, sensori, unità DDC e accessori | IT. No. Art. n. | 1 | LS/AC | 0.00 | 0.00 | 0.00 | |||||||
| 2 | REMOVAL OF EXISTING MINI AIR HANDLING UNIT INCLUDING MECHANICAL AND ELECTRICAL CONNECTIONS, THERMOSTAT, CONTROL VALVES AND FITTINGS | ||||||||||||
| Rimozione della mini UTA esistente comprensiva di connessioni meccaniche ed elettriche, termostato, valvole di regolazione ed accessori | IT. No. Art. n. | 2 | LS/AC | 0.00 | 0.00 | ||||||||
| 3 | TEMPORARY REMOVAL AND RELOCATE OF EXISTING WATER TREATMENT SYSTEM TO ALLOW NEW AHU INSTALL. | ||||||||||||
| Rimozione temporanea e riposizionamento dell'esistente sistema di trattametno acqua per consentire l'installazione della nuova AHU | IT. No. Art. n. | 3 | LS/AC | 0.00 | 0.00 | 0.00 | |||||||
| 4 | REMOVAL OF N°2 EXISTING AHU-02 HUMIDIFIER | ||||||||||||
| Rimozione di n°2 umidificatore esistenti a servizio AHU-02 | IT. No. Art. n. | 4 | LS/AC | 0.00 | 0.00 | ||||||||
| 5 | REMOVAL OF EXISTING CHILLER UNIT, MECHANICAL AND ELECTRICAL CONNECTION AND FITTINGS | ||||||||||||
| Rimozione del chiller esistente, connessioni meccaniche ed elettriche ed accessori | IT. No. Art. n. | 5 | LS/AC | 0.00 | 0.00 | 0.00 | |||||||
| Total Mechanical - Totale Meccanico | 0.00 | ||||||||||||
| Ic Electrical Demolitions - Ie Demolizioni Elettriche | |||||||||||||
| Not Applicable/Non applicabile | |||||||||||||
| TOTAL PART I / Totale Parte I | |||||||||||||
| PART II - ARCHITECTURAL, STRUCTURAL AND CIVIL WORK / Parte II - Lavori Architettonici, Strutturali e Civili |
| IIa Architectural - IIa Architettonico | |||||||
| 6 | REMOVAL AND REINSTALLATION OF SUSPENDED CEILING PANELS | ||||||
| Rimozione e reinstallazione pannelli contrrosoffitto | IT. No. Art. n. | 1 | LS/AC | 0.00 | 0.00 | 0 | 0.00 |
| Total Architectural - Totale Architettura |
| TOTAL PART II / Totale Parte II |
| PART III - MECHANICAL WORK / Parte III - Lavori Meccanici |
| 7 | NEW AHU-01 INCLUDING MECHANICAL AND ELECTRICAL CONNECTIONS, CONTROL AND SHUT OFF VALVES, PIPING AND DUCTWORK FURNISHING AND ADJUSTMENT AND FITTINGS | ||||||||
| Nuova unità di trattamento aria AHU-01 comprensiva di connessioni meccaniche ed elettriche, valvole di regolazione e intercettazione, modifica e fornitura tubazioni e canalizzazioni e accessori | IT. No. Art. n. | 1 | EA/NO | 0.00 | 0.00 | 0 | 0.00 | ||
| 8 | NEW DDC UNIT INCLUDING CONTROLLED POINTS AND FIELD ELEMENTS, WIRING, PROGRAMMING, CONTROL PANEL AND FITTINGS. REUSE AND REPROGRAM EXISTING DDC UNIT FOR CONTROL OF AHU-02. | ||||||||
| Nuova unità DDC comprensiva dei punti controllati e degli elementi in campo, cablaggio, programmazione, pannello di controllo e accessori. Riutilizzo e riprogrammazione del DDC esistente per il controllo della AHU-02 | IT. No. Art. n. | 2 | LS/AC | 0.00 | 0.00 | 0 | 0.00 | 0.00 | |
| 9 | NEW MINI AIR HANDLING UNIT INCLUDING MECHANICAL AND ELECTRICAL CONNECTIONS, FRESH AIR INTAKE GRILLE WITH G3 FILTER, BRACKETS, ROOM PANEL, 3 WAY CONTROL VALVES, SILENCER, DUCTWORK ADJUSTMENT AND FITTINGS. AHUM-01 | ||||||||
| Nuova mini unità di trattamento aria comprensiva di connessioni meccaniche ed elettriche, griglia di presa aria esterna con filtro G3, staffaggi, pannello ambiente, valvole di controllo a 3 vie, silenziatore, modifica canalizzazione e accessori. AHUM-01 | IT. No. Art. n. | 3a | EA/NO | 0.00 | 0.00 | 0.00 | 0 | 0.00 | 0.00 |
| 10 | NEW MINI AIR HANDLING UNIT INCLUDING MECHANICAL AND ELECTRICAL CONNECTIONS, FRESH AIR INTAKE GRILLE WITH G3 FILTER, BRACKETS, ROOM PANEL, 3 WAY CONTROL VALVES, SILENCER, DUCTWORK ADJUSTMENT AND FITTINGS. AHUM-03 | ||||||||
| Nuova mini unità di trattamento aria comprensiva di connessioni meccaniche ed elettriche, griglia di presa aria esterna con filtro G3, staffaggi, pannello ambiente, valvole di controllo a 3 vie, silenziatore, modifica canalizzazione e accessori. AHUM-03 | IT. No. Art. n. | 3b | EA/NO | 0.00 | 0.00 | 0.00 | 0 | 0.00 | 0.00 |
| 11 | NEW MINI AIR HANDLING UNIT INCLUDING MECHANICAL AND ELECTRICAL CONNECTIONS, FRESH AIR INTAKE GRILLE WITH G3 FILTER, BRACKETS, ROOM PANEL, 3 WAY CONTROL VALVES, SILENCER, DUCTWORK ADJUSTMENT AND FITTINGS. AHUM-04 | ||||||||
| Nuova mini unità di trattamento aria comprensiva di connessioni meccaniche ed elettriche, griglia di presa aria esterna con filtro G3, staffaggi, pannello ambiente, valvole di controllo a 3 vie, silenziatore, modifica canalizzazione e accessori. AHUM-04 | IT. No. Art. n. | 3c | EA/NO | 0.00 | 0.00 | 0.00 | 0 | 0.00 | 0.00 |
| 12 | NEW MINI AIR HANDLING UNIT INCLUDING MECHANICAL AND ELECTRICAL CONNECTIONS, BRACKETS, ROOM PANEL, 3 WAY CONTROL VALVES, SILENCER, DUCTWORK ADJUSTMENT AND FITTINGS. AHUM-02 | ||||||||
| Nuova mini unità di trattamento aria comprensiva di connessioni meccaniche ed elettriche, staffaggi, pannello ambiente, valvole di controllo a 3 vie, silenziatore, modifica canalizzazione e accessori. AHUM-02 | IT. No. Art. n. | 4a | EA/NO | 0.00 | 0.00 | 0.00 | 0 | 0.00 | 0.00 |
| 13 | NEW CHILLER UNIT WITH HYDRONIC MODULE INCLUDING MECHANICAL AND ELECTRICAL CONNECTIONS AND FITTINGS | ||||||||
| Nuovo refrigeratore e con modulo idronico comprensivo di connessioni meccaniche ed elettriche e accessori | IT. No. Art. n. | 5 | LS/AC | 0.00 | 0.00 | 0.00 | 0 | 0.00 | 0.00 |
| 14 | NEW HUMIDIFIER FOR AHU-02 | ||||||||
| Nuovo umidificatore per AHU-2 | IT. No. Art. n. | 6 | LS/AC | 0.00 | 0.00 | 0 | 0.00 | 0.00 | |
| 15 | NEW CHILLER UNIT | ||||||||
| Nuova Unita' Chiller | IT. No. Art. n. | 7 | LS/AC | ||||||
| 16 | SYSTEM BALANCING AND TECHNICAL TEST REPORT | ||||||||
| bilanciamento del sistema e redazione report | IT. No. Art. n. | 8 | LS/AC | 0.00 | 0.00 | ||||
| Total Mechanical - Totale Meccanico |
| TOTAL PART III - Totale Parte III |
| PART IV- ELECTRICAL WORK / Parte VI - Lavori Elettrici |
| Not Applicable/Non applicabile |
| SUMMARY / Riepilogo | ||||
| PART I - DEMOLITIONS, EXCAVATIONS AND REMOVALS | ||||
| PART II - ARCHITECTURAL, STRUCTURAL AND CIVIL WORK | ||||
| PART III - MECHANICAL WORK | ||||
| PART IV - ELECTRICAL WORK | € - 0 | € - 0 | € - 0 | € - 0 |
| TOTAL PRICE / Costo Totale |
OR US DOLLARS (RATE 1$ = ….................. €)
&"Arial,Grassetto"&12FOR OFFICIAL USE ONLY
&"Arial,Grassetto"&12FOR OFFICIAL USE ONLY Sheet &P of &N
| CONSTRUCTION COST ESTIMATE BREAKDOWN | |
| CONTRACTOR | ADDRESS |
| CONTRACT FOR (Work to be performed) | PROPOSED TOTAL CONTRACT PRICE | |||||||||
| DESIGN FOR SUSTAIN HVAC SYSTEM MULTI - BLDG 1013 | ||||||||||
| PURCHASE REQUEST NUMBER | PROJECT NUMBER | WORK LOCATION | ||||||||
| ASHE 18-1087 | AREA F, AVIANO AIR BASE, ITALY | |||||||||
| MATERIAL COSTS | LABOR COSTS | |||||||||
| LINE NO. | ITEM | UNIT OF MEASURE | QUANTITY | UNIT | TOTAL | MANHOURS MANDAYS | AVERAGE RATE | TOTAL | OTHER DIRECT COSTS | LINE TOTAL |
| (1) | (2) | (3) | (4) | (5) | (6) | (7) | (8) | (9) | (10) | |
| BLDG 1013 | ||||||||||
| PART I - DEMOLITIONS, EXCAVATIONS AND REMOVALS / Parte I - Demolizioni, Scavi e Rimozioni |
| Ia Architectural Demolition - Ia Demolizioni Architettoniche | ||||||||
| Not Applicable/Non applicabile | ||||||||
| Ib Mechanical Demolitions - Demolizioni Meccaniche | ||||||||
| 1 | REMOVAL OF EXISTING FANCOIL UNIT, MECHANICAL & ELECTRICAL CONNECTIONS AND FITTINGS | |||||||
| Rimozione del ventilconvettore esistente, connessioni meccaniche ed elettriche ed accessori | IT. No. Art. n. | 1 | LS/AC | 0.00 | 0 | 0.00 | ||
| 2 | REMOVAL OF EXISTING BURIED HOT WATER PIPES INSIDE THE BUILDING | |||||||
| Rimozione delle tubazioni esistenti acqua calda all'interno del fabbricato | IT. No. Art. n. | 2 | LS/AC | 0.00 | 0 | 0.00 | 0.00 | |
| 3 | REMOVAL OF EXISTING BURIED HOT WATER PIPES FROM BOILER ROOM FEEDING FANCOIL UNITS | |||||||
| Rimozione delle tubazioni esistenti interrate di acqua calda dalla centrale termica alimentanti i ventilconvettori | IT. No. Art. n. | 3 | LS/AC | 0.00 | 0 | 0.00 | 0.00 | |
| 4 | REMOVAL OF DX UNIT, MECHANICAL & ELECTRICAL CONNECTIONS AND FITTINGS | |||||||
| Rimozione dell'unità ad espansione diretta, connessioni meccaniche ed elettriche ed accessori | IT. No. Art. n. | 4 | EA/NO | 0.00 | 0 | 0.00 | ||
| Total Mechanical - Totale Meccanico | 0.00 | |||||||
| Ic Electrical Demolitions - Ie Demolizioni Elettriche | ||||||||
| 5 | REMOVE F/A SYSTEM | |||||||
| Rimozione Impianto Allarme Incendio | IT. No. Art. n. | 5 | LS/AC | 0.00 | 0 | 0.00 | 0.00 | |
| Total Electrical - Totale Elettrico |
| TOTAL PART I / Totale Parte I |
| PART II - ARCHITECTURAL, STRUCTURAL AND CIVIL WORK / Parte II - Lavori Architettonici, Strutturali e Civili |
| IIa Architectural - IIa Architettonico | |||||||||
| 6 | REMOVAL AND REINSTALLATION OF SUSPENDED CEILING PANELS | ||||||||
| Rimozione e reinstallazione pannelli contrrosoffitto | IT. No. Art. n. | 1 | LS/AC | 0.00 | 0.00 | 0.00 | 0 | 0.00 | 0.00 |
| 7 | PREPAINTED GALVANIZED STEEL PIPING COVER | ||||||||
| Carter in accio zincato preverniciatpo per protezione tubi | IT. No. Art. n. | 2 | EA/NO | 0.00 | 0.00 | 0 | 0.00 | 0.00 | |
| 8 | NEW CONCRETE PAD | ||||||||
| Nuovo basamento in calcestruzzo | IT. No. Art. n. | 3 | LS/AC | 0.00 | 0.00 | 0 | 0.00 | 0.00 | |
| 9 | UTILITY TRENCHES | ||||||||
| Trincee sottoservizi | IT. No. Art. n. | 4 | LS/AC | 0.00 | 0.00 | 0 | 0.00 | 0.00 | |
| Total Architectural - Totale Architettura |
| TOTAL PART II / Totale Parte II |
| PART III - MECHANICAL WORK / Parte III - Lavori Meccanici |
| 10 | NEW BURIED PIPES FROM BOILER ROOM FEEDING NEW FANCOIL UNITS INCLUDING BACKFILLING | |||||||
| Nuove tubazioni interrate di acqua calda dalla centrale termica alimentanti i nuovi ventilconvettori compreso il rinterro | IT. No. Art. n. | 1 | LS/AC | 0.00 | 0.00 | 0 | 0.00 | 0.00 |
| 11 | FURNISHING AND INSTALLATION OF NEW CHILLER UNIT CH-01 INCLUDING EXPANSION TANK, INERTIAL TANK AND FITTINGS | |||||||
| Fornitura e posa in opera di nuovo refrigeratore CH-01 comprensivo di vaso di espansione, serbatoio inerziale e accessori | IT. No. Art. n. | 2 | LS/AC | 0.00 | 0.00 | 0 | 0.00 | |
| 12 | NEW VERTICAL CABINET ECM FANCOIL UNIT INCLUDING MECHANICAL AND ELECTRICAL CONNECTIONS,3-WAY ON/OFF CONTROL VALVE WITH ACTUATOR, SHUT-OFF VALVES, CONTROLLER, ROOM PANEL AND FITTINGS. |
FCV-01
| Nuovo ventilconvettore a mobiletto ecm comprensivo di connessioni meccaniche ed elettriche, valvola di regolazione ON/OFF a 3 vie con attuatore, valvole di intercettazione, controllore, pannello di controllo ed accessori. FCV-01 | IT. No. Art. n. | 3a | EA/NO | 0.00 | 0.00 | 0 | 0.00 | |
| 13 | NEW CHILLED WATER PIPING FEEDING NEW FANCOIL UNITS | |||||||
| Nuova tubazione acqua refrigerata per alimentazione nuovi ventilconvettori | IT. No. Art. n. | 4 | LS/AC | 0.00 | 0.00 | 0 | 0.00 | 0.00 |
| 14 | NEW CONDENSATE DRAIN PIPING | |||||||
| Nuove linea di scarico condensa | IT. No. Art. n. | 5 | LS/AC | 0.00 | 0.00 | 0 | 0.00 | 0.00 |
| 15 | NEW MAKE UP WATER LINE | |||||||
| Nuova linea di reintegro | IT. No. Art. n. | 6 | LS/AC | 0.00 | 0.00 | 0 | 0.00 | |
| Total Mechanical - Totale Meccanico |
| TOTAL PART III - Totale Parte III | |||||||||
| PART IV- ELECTRICAL WORK / Parte VI - Lavori Elettrici | |||||||||
| Power System - Impianto Forza Motrice | |||||||||
| 16 | RES. CURR. MAGNETOT. CIRCUIT BREAKER AND FEEDING LINE FG16OM16 3G4 MMQ CABLE FOR NEW CHILLER | ||||||||
| Interruttore magnetot.diff.e linea di alimentazione con cavo FG16OM16 3G4 mmq del nuovo refrigeratore | IT. No. Art. n. | 1 | LS/AC | 0 | 0.00 | 0 | 0.00 | 0.00 | |
| Total Power System - Totale Impianto Forza Motrice | |||||||||
| Fire Alarm System systems - Impianto Allarme Incedio | |||||||||
| 17 | SMOKE DETECTORS | ||||||||
| Rilevatori di fumo | IT. No. Art. n. | 2 | EA/NO | 0 | 0.00 | 0.00 | 0 | 0.00 | 0.00 |
| 18 | RED PILOT LIGHT | ||||||||
| Lampada spia rossa | IT. No. Art. n. | 3 | EA/NO | 0 | 0.00 | 0 | 0.00 | 0.00 | |
| 19 | PULL STATIONS | ||||||||
| Stazioni manuali | IT. No. Art. n. | 4 | EA/NO | 0 | 0.00 | 0 | 0.00 | 0.00 | |
| 20 | Audio/video devices | ||||||||
| Dispositivi audio/video | IT. No. Art. n. | 5 | EA/NO | 0 | 0.00 | 0 | 0.00 | 0.00 | |
| 21 | ALARM BELL | ||||||||
| Campana di allarme | IT. No. Art. n. | 6 | EA/NO | 0 | 0.00 | 0 | 0.00 | 0.00 | |
| 22 | CONVENTIONAL FIRE ALARM CONTROL PANEL | ||||||||
| Centrale Rivelazione Incendi Convenzionale | IT. No. Art. n. | 7 | EA/NO | 0 | 0.00 | 0 | 0.00 | 0.00 | |
| 23 | FTE40HM1 2X1,5 MMQ CABLE | ||||||||
| Cavo FTE40HM1 2X1,5 mmq | IT. No. Art. n. | 8 | LM/ML | 0 | 0.00 | 0 | 0.00 | 0.00 | |
| 24 | METAL CABLE TRAY 100x100 MM | ||||||||
| Canalina Metallica 100x100 mm | IT. No. Art. n. | 9 | LM/ML | 0 | 0.00 | 0 | 0.00 | 0.00 | |
| 25 | PVC RIGID CONDUIT DIAM. 40 MM | ||||||||
| Tubazione Rigida in PVC Diam. 40 mm | IT. No. Art. n. | 10a | LM/ML | 0 | 0.00 | 0 | 0.00 | 0.00 | |
| 26 | PVC RIGID CONDUIT DIAM. 25 MM | ||||||||
| Tubazione Rigida in PVC Diam. 25 mm | IT. No. Art. n. | 10b | LM/ML | 0 | 0.00 | 0 | 0.00 | 0.00 | |
| 27 | PVC FLEXIBLE CONDUIT DIAM. 25 MM | ||||||||
| Tubazione Flesibile in PVC Diam. 25 mm | IT. No. Art. n. | 11 | LM/ML | 0 | 0.00 | 0 | 0.00 | 0.00 | |
| 28 | JUNCTION BOX 80X80X40 MM | ||||||||
| Scatola di Derivazione 80x80x40 mm | IT. No. Art. n. | 12 | LM/ML | 0 | 0.00 | 0 | 0.00 | 0.00 | |
| 29 | F/A programmation | ||||||||
| Programmazione quadro F/A | IT. No. Art. n. | 13 | LS/AC | 0 | 0.00 | 0 | 0.00 | 0.00 | |
| Total Fire Alarm System - Totale Impianto Allarme Incendio | |||||||||
| TOTAL PART IV - Totale Parte IV |
| SUMMARY / Riepilogo |
| PART I - DEMOLITIONS, EXCAVATIONS AND REMOVALS |
| PART II - ARCHITECTURAL, STRUCTURAL AND CIVIL WORK |
| PART III - MECHANICAL WORK |
| PART IV - ELECTRICAL WORK |
| TOTAL PRICE / Costo Totale |
OR US DOLLARS (RATE 1$ = ….................. €)
&"Arial,Grassetto"&12FOR OFFICIAL USE ONLY
&"Arial,Grassetto"&12FOR OFFICIAL USE ONLY Sheet &P of &N
| CONSTRUCTION COST ESTIMATE BREAKDOWN | |
| CONTRACTOR | ADDRESS |
| CONTRACT FOR (Work to be performed) | PROPOSED TOTAL CONTRACT PRICE | |||||||||
| DESIGN FOR SUSTAIN HVAC SYSTEM MULTI - BLDG 1405 | ||||||||||
| PURCHASE REQUEST NUMBER | PROJECT NUMBER | WORK LOCATION | ||||||||
| ASHE 18-1087 | AREA F, AVIANO AIR BASE, ITALY | |||||||||
| MATERIAL COSTS | LABOR COSTS | |||||||||
| LINE NO. | ITEM | UNIT OF MEASURE | QUANTITY | UNIT | TOTAL | MANHOURS MANDAYS | AVERAGE RATE | TOTAL | OTHER DIRECT COSTS | LINE TOTAL |
| (1) | (2) | (3) | (4) | (5) | (6) | (7) | (8) | (9) | (10) | |
| BLDG 1405 | ||||||||||
| PART I - DEMOLITIONS, EXCAVATIONS AND REMOVALS / Parte I - Demolizioni, Scavi e Rimozioni |
| Ia Architectural Demolition - Ia Demolizioni Architettoniche | ||||||||
| Not Applicable/Non applicabile | ||||||||
| Ib Mechanical Demolitions - Demolizioni Meccaniche | ||||||||
| 1 | REMOVAL OF EXISTING CHILLER UNIT, MECHANICAL AND ELECTRICAL CONNECTION AND FITTINGS | |||||||
| Rimozione del chiller esistente, connessioni meccaniche ed elettriche ed accessori | IT. No. Art. n. | 1 | LS/AC | 0.00 | 0 | 0.00 | 0.00 | |
| Total Mechanical - Totale Meccanico | 0.00 | |||||||
| Ic Electrical Demolitions - Ie Demolizioni Elettriche | ||||||||
| Not Applicable/Non applicabile |
| TOTAL PART I / Totale Parte I |
| PART II - ARCHITECTURAL, STRUCTURAL AND CIVIL WORK / Parte II - Lavori Architettonici, Strutturali e Civili |
| IIa Architectural - IIa Architettonico | |||||||
| 2 | NEW CHILLER PAD | ||||||
| Nuovo basamento chilLer | IT. No. Art. n. | 1 | LS/AC | 0.00 | 0.00 | 0 | 0.00 |
| Total Architectural - Totale Architettura |
| TOTAL PART II / Totale Parte II |
| PART III - MECHANICAL WORK / Parte III - Lavori Meccanici |
| 3 | NEW CHILLER UNIT INCLUDING MECHANICAL AND ELECTRICAL CONNECTIONS, PIPING WITH INSULATION, ANTI VIBRATING JOINTS, CHECK AND SHUTOFF VALVE AND FITTINGS | |||||||
| Nuovo chiller comprensivo di connessioni meccaniche ed elettriche, tubazione con isolamento, giunti antivibranti, valvole di ritegno e intercettazione e accessori | IT. No. Art. n. | 1 | LS/AC | 0.00 | 0.00 | 0 | 0.00 | 0.00 |
| 4 | NEW CHILLED WATER PIPING | |||||||
| Nuove tubazioni acqua refrigerata | IT. No. Art. n. | 2 | LS/AC | 0.00 | 0.00 | 0 | 0.00 | |
| 5 | SYSTEM BALANCING AND TECHNICAL TEST REPORT | |||||||
| bilanciamento del sistema e redazione report | IT. No. Art. n. | 3 | LS/AC | 0.00 | 0.00 | 0.00 | ||
| Total Mechanical - Totale Meccanico |
| TOTAL PART III - Totale Parte III |
| PART IV- ELECTRICAL WORK / Parte VI - Lavori Elettrici |
| Not Applicable/Non applicabile |
| SUMMARY / Riepilogo | ||
| PART I - DEMOLITIONS, EXCAVATIONS AND REMOVALS | ||
| PART II - ARCHITECTURAL, STRUCTURAL AND CIVIL WORK | ||
| PART III - MECHANICAL WORK | ||
| PART IV - ELECTRICAL WORK | € - 0 | € - 0 |
| TOTAL PRICE / Costo Totale |
OR US DOLLARS (RATE 1$ = ….................. €)
&"Arial,Grassetto"&12FOR OFFICIAL USE ONLY
&"Arial,Grassetto"&12FOR OFFICIAL USE ONLY Sheet &P of &N
| CONSTRUCTION COST ESTIMATE BREAKDOWN | |
| CONTRACTOR | ADDRESS |
| CONTRACT FOR (Work to be performed) | PROPOSED TOTAL CONTRACT PRICE | ||||||||||||
| DESIGN FOR SUSTAIN HVAC SYSTEM MULTI - BLDG 1407 | |||||||||||||
| PURCHASE REQUEST NUMBER | PROJECT NUMBER | WORK LOCATION | |||||||||||
| ASHE 18-1087 | AREA F, AVIANO AIR BASE, ITALY | ||||||||||||
| MATERIAL COSTS | LABOR COSTS | ||||||||||||
| LINE NO. | ITEM | UNIT OF MEASURE | QUANTITY | UNIT | TOTAL | MANHOURS MANDAYS | AVERAGE RATE | TOTAL | OTHER DIRECT COSTS | LINE TOTAL | |||
| (1) | (2) | (3) | (4) | (5) | (6) | (7) | (8) | (9) | (10) | ||||
| BLDG 1407 | |||||||||||||
| PART I - DEMOLITIONS, EXCAVATIONS AND REMOVALS / Parte I - Demolizioni, Scavi e Rimozioni | |||||||||||||
| Ia Architectural Demolition - Ia Demolizioni Architettoniche | |||||||||||||
| 1 | REMOVAL OF WATERPROOFING MEMBRANE | ||||||||||||
| Rimozione dui guaina impermeabilizzante | IT. No. Art. n. | 1 | SM/MQ | 0.00 | 0 | 0 | 0.00 | 0.00 | |||||
| Total Architectural - Totale Architettura | |||||||||||||
| Ib Mechanical Demolitions - Demolizioni Meccaniche | |||||||||||||
| 2 | REMOVAL OF EXISTING AIR HANDLING UNIT, INCLUDING MECHANICAL AND ELECTRICAL CONNECTIONS, DUCTWORK, ACTUTATORS, SENSORS, DDC UNIT AND FITTINGS | ||||||||||||
| Rimozione dell'esistente unità di trattamento aria esistente, comprese le connessioni meccaniche ed elettriche, canalizzazioni, attuatori, sensori, unità DDC e accessori | IT. No. Art. n. | 2 | LS/AC | 0.00 | 0 | 0.00 | 0.00 | ||||||
| 3 | REMOVAL OF EXISTING HOT/CHILLED WATER PIPING, CONTROL AND SHUTOFF VALVES AND FITTINGS | ||||||||||||
| Rimozione delle tubazioni esistenti di acqua calda/refrigerata, valvole di controllo e regolazione e accessori | IT. No. Art. n. | 3 | LS/AC | 0.00 | 0 | 0.00 | 0.00 | ||||||
| 4 | REMOVAL AND RELOCATION OF EXISTING DX CONDENSING UNIT FOOR MOUNTED | ||||||||||||
| Rimozione e riposizionamento di unità condensante DX installata a pavimento | IT. No. Art. n. | 4 | LS/AC | 0.00 | 0.00 | 0 | 0.00 | ||||||
| 5 | REMOVAL AND RELOCATION OF EXISTING DX CONDENSING UNIT WALL MOUNTED | ||||||||||||
| Rimozione e riposizionamento di unità condensante DX installata a parete | IT. No. Art. n. | 5 | LS/AC | 0.00 | 0.00 | 0 | 0.00 | ||||||
| Total Mechanical - Totale Meccanico | 0.00 | ||||||||||||
| Ic Electrical Demolitions - Ie Demolizioni Elettriche | |||||||||||||
| Not Applicable/Non applicabile |
| TOTAL PART I / Totale Parte I |
| PART II - ARCHITECTURAL, STRUCTURAL AND CIVIL WORK / Parte II - Lavori Architettonici, Strutturali e Civili |
| IIa Architectural - IIa Architettonico | |||||||||
| 6 | NEW WATERPROOFING MEMBRANE | ||||||||
| Nuova Guaina Impermeabilizzante | IT. No. Art. n. | 1 | SM/MQ | 0.00 | 0.00 | 0.00 | 0 | 0.00 | 0.00 |
| 7 | ROOF REPAIR | ||||||||
| Ripristino copertura | IT. No. Art. n. | 2 | LS/AC | 0.00 | 0.00 | 0 | 0.00 | ||
| 8 | PROTECTIVE CASES/FLASHINGS | ||||||||
| Scossasline e involucri di protezione | IT. No. Art. n. | 3 | LS/AC | 0.00 | 0.00 | 0 | 0.00 | ||
| Total Architectural - Totale Architettura |
| TOTAL PART II / Totale Parte II |
| PART III - MECHANICAL WORK / Parte III - Lavori Meccanici |
| 9 | COMPLETE REPLACEMENT OD DAMAGED PIPEWORK AND DEVICES IN MECH ROOM | ||||||
| Sostituzione delle tubazioni e dispositivi danneggiati all'interno del locale meccanico | IT. No. Art. n. | 1 | LS/AC | 0.00 | 0.00 | 0 | 0.00 |
| 10 | NEW CHEMICAL POT FEEDER AND DIRT/SLUDGE SEPARATOR CPF-1 | ||||||
| Nuovo filtro a masse chiarificatore e defangatore CPF-1 | IT. No. Art. n. | 2 | EA/NO | 0.00 | 0.00 | 0 | 0.00 |
| 11 | NEW ENERGY RECOVERY UNIT AHU-01 INCLUDING MECHANICAL AND ELECTRICAL CONNECTIONS, NEW DUCTWORK, 3-WAY CONTROL VALVE AND FITTINGS | ||||||
| Nuovo recuperatore AHU-01 comprensivo di connessioni meccaniche ed elettriche, nuova canalizzazione, valvola di controllo a 3 vie e accessori | IT. No. Art. n. | 3 | EA/NO | 0.00 | 0.00 | 0 | 0.00 |
