Questions & Answer FA568220Q0015:
- 1. Can services be completed during day time by coordinating with the different galleys managers or does it need to happen during the break of operations at night?
Response: Please refer to paragraphs 1.2 and 4.4 and Appendix A in the
PWS
‐ 2. Please provide number of floors above the rooms with the hoods (for example ed 1467 has 3 floors above the mezzanine where the hoods are installed while ed 1391 has no floors above).
Response: The Youth Center Bld 116, is the only facility with duct work that passes through more than one floor.
‐ 3. It was stated that all areas are accessible without need for platforms or truck-mounted platforms to safely reach the roofs and / or extraction fans.
Please confirm.
Response: All roof systems have anchor systems, contractors may use whatever method they desire to safely perform the work.
‐ 4. In some locations there are multiple hoods inside the same building, how many extraction cupcakes / extraction fans are there? (i.e. buildings 1404, 1411.1412 and 1467).
Response:
Facilities w/1 extraction cupcake/fan – 110, 116, 170, 172, 176, 1434, 1476, 5293(Ghedi) Facilities w/3 extraction cupcakes/fans – 1404, 1411 Facilities w/6 extraction cupcakes/fans – 1412 Facilities w/Exhaust Handling Unit(EHU) – 1467, 1391
‐ 5. In the case of a compensated extraction hood, is the delivery part excluded from the contract?
Response: Yes, the delivery system is not part of the contract.
‐ 6. Some systems viewed have highlighted the presence of access hatches for carrying out the work correctly. Are there any system that DO NOT have access?
Response: All systems have access panels/hatches except for the Bowling alley bld 176, the new system has a duct run that is short enough and does not require a hatch.
‐ 7. Indicate if possible for each structure if the kitchen serves 3 meals a day (breakfast lunch and dinners) or if the structure works only for lunch or only for dinner or other combinations.
Response: All facilities operate according to the normal working hours stated in para 4.4 of the PWS. Meal schedules vary and contractors must coordinate with the FM/Kitchen Managers to schedule cleaning dates/times.
‐ 8. Indicate for each structure if there is a closing day in order to facilitate activities in the absence of users and is it necessary to coordinate the activity with the janitorial contractor that will carry out "fine" cleaning? (the premises will be left clean but by experience some customers like a janitorial cleaning company to go through before putting the kitchen back into operation).
Response: Please refer to the Holiday day schedule indicated in para
4.4. and para 1.3.5 regarding Service Completion in the PWS. No additional custodial service will be performed by the Government upon completion of the service.
9. Please confirm that all the buildings are provided (and contractor allowed to use) 220V 16A or 20A power supply.
Response: We can confirm that 220V 16A power is available for contractor use. 20A availability is currently unknown.
10. It was stated that all areas are accessible without need for platforms or truck-mounted platforms to safely reach the roofs and / or extraction fans. Please confirm. The intent is to confirm what was verbally said during the site visit, that is that all roofs and extraction fans are currently reachable without need to estimate costs for platforms or lifts. Please confirm that there are existing ladders or other accessible means that meet safety requirements for all areas considered in this project. This will support a fair and reasonable cost estimate for all participants.
Response: Please, see answer to question no.3.
11. Regarding the "ADDENDUM TO 52.212-1 INSTRUCTIONS TO
OFFERORS - COMMERCIAL ITEMS (JULY 2020) - OFFERS -
PREPARATION INSTRUCTIONS - 1. GENERAL INSTRUCTIONS: e.
Documentation proving good standing and license to operate a business at Aviano Air Base, Italy". Do you mean the authorization to work in Italy? Being an Italian registered company, the Chamber of Commerce certificate from an Italian Chamber of commerce is it enough?
Response: Yes, being an Italian registered company the Chamber of Commerce certificate is enough.
12. Regarding the "ADDENDUM TO 52.212-1 INSTRUCTIONS TO
OFFERORS - COMMERCIAL ITEMS (JULY 2020) - OFFERS -
PREPARATION INSTRUCTIONS - 1. GENERAL INSTRUCTIONS:
d. Proof of System for Award Management (SAM) registration".
We can provide it for the Contractor. Do we have also to provide it for the Subcontractor?
Response: The proof of the System for Award Management (SAM) registration of the main contractor will be sufficient.