TECHNICAL SPECIFICATIONS
View the file
Other files
| File | Type | Posted |
|---|---|---|
| FA5682-16-R-0039.pdf | ||
| Blank_Cost_Est_Fac__1405.xls | XLS spreadsheet | |
| ADDITIONAL_REQUIREMENTS.pdf | ||
| B_1405_Applicable_Master_Tech_Specs.pdf | ||
| Attachment___1.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Technical Specifications
DATE: AUGUST 2016
31FSS 1
U.S. AIR FORCE
31ST FIGHTER WING
31ST CES/CENMP
AVIANO AIR BASE, ITALY
TECHNICAL SPECIFICATIONS
PAINTING INTERIOR AND SECURE FITNESS CENTER BACK
OFFICES, FAC. 1405, AVIANO AB, ITALY
31FSS 2
1. SCOPE OF WORK. The Contractor shall provide all management, tools, supplies, equipment and qualified personnel necessary to paint the interior of several rooms of Dragon Fitness Center, bldg.
1405 in Area F. The project includes also the closing of snack bar serving window and adjacent door opening thus the furnishing and installation of a new roller shutter and new door. Period of performance shall be 60 calendar days to allow material procurement, work execution and clean-up.
2. WORK LOCATION : Bldg. 1405 (Area F)
31FSS 3
3. WORK SITE CONDITIONS:
a. Before works start, Contractor in coordination with the facility manager will provide a detailed work schedule to be approved by C.O.
b. The Contractor is permitted to use reasonable quantities of available electricity and water at the work site. The Contractor shall alter characteristics and shall observe conservation practices at all times. All connections shall be the responsibility of the Contractor including restorations to initial conditions.
c. Authorized work hours and days. Performance of work hereunder shall be from Monday through Friday excluding holidays from 08.00 to 17.00 hours. Work during weekends or holidays may be requested by the Contractor with a minimum of 10 days advance notice, however the Contracting Officer has the right to deny such request if reasons requiring weekend and holiday work are not valid or for security or other necessities.
d. Toilet facilities in the vicinity of the work site shall be available for Contractor use. The Contractor shall use facilities in a manner to maintain their state of cleanliness and hygiene.
e. The Contractor shall not use base refuse containers to discard debris. All construction debris shall be discarded by the Contractor off base at authorized sites according to category of debris/refuse in strict observance of all host country laws, decrees and local regulations in force.
f. The Contractor shall be responsible for ensuring all personnel engaged in the performance of this contract observe all host country laws concerning safety. At all times the Contractor will assure all personnel are wearing the correct safety equipment when performing their work, such as steel toe boots, gloves, reflective gear and any other equipment deemed necessary to perform their work in the safest form. The Contractor shall also assure all personnel comply with Italian laws
DM. 81/08.
g. At least 5 days prior to the pre-final inspection, the Contractor shall furnish to the Contracting Officer all documentation for the subject contract as required per host nation laws..
4. GENERAL NOTES
1. At the end of the work, the Contractor shall provide the Government with three copies of the following documents: for warranty call purpose, 3 copies of letter identifying project number, item, company address, phone number, point of contact, item warranty expiration date, etc. One copy of the letter will be installed next the item for immediate consultation.
2. Offerors will submit Technical data of the material to be installed and indicated in the Item
5.1 - 5.3 - 5.4 below, along with the proposal documentation.
3. Contractor will have to move/relocate and protect with plastic sheet any furniture and equipment at his own expense in order to perform painting works.
4. Works will have to be performed in four phases.
31FSS 4
5. WORK DESCRIPTION
Each item of the schedule is inclusive of furnishing and installation of materials and equipment, scaffolding, transportation to dump or storage of demolished and/or removed materials, in accordance with contracting officer's instructions and all finishing work required to make each item complete in a workmanlike manner.
All the quantities that are indicated or successively added are estimates. Therefore the government shall be not held responsible for the accuracy of the estimated quantities. The contract requires a completed project on a lump sum basis. It is therefore the responsibility of the contractor to calculate, foresee and perform all quantities and work necessary even if not mentioned in the specifications but included in the drawings and/or are manifested, in order to deliver a complete project based on its overall scope.
5.1 Furnish and application of two coats of acrylic-polyurethane enamel satin water,for indoor,type
SIGMA CONTOUR AQUA PU SATIN, or equivalent, having high resistance to abrasion and dirt with the new LTA + technology the enamel layer rejects body oil and dirt making the surface easier to clean and beautiful over time.
• Innovative technology LTA + (Lipophobic Technology for (PU) Acrylics +) allows to reject grease and grime.
• Very high resistance to scratching and abrasion.
• Excellent hiding power.
• Excellent leveling and ease of application.
• Non-yellowing.
• Odorless.
• Under VOC.
Contractor shall remove all harmful substances from all stucco/concrete surfaces using sandpaper, wire brush or sub with steel wool over the entire surface and scrape where necessary to remove damaged paint, including walls grouting. Contractor shall use the proper equipment to perform the job to include scaffolding, protections, cleaning and any other work to provide a job in a workmanlike manner. