Revision to Tech Specs. Posting Rev #4 dated 15 Feb 2018
View the file
Other files
| File | Type | Posted |
|---|---|---|
| FA568218R0017U00001.pdf | ||
| ASHE_18-1069_BLANK_COST_ESTIMATE.xls | XLS spreadsheet | |
| ADDITIONAL_REQUIREMENTS_January_2018.pdf | ||
| FA568218R0017.pdf | ||
| 2_ASHE181069_Tech_specs_Rev2.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
PROJECT 181069 REV. # 4
DATE: 15 FEB 18
31CES/CEOER 1
DATE: 15 FEB 2018
U.S. AIR FORCE
31ST FIGHTER WING
31ST CES/CEOER
AVIANO AIR BASE, ITALY
STATEMENT OF WORK FOR
ASHE 181069
REPLACE CARPET IN THE 31 FW OFFICES, Bldg # 1360, AREA F, Aviano AB. Italy
31CES/CEOER 2
1. SCOPE OF WORK
The Contractor shall provide all management, tools, supplies, equipment, transportation and qualified personnel necessary to replace carpet in the 31 FW Offices, Fac. # 1360. Work includes removal of existing carpet, old glue, baseboard and thresholds; replace it with high traffic carpet, wooden baseboard and metal thresholds. The color of the carpet will be selected by user representative and approved by PM and CO. The contractor shall give this office a minimum 10 day notification for any eventual disruption of building utilities.
a. The Contractor shall provide, with the bid quotation, the Technical Data Sheets and Material samples related to the carpet intended to be used for the execution of the work.
b. The contractor shall provide, with the bid quotation, a detailed work phasing schedule.
c. Before work starts, if required, the PM, in coordination with the facility manager, will provide a temporary storage area to be approved by CO.
2. WORK LOCATION
Facility # 1360
Works will be performed as marked on the above image.
Phase 2
Phase 1
31CES/CEOER 3
3. WORK SITE CONDITIONS
a. The Contractor is permitted to use reasonable quantities of available electricity and water at the work site. The Contractor shall observe conservation practices at all times. All connections shall be the responsibility of the Contractor including restorations to initial conditions.
b. Authorized work hours and days. Performance of work hereunder shall be from Monday through Friday excluding holidays from 08.00 to 17.00 hours.
c. Public toilets at the work site shall be available for Contractor use. The Contractor shall use facilities in a manner to maintain their state of cleanliness and hygiene.
d. The Contractor shall not use base refuse containers to discard debris. All construction debris shall be discarded by the Contractor off base at authorized sites according to category of debris/refuse in strict observance of all host country laws, decrees and local regulations in force.
e. The Contractor shall be responsible for ensuring all personnel engaged in the performance of this contract observe all national laws concerning safety. At all times the Contractor will assure all personnel are wearing the correct safety equipment when performing their work, such as hard hats, steel toe boots, gloves, reflective gear and any other equipment deemed necessary to perform their work in the safest way. The Contractor shall also assure all personnel comply with Italian laws DM. 81/08. A copy of the Piano Operativo di Sicurezza (POS) will be provided to 31FW/SE (Mr.
Nicola Pezzetta, ph. 0434-307476) after contract award.
4. GENERAL NOTES
a. The Contractor shall be aware that not all areas will be available at the same time therefore the work has to be organized in phases considering giving the offices the minimum possible interruption of functions.
b. The Performance Period for the execution of this project is 45 days considering the time for material procurement, work set up on site.
c. The work in the main admin and main offices (1st phase) shall be performed during the following timeframe, coordinating precise dates with the Project Manager and with the approval of the CO:
‐ The week from 2 - 8 April (max 7 days total);
The work in the remaining areas can be performed in a 2nd phase, immediately consequent to the 1st phase.
d. The Contractor will work as efficiently and systematically as possible to prevent unnecessary work stoppages.
e. After work is completed, all areas will be perfectly cleaned in the way that dust, debris and any material used for the project shall be removed.
5. WORK DESCRIPTION
Each item of the schedule is inclusive of furnishing and installation of materials and equipment, transportation to dump or storage of demolished and/or removed materials, in accordance with contracting officer's instructions and all finishing work required to make each item complete in a workmanlike manner.
31CES/CEOER 4
Contractor shall use proper equipment to remove carpet, baseboard and thresholds taking into consideration the specific area of work. The Contractor shall adhere to proper safety procedures when executing the work, supervising employees working in the immediate area and ensuring they wear the proper safety equipment at all times.
All the quantities that are indicated or successively added are estimates. Therefore the government shall not be held responsible for the accuracy of the estimated quantities. The contract requires a completed project on a lump sum basis. It is therefore the responsibility of the contractor to calculate, foresee and perform all quantities and work necessary even if not mentioned in the specifications but included in the drawings and/or are manifested, in order to deliver a complete project based on its overall scope.
a. Preparation Works: Contractor shall move furniture and equipment as necessary for the removal and installation of new carpet and baseboard. Users are only responsible empty all furniture prior work commencement and to disconnect and reconnect all electronic devices such as computers, tablets, printers, copiers, telephones, etc. At work completion or work phase completion, Contractor shall reposition all furniture and equipment back to their original positions. Items include, protections for furniture and equipment, cleaning and any other work to provide a job made in a workmanlike manner.
Qty: Lump Sum. 1.00
b. Removals: Contractor shall remove existing carpet, baseboard and thresholds. Contractor shall also remove glue and loose particles, baseboard glue or nails, threshold screws and any other substances from the surfaces which are to be covered with carpet. Items include, protections, cleaning and any other work to provide a job in a workmanlike manner. All removed materials shall be disposed IAW IT/EU Laws and Norms.
Qty Sqmt. 430.00
c. Carpet installation: Contractor shall furnish and install high quality and traffic carpet with acoustic backing type Balsan Brooklyn/Odeon/Soho Cat. A+, color # 935, or equivalent approved.
The carpet pile shall be made with 100% solution dyed nylon and the backfelt with 100% polyester, with a Cross-Over Loop Pile structure, minimum total weight 4.855 kg/sqmt, minimum total thickness 10.8mm, minimum pile height 4.2mm. The carpet shall comply with EN14041and shall be CE marked. The installation shall follow manufacturer instruction and recommendations.
Qty Sqmt 430.00
d. Baseboard installation: Contractor shall furnish and install wooden baseboard similar to the existing for dimensions and color.
Qty: Lmt. 300.00
e. Thresholds installation: The Contractor shall furnish and install metal thresholds to cover the joint between 2 different flooring materials.
Qty: Lmt. 27.00
f. Cleaning of areas and touch ups: Contractor shall touch up paint in case of damages during the work performance and also shall perfectly clean the area at work completion, after repositioning of all furniture pieces.
Qty Lump Sum. 1.00
31CES/CEOER 5
6. WARRANTY
a. At the end of the work, for warranty call purposes, the Contractor shall provide the Government with the following document:
- Letter identifying project number, item, company address, phone number, point of contact, item warranty expiration date, etc.
File details come from the government source that posted it.