| 12 | NEW AHU-02 INCLUDING MECHANICAL AND ELECTRICAL CONNECTIONS, NEW DUCTWORK, SENSORS AND FIELD ELEMENTS, 3 WAY CONTROL VALVE AND FITTINGS | ||||||
| Nuova unità di trattamento aria AHU-02 comprensiva di connessioni meccaniche ed elettriche, nuove canalizzazioni, sensori ed elementi in campo, valvola di controllo a 3 vie e accessori | IT. No. Art. n. | 4 | EA/NO | 0.00 | 0.00 | 0 | 0.00 |
| 13 | NEW DDC-1 | ||||||
| Nuovo DDC-1 | IT. No. Art. n. | 5 | LS/AC | 0.00 | 0.00 | 0 | 0.00 |
| 14 | NEW HOT/CHILLED WATER PIPING INCLUDING BRACKETS, SHUTOFF VALVES, INSULATION, ALUMINUM COVER AND FITTINGS | ||||||
| Nuova tubazione di acqua calda/refrigerata compresi gli staffaggi, valvole di intercettazione, isolamento e lamierino e accessori | IT. No. Art. n. | 6 | LS/AC | 0.00 | 0.00 | 0 | 0.00 |
| 15 | SYSTEM BALANCING AND TECHNICAL TEST REPORT | ||||||
| bilanciamento del sistema e redazione report | IT. No. Art. n. | 7 | LS/AC | 0.00 | 0.00 | 0 | 0.00 |
| Total Mechanical - Totale Meccanico |
| TOTAL PART III - Totale Parte III | |||||||||
| PART IV- ELECTRICAL WORK / Parte VI - Lavori Elettrici | |||||||||
| Power System - Impianto Forza Motrice | |||||||||
| 16 | RES. CURR. MAGNETOT. CIRCUIT BREAKER FOR NEW AHU FAN | ||||||||
| Interruttore magnetot.diff. per ventilatore nuova UTA | IT. No. Art. n. | 1 | EA/NO | 0 | 0.00 | 0.00 | 0 | 0.00 | 0.00 |
| Total Power System - Totale Impianto Forza Motrice |
TOTAL PART IV - Totale Parte IV
| SUMMARY / Riepilogo | |
| PART I - DEMOLITIONS, EXCAVATIONS AND REMOVALS | |
| PART II - ARCHITECTURAL, STRUCTURAL AND CIVIL WORK | |
| PART III - MECHANICAL WORK | |
| PART IV - ELECTRICAL WORK | € - 0 |
| TOTAL PRICE / Costo Totale |
OR US DOLLARS (RATE 1$ = ….................. €)
&"Arial,Grassetto"&12FOR OFFICIAL USE ONLY
&"Arial,Grassetto"&12FOR OFFICIAL USE ONLY Sheet &P of &N
| CONSTRUCTION COST ESTIMATE BREAKDOWN | |
| CONTRACTOR | ADDRESS |
| CONTRACT FOR (Work to be performed) | PROPOSED TOTAL CONTRACT PRICE | |||||||||
| DESIGN FOR SUSTAIN HVAC SYSTEM MULTI - BLDG 1434 | ||||||||||
| PURCHASE REQUEST NUMBER | PROJECT NUMBER | WORK LOCATION | ||||||||
| ASHE 18-1087 | AREA F, AVIANO AIR BASE, ITALY | |||||||||
| MATERIAL COSTS | LABOR COSTS | |||||||||
| LINE NO. | ITEM | UNIT OF MEASURE | QUANTITY | UNIT | TOTAL | MANHOURS MANDAYS | AVERAGE RATE | TOTAL | OTHER DIRECT COSTS | LINE TOTAL |
| (1) | (2) | (3) | (4) | (5) | (6) | (7) | (8) | (9) | (10) | |
| BLDG 1434 | ||||||||||
| PART I - DEMOLITIONS, EXCAVATIONS AND REMOVALS / Parte I - Demolizioni, Scavi e Rimozioni |
| Ia Architectural Demolition - Ia Demolizioni Architettoniche | ||||||||
| Not Applicable/Non applicabile | ||||||||
| Ib Mechanical Demolitions - Demolizioni Meccaniche | ||||||||
| 1 | REMOVAL OF EXISTING CHILLER UNIT, MECHANICAL AND ELECTRICAL CONNECTION AND FITTINGS | |||||||
| Rimozione del chiller esistente, connessioni meccaniche ed elettriche ed accessori | IT. No. Art. n. | 1 | LS/AC | 0.00 | 0 | 0.00 | 0.00 | |
| 2 | REMOVAL OF EXISTING CIRCULATING PUMP AND FITTINGS | |||||||
| Rimozione della pompa di circolazione esistente ed accessori | IT. No. Art. n. | 2 | LS/AC | 0.00 | 0 | 0.00 | 0.00 | |
| 3 | TEMPORARY REMOVAL OF EXISTING INERTIAL TANK IT-01 | |||||||
| Rimozione temporanea del serbatoio inerziale esistente IT-01 | IT. No. Art. n. | 3 | LS/AC | 0.00 | 0 | 0.00 | 0.00 | |
| 4 | REMOVAL OF EXISTING 3-WAY CONTROL VALVES OF AHU-01 AND AHU-02 AT THE ATTIC LEVEL | |||||||
| Rimozione delle valvole di regolazione a tre vie delle AHU-01 ed AHU-02 installate nel sottotetto | IT. No. Art. n. | 4 | LS/AC | 0.00 | 0 | 0.00 | 0.00 | |
| Total Mechanical - Totale Meccanico | 0.00 | |||||||
| Ic Electrical Demolitions - Ie Demolizioni Elettriche | ||||||||
| Not Applicable/Non applicabile |
| TOTAL PART I / Totale Parte I |
| PART II - ARCHITECTURAL, STRUCTURAL AND CIVIL WORK / Parte II - Lavori Architettonici, Strutturali e Civili |
| IIa Architectural - IIa Architettonico | |||||||
| 5 | REMOVAL AND REINSTALLATION OF SUSPENDED CEILING PANELS | ||||||
| Rimozione e reinstallazione pannelli contrrosoffitto | IT. No. Art. n. | 1 | LS/AC | 0.00 | 0.00 | 0 | 0.00 |
| Total Architectural - Totale Architettura |
| TOTAL PART II / Totale Parte II |
| PART III - MECHANICAL WORK / Parte III - Lavori Meccanici |
| 6 | NEW CHILLER UNIT INCLUDING MECHANICAL AND ELECTRICAL CONNECTIONS, PIPING WITH INSULATION, ANTI VIBRATING JOINTS, CHECK AND SHUTOFF VALVE AND FITTINGS | |||||||
| Nuovo chiller comprensivo di connessioni meccaniche ed elettriche, tubazione con isolamento, giunti antivibranti, valvole di ritegno e intercettazione e accessori | IT. No. Art. n. | 1 | EA/NO | 0.00 | 0.00 | 0 | 0.00 | 0.00 |
| 7 | RE-INSTALLATION IN NEW POSITION OF EXISTING INERTIAL TANK IT-01 | |||||||
| Re-installazione in nuova posizione del serbatoio inerziale esistente IT-01 | IT. No. Art. n. | 2 | EA/NO | 0.00 | 0.00 | 0 | 0.00 | 0.00 |
| 8 | NEW CHILLED WATER PIPING | |||||||
| Nuove tubazioni acqua refrigerata | IT. No. Art. n. | 3 | LS/AC | 0.00 | 0.00 | 0 | 0.00 | 0.00 |
| 9 | SYSTEM BALANCING AND TECHNICAL TEST REPORT | |||||||
| bilanciamento del sistema e redazione report | IT. No. Art. n. | 4 | LS/AC | 0.00 | 0.00 | 0 | 0.00 | 0.00 |
| 10 | NEW CHECK VALVES AND BALL VALVES IN MECH ROOM WITH PIPING ADJUSTMENT | |||||||
| Nuove valvole di ritegno e valvole a sfera nelal centrale meccanica con adeguamento tubazioni | IT. No. Art. n. | 5 | LS/AC | 0.00 | 0.00 | 0 | 0.00 | 0.00 |
| 11 | PROVIDE COMPLETE REVISION OF AHUs | |||||||
| Provvedere alla completa revisione delle UTA | IT. No. Art. n. | 6 | LS/AC | 0.00 | 0.00 | 0 | 0.00 | 0.00 |
| Total Mechanical - Totale Meccanico |
| TOTAL PART III - Totale Parte III |
| PART IV- ELECTRICAL WORK / Parte VI - Lavori Elettrici |
| Not Applicable/Non applicabile |
| SUMMARY / Riepilogo | ||||
| PART I - DEMOLITIONS, EXCAVATIONS AND REMOVALS | ||||
| PART II - ARCHITECTURAL, STRUCTURAL AND CIVIL WORK | ||||
| PART III - MECHANICAL WORK | ||||
| PART IV - ELECTRICAL WORK | € - 0 | € - 0 | € - 0 | € - 0 |
| TOTAL PRICE / Costo Totale |
OR US DOLLARS (RATE 1$ = ….................. €)
&"Arial,Grassetto"&12FOR OFFICIAL USE ONLY
&"Arial,Grassetto"&12FOR OFFICIAL USE ONLY Sheet &P of &N
| CONSTRUCTION COST ESTIMATE BREAKDOWN | |
| CONTRACTOR | ADDRESS |
| CONTRACT FOR (Work to be performed) | PROPOSED TOTAL CONTRACT PRICE | |||||||||
| DESIGN FOR SUSTAIN HVAC SYSTEM MULTI - BLDG 1483 | ||||||||||
| PURCHASE REQUEST NUMBER | PROJECT NUMBER | WORK LOCATION | ||||||||
| ASHE 18-1087 | AREA F, AVIANO AIR BASE, ITALY | |||||||||
| MATERIAL COSTS | LABOR COSTS | |||||||||
| LINE NO. | ITEM | UNIT OF MEASURE | QUANTITY | UNIT | TOTAL | MANHOURS MANDAYS | AVERAGE RATE | TOTAL | OTHER DIRECT COSTS | LINE TOTAL |
| (1) | (2) | (3) | (4) | (5) | (6) | (7) | (8) | (9) | (10) | |
| BLDG 1483 | ||||||||||
| PART I - DEMOLITIONS, EXCAVATIONS AND REMOVALS / Parte I - Demolizioni, Scavi e Rimozioni |
| Ia Architectural Demolition - Ia Demolizioni Architettoniche | ||||||||
| Not Applicable/Non applicabile | ||||||||
| Ib Mechanical Demolitions - Demolizioni Meccaniche | ||||||||
| 1 | REMOVAL OF EXISTING CHILLER UNIT, MECHANICAL AND ELECTRICAL CONNECTION AND FITTINGS | |||||||
| Rimozione del chiller esistente, connessioni meccaniche ed elettriche ed accessori | IT. No. Art. n. | 1 | LS/AC | 0.00 | 0 | 0.00 | 0.00 | |
| Total Mechanical - Totale Meccanico | 0.00 | |||||||
| Ic Electrical Demolitions - Ie Demolizioni Elettriche | ||||||||
| Not Applicable/Non applicabile |
| TOTAL PART I / Totale Parte I |
| PART II - ARCHITECTURAL, STRUCTURAL AND CIVIL WORK / Parte II - Lavori Architettonici, Strutturali e Civili |
| IIa Architectural - IIa Architettonico |
| Not Applicable/Non applicabile |
PART III - MECHANICAL WORK / Parte III - Lavori Meccanici
| 2 | NEW CHILLER UNIT INCLUDING MECHANICAL AND ELECTRICAL CONNECTIONS, PIPING WITH INSULATION, ANTI VIBRATING JOINTS, CHECK AND SHUTOFF VALVE AND FITTINGS | |||||||
| Nuovo chiller comprensivo di connessioni meccaniche ed elettriche, tubazione con isolamento, giunti antivibranti, valvole di ritegno e intercettazione e accessori | IT. No. Art. n. | 1 | EA/NO | 0.00 | 0.00 | 0 | 0.00 | 0.00 |
| 3 | NEW INERTIAL TANK | |||||||
| Nuovo serbatoio inerziale | IT. No. Art. n. | 2 | EA/NO | 0.00 | 0.00 | 0 | 0.00 | |
| 4 | NEW CHILLED WATER PIPING | |||||||
| Nuove tubazioni acqua refrigerata | IT. No. Art. n. | 3 | LS/AC | 0.00 | 0.00 | 0 | 0.00 | |
| 5 | SYSTEM BALANCING AND TECHNICAL TEST REPORT | |||||||
| bilanciamento del sistema e redazione report | IT. No. Art. n. | 4 | LS/AC | 0.00 | 0.00 | 0 | 0.00 | 0.00 |
| Total Mechanical - Totale Meccanico |
| TOTAL PART III - Totale Parte III |
| PART IV- ELECTRICAL WORK / Parte VI - Lavori Elettrici |
| Not Applicable/Non applicabile |
| SUMMARY / Riepilogo | ||||
| PART I - DEMOLITIONS, EXCAVATIONS AND REMOVALS | ||||
| PART II - ARCHITECTURAL, STRUCTURAL AND CIVIL WORK | € - 0 | € - 0 | € - 0 | € - 0 |
| PART III - MECHANICAL WORK | ||||
| PART IV - ELECTRICAL WORK | € - 0 | € - 0 | € - 0 | € - 0 |
| TOTAL PRICE / Costo Totale |
OR US DOLLARS (RATE 1$ = ….................. €)
&"Arial,Grassetto"&12FOR OFFICIAL USE ONLY
&"Arial,Grassetto"&12FOR OFFICIAL USE ONLY Sheet &P of &N
10462
| CONSTRUCTION COST ESTIMATE BREAKDOWN | |
| CONTRACTOR | ADDRESS |
| CONTRACT FOR (Work to be performed) | PROPOSED TOTAL CONTRACT PRICE | |||||||||
| DESIGN FOR SUSTAIN HVAC SYSTEM MULTI - BLDG 10462 | ||||||||||
| PURCHASE REQUEST NUMBER | PROJECT NUMBER | WORK LOCATION | ||||||||
| ASHE 18-1087 | AREA F, AVIANO AIR BASE, ITALY | |||||||||
| MATERIAL COSTS | LABOR COSTS | |||||||||
| LINE NO. | ITEM | UNIT OF MEASURE | QUANTITY | UNIT | TOTAL | MANHOURS MANDAYS | AVERAGE RATE | TOTAL | OTHER DIRECT COSTS | LINE TOTAL |
| (1) | (2) | (3) | (4) | (5) | (6) | (7) | (8) | (9) | (10) | |
| BLDG 10462 | ||||||||||
| PART I - DEMOLITIONS, EXCAVATIONS AND REMOVALS / Parte I - Demolizioni, Scavi e Rimozioni |
| Ia Architectural Demolition - Ia Demolizioni Architettoniche | ||||||||
| Not Applicable/Non applicabile | ||||||||
| Ib Mechanical Demolitions - Demolizioni Meccaniche | 0.00 | |||||||
| 1 | REMOVAL OF EXISTING DUCTED DX UNIT AND EXTERNAL UNIT INCLUDING MECHANICAL AND ELECTRICAL CONNECTIONS, THERMOSTAT, DUCTWORK CONNECTIONS, BRACKETS AND FITTINGS | |||||||
| Rimozione dell'unità ad espansione diretta canalizzata esistente e la relativa unità esterna comprese le connessioni meccaniche ed elettriche, connessione alle canalizzazioni, staffaggi ed accessori | IT. No. Art. n. | 1 | LS/AC | 0.00 | 0 | 0.00 | 0.00 | |
| Total Mechanical - Totale Meccanico | 0.00 | |||||||
| Ic Electrical Demolitions - Ie Demolizioni Elettriche | ||||||||
| 2 | REMOVE F/A SYSTEM | |||||||
| Rimozione Impianto Allarme Incendio | IT. No. Art. n. | 2 | LS/AC | 0.00 | 0 | 0.00 | 0.00 | |
| Total Electrical - Totale Elettrico |
| TOTAL PART I / Totale Parte I |
| PART II - ARCHITECTURAL, STRUCTURAL AND CIVIL WORK / Parte II - Lavori Architettonici, Strutturali e Civili |
| IIa Architectural - IIa Architettonico | |||||||
| 3 | REMOVAL AND REINSTALLATION OF SUSPENDED CEILING PANELS | ||||||
| Rimozione e reinstallazione pannelli contrrosoffitto | IT. No. Art. n. | 1 | LS/AC | 0.00 | 0.00 | 0 | 0.00 |
| Total Architectural - Totale Architettura |
| TOTAL PART II / Totale Parte II |
| PART III - MECHANICAL WORK / Parte III - Lavori Meccanici |
| 4 | FURNISHING AND INSTALLATION OF NEW CHILLER UNIT CH-01 INCLUDING EXPANSION TANK, INERTIAL TANK AND FITTINGS | |||||||
| Fornitura e posa in opera di nuovo refrigeratore CH-01 comprensivo di vaso di espansione, serbatoio inerziale e accessori | IT. No. Art. n. | 1 | LS/AC | 0.00 | 0.00 | 0 | 0.00 | |
| 5 | NEW MINI AIR HANDLING UNIT INCLUDING MECHANICAL AND ELECTRICAL CONNECTIONS, FRESH AIR INTAKE GRILLE WITH G3 FILTER, BRACKETS, ROOM PANEL, 3 WAY CONTROL VALVES, SILENCER, DUCTWORK ADJUSTMENT AND FITTINGS. AHUM-01 | |||||||
| Nuova mini unità di trattamento aria comprensiva di connessioni meccaniche ed elettriche, griglia di presa aria esterna con filtro G3, staffaggi, pannello ambiente, valvole di controllo a 3 vie, silenziatore, modifica canalizzazione e accessori. AHUM-01 | IT. No. Art. n. | 2 | EA/NO | 0.00 | 0.00 | 0 | 0.00 | 0.00 |
| Total Mechanical - Totale Meccanico |
| TOTAL PART III - Totale Parte III | ||||||||||
| PART IV- ELECTRICAL WORK / Parte VI - Lavori Elettrici | ||||||||||
| Power System - Impianto Forza Motrice | ||||||||||
| 6 | RES. CURR. MAGNETOT. CIRCUIT BREAKER AND FEEDING LINE FG16OM16 5G4 MMQ CABLE FOR NEW CHILLER | |||||||||
| Interruttore magnetot.diff.e linea di alimentazione con cavo FG16OM16 5G4 mmq del nuovo refrigeratore | IT. No. Art. n. | 1 | LS/AC | 0 | 0.00 | 0 | 0.00 | 0.00 | ||
| Total Power System - Totale Impianto Forza Motrice | ||||||||||
| Fire Alarm System systems - Impianto Allarme Incedio | ||||||||||
| 7 | SMOKE DETECTORS | |||||||||
| Rilevatori di fumo | IT. No. Art. n. | 2 | EA/NO | 0 | 0.00 | 0.00 | 0 | 0.00 | 0.00 | |
| 8 | HEAT DETECTORS | |||||||||
| Rilevarori di Calore | IT. No. Art. n. | 3 | EA/NO | 0 | 0.00 | 0.00 | 0 | 0.00 | 0.00 | |
| 8 | RED PILOT LIGHT | |||||||||
| Lampada spia rossa | IT. No. Art. n. | 4 | EA/NO | 0 | 0.00 | 0.00 | 0 | 0.00 | 0.00 | |
| 9 | PULL STATIONS | |||||||||
| Stazioni manuali | IT. No. Art. n. | 5 | EA/NO | 0 | 0.00 | 0.00 | 0 | 0.00 | 0.00 | |
| 10 | Audio/video devices | |||||||||
| Dispositivi audio/video | IT. No. Art. n. | 6 | EA/NO | 0 | 0.00 | 0.00 | 0 | 0.00 | 0.00 | |
| 11 | CONVENTIONAL FIRE ALARM CONTROL PANEL | |||||||||
| Centrale Rivelazione Incendi Convenzionale | IT. No. Art. n. | 7 | EA/NO | 0 | 0.00 | 0.00 | 0 | 0.00 | 0.00 | |
| 12 | FTE40HM1 2X1,5 MMQ CABLE | |||||||||
| Cavo FTE40HM1 2X1,5 mmq | IT. No. Art. n. | 8 | LM/ML | 0 | 0.00 | 0.00 | 0 | 0.00 | 0.00 | |
| 13 | PVC RIGID CONDUIT DIAM. 40 MM | |||||||||
| Tubazione Rigida in PVC Diam. 40 mm | IT. No. Art. n. | 9a | LM/ML | 0 | 0.00 | 0.00 | 0 | 0.00 | 0.00 | |
| 14 | PVC RIGID CONDUIT DIAM. 25 MM | |||||||||
| Tubazione Rigida in PVC Diam. 25 mm | IT. No. Art. n. | 9b | LM/ML | 0 | 0.00 | 0.00 | 0 | 0.00 | 0.00 | |
| 15 | PVC FLEXIBLE CONDUIT DIAM. 25 MM | |||||||||
| Tubazione Flesibile in PVC Diam. 25 mm | IT. No. Art. n. | 10 | LM/ML | 0 | 0.00 | 0.00 | 0 | 0.00 | 0.00 | |
| 16 | JUNCTION BOX 80X80X40 MM | |||||||||
| Scatola di Derivazione 80x80x40 mm | IT. No. Art. n. | 11 | LM/ML | 0 | 0.00 | 0.00 | 0 | 0.00 | 0.00 | |
| 17 | F/A programmation | |||||||||
| Programmazione quadro F/A | IT. No. Art. n. | 12 | LS/AC | 0 | 0.00 | 0.00 | 0 | 0.00 | 0.00 | |
| Total Fire Alarm System - Totale Impianto Allarme Incendio | 0.00 |
TOTAL PART IV - Totale Parte IV
| SUMMARY / Riepilogo |
| PART I - DEMOLITIONS, EXCAVATIONS AND REMOVALS |
| PART II - ARCHITECTURAL, STRUCTURAL AND CIVIL WORK |
| PART III - MECHANICAL WORK |
| PART IV - ELECTRICAL WORK |
| TOTAL PRICE / Costo Totale |
OR US DOLLARS (RATE 1$ = ….................. €)
&"Arial,Grassetto"&12FOR OFFICIAL USE ONLY
&"Arial,Grassetto"&12FOR OFFICIAL USE ONLY Sheet &P of &N
SUM BLDGS
| CONSTRUCTION COST ESTIMATE BREAKDOWN | |
| CONTRACTOR | ADDRESS |
| CONTRACT FOR (Work to be performed) | PROPOSED TOTAL CONTRACT PRICE | |||||||||
| DESIGN FOR SUSTAIN HVAC SYSTEM MULTI | ||||||||||
| PURCHASE REQUEST NUMBER | PROJECT NUMBER | WORK LOCATION | ||||||||
| ASHE 18-1087 | AREA C - AREA F, AVIANO AIR BASE, ITALY | |||||||||
| MATERIAL COSTS | LABOR COSTS | |||||||||
| LINE NO. | ITEM | UNIT OF MEASURE | QUANTITY | UNIT | TOTAL | MANHOURS MANDAYS | AVERAGE RATE | TOTAL | OTHER DIRECT COSTS | LINE TOTAL |
| (1) | (2) | (3) | (4) | (5) | (6) | (7) | (8) | (9) | (10) |
BUILDING SUMMARY / Riepologo per Fabbricati
| 1 | BUILDING 410 - SHOPS |
| 2 | BUILDING 416 - WOOD CARPENTRY SHOP |
| 3 | BUILDING 907 - P.MEL LABORATORY |
| 4 | BUILDING 1013 - PETROL OPS |
| 5 | BUILDING 1405 - GYM |
| 6 | BUILDING 1407 - SHOPPETTE |
| 7 | BUILDING 1434 - FIRE BRIGADE |
| 8 | BUILDING 1483 - TLF |
| 9 | BUILDING 10462 - BCE |
TOTAL PRICE / Costo Totale
OR US DOLLARS (RATE 1$ = ….................. €)
&"Arial,Grassetto"&12FOR OFFICIAL USE ONLY
&"Arial,Grassetto"&12FOR OFFICIAL USE ONLY Sheet &P of &N
SUM DISCIPLINES
| CONSTRUCTION COST ESTIMATE BREAKDOWN | |
| CONTRACTOR | ADDRESS |
| CONTRACT FOR (Work to be performed) | PROPOSED TOTAL CONTRACT PRICE | |||||||||
| DESIGN FOR SUSTAIN HVAC SYSTEM MULTI | ||||||||||
| PURCHASE REQUEST NUMBER | PROJECT NUMBER | WORK LOCATION | ||||||||
| ASHE 18-1087 | AREA C - AREA F, AVIANO AIR BASE, ITALY | |||||||||
| MATERIAL COSTS | LABOR COSTS | |||||||||
| LINE NO. | ITEM | UNIT OF MEASURE | QUANTITY | UNIT | TOTAL | MANHOURS MANDAYS | AVERAGE RATE | TOTAL | OTHER DIRECT COSTS | LINE TOTAL |
| (1) | (2) | (3) | (4) | (5) | (6) | (7) | (8) | (9) | (10) |
| DISCIPLINES SUMMARY / Riepilogo per discipline |
| PART I - DEMOLITIONS, EXCAVATIONS AND REMOVALS |
| PART II - ARCHITECTURAL, STRUCTURAL AND CIVIL WORK |
| PART III - MECHANICAL WORK |
| PART IV - ELECTRICAL WORK |
| TOTAL PRICE / Costo Totale |
OR US DOLLARS (RATE 1$ = ….................. €)
&"Arial,Grassetto"&12FOR OFFICIAL USE ONLY
&"Arial,Grassetto"&12FOR OFFICIAL USE ONLY Sheet &P of &N
GRAND TOTAL
ASHE 18-1087- DESIGN FOR SUSTAIN HVAC SYSTEM MULTI - AREA F AND AREA C, AVIANO AB, ITALY
INSTRUCTIONS FOR COMPLETING THE FORM
TOTAL MATERIAL COSTS € $
TOTAL LABOR COSTS € $
TOTAL OTHER DIRECT COSTS € $
TOTAL DIRECT COSTS € $
OVERHEAD % € $
SUBTOTAL € $
PROFIT % € $
TOTAL PRICE € $
DATE FIRM NAME
TITLE BY
INSTRUCTIONS TO OFFERORS
&"Arial,Grassetto"&12FOR OFFICIAL USE ONLY
&"Arial,Grassetto"&12FOR OFFICIAL USE ONLY
Col 1 Item. Description of materials required, work to be done, special equipment needed, etc. Breakdown should be in sufficient detail to permit itemizing of all direct costs.
Col 2 Unit of Measure. Description of the unit in which each item is to be estimated (examples - square yards-SY, cubic yards-CY, square feet- SF, linear feet-LF, board feet-BF, each-EA,, pound-LB).
Col 3 Quantity. Contractor's estimated of quantity required in terms of unit of measure (column 2). Item and units of measure will be furnished by the Government. Quantity estimates will be furnished by the Government only when it is anticipated that a unit price contract will be issued. Otherwise, the contractor is responsible for determining quantity estimates.
Col 4 and 5 Material Costs. Enter unit cost (Col 4) of material to be supplied and total cost (Col 5) for item listed in column 1.
Col 6, 7 and 8 Labor Costs. Enter in col 6 the estimated number of manhours or mandays needed to perform the work listed in column 1. Enter in col 7 the average rate per manhour (manday) and in col 8 the total labor cost.
Col 9 Other Direct Costs. Enter estimated costs of special equipment and other items (listed in column 1), which are special to the contract and of significant dollar value.
Col 10 Line. Self-explanatory.
Note: In addition to other totals entered on various pages, the grand total of column 10, plus overhead and profit will be shown on the last page as follows:
1. The purpose of this form is to provide a standard format by which the offeror submits to the Government a summary of incurred and estimated costs, (and attached supporting information) suitable for detailed review and analysis. Prior to the award of a contract resulting from this proposal, the offeror shall, under the conditions stated in ASPR 3-807.3, be required to submit a certificate of current cost or pricing data (see ASPR 3-807.3 and 3-807.4).
2. In addition to the specific information required by this form, the offeror is experted, in good faith, to incorporate in and submit with this form any additional data, supporting schedules, or substation which are reasonably required for the conduct of an appropriate review and analysis in the light of the specific facts of this procurement. For effective negotiations, it is essential that there be a clean understanding of:
a. The existing, verifiable data.
b. The judgmental factors applied in projecting from know data to the estimate, and
c. The contingencies used by the offeror in his proposed price.
In short, the offeror's estimating process itself needs to be disclosed.
3. When attachment of supporting cost or pricing data to this form is impracticable, the data will be described (with schedules as appropriate) and made available to the contracting officer or his authorized representative upon request.
4. By submission of this proposal the offeror grants to the contracting officer, or his authorized representative, the right to examine, for the purpose of verifying the cost or pricing data submitted, those books, records, documents and other supporting data which will permit adequate evaluation of such cost or pricing data, along with the computations and projections used therein.