UUUY_18_1073_CCEB.XLSX
XLSX spreadsheet 15 KB Posted
- Solicitation number
- FA568218R0040
About this file
UUUY 18-1073 CONSTRUCTION COST ESTIMATE BREAKDOWN
View the file
Other files
| File | Type | Posted |
|---|---|---|
| FA568218R0040_0002.pdf | ||
| FA568218R0040_0003.pdf | ||
| FA568218R0040_00001.pdf | ||
| UUUY181073_Design_REV1.pdf | ||
| UUUY_18_1073_REV1_Submittals_Form_.pdf | ||
| UUUY_18_1073_CCEB_Rev_1.xlsx | XLSX spreadsheet | |
| UUUY_18-1073_SOW_REV1.pdf | ||
| SanVito_HVAC_design.pdf | ||
| Technical_Specifications_UUUY_18-1073.pdf | ||
| ADDITIONAL_REQUIREMENTS.pdf | ||
| FA568218R0040.pdf |
Show all 11
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
UUUY 18-1073
| CONTRACTOR COST ESTIMATE BREAKDOWN | ||||||||||||
| CONTRACTOR | ADDRESS | |||||||||||
| CONTRACT FOR (Work to be performed) | PROPOSED TOTAL CONTRACT PRICE | |||||||||||
| UUUY 18-1073 SUSTAIN HVAC SYSTEM AND WATER SOFTENER SAN VITO | ||||||||||||
| PURCHASE REQUEST NUMBER | PROJECT NUMBER UUUY 18-1073 | WORK LOCATION: San Vito dei Normanni (Brindisi) Italy | ||||||||||
| MATERIAL PLUS LABOR COST | ||||||||||||
| LINE NO. | ITEM | UNIT OF MEASURE | QUANTITY | UNIT | TOTAL | OTHER DIRECT COSTS | LINE TOTAL | |||||
| (1) | (2) | (3) | (4) | (5) | (6) | (7) | (8) | (9) | (10) | |||
| 3. REMOVALS | ||||||||||||
| 1 | REMOVALS | IT. No. Art. n. | 3.1 | LS | 1 | |||||||
| 4. NEW HVAC SYSTEM | ||||||||||||
| 2 | CHILLER UNITS | IT. No. Art. n. | 4.1 | EA | 2 | |||||||
| 3 | AIR TREATMENT UNITS | IT. No. Art. n. | 4.2 | EA | 4 | |||||||
| 4 | CHILLED WATER STORAGE TANK STAINLESS STEEL | IT. No. Art. n. | 4.3 | L.S. | 1 | |||||||
| 5 | CIRCULATING PUMPS | IT. No. Art. n. | 4.4 | EA | 2 | |||||||
| 6 | STAINLESS STEEL PIPELINE | IT. No. Art. n. | 4.5 | LS | 1 | |||||||
| 7 | VALVES, FILTERS, GAUGES AND ASSOCIATED PART | IT. No. Art. n. | 4.6 | LS | 1 | |||||||
| 8 | THERMAL INSULATION STAINLESS STEEL PIPELINE | IT. No. Art. n. | 4.7 | LS | 1 | |||||||
| 9 | UNDERGROUND PLASTIC PIPELINE | IT. No. Art. n. | 4.8 | LS | 1 | |||||||
| TOTAL MECHANICAL WORKS | ||||||||||||
| 5. ELECTRICAL WORKS | ||||||||||||
| 10 | OUTDOOR CONDUITS, BOXES, STAINLESS STEEL CHANNELS | IT. No. Art. n. | 5.1 | LS | 1 | |||||||
| 11 | ELECTRICAL FEEDING LINE CHILLERS | IT. No. Art. n. | 5.2 | LS | 1 | |||||||
| 12 | SECONDARY PANEL FOR PUMPS | IT. No. Art. n. | 5.3 | LS | 1 | |||||||
| 13 | FEEDING LINE FOR SECONDARY PANEL | IT. No. Art. n. | 5.4 | L.S. | 1 | |||||||
| 14 | BLDG 308 FEEDING LINE | IT. No. Art. n. | 5.5 | LS | 1 | |||||||
| 15 | BLDG 309 FEEDING LINE | IT. No. Art. n. | 5.6 | LS | 1 | |||||||
| TOTAL ELECTRICAL WORKS | ||||||||||||
| 5. CIVIL WORKS | ||||||||||||
| 16 | MASONRY ASSISTANCE | IT. No. Art. n. | 6.1 | LS | 1 |
TOTAL COSTS
Sheet &P of & 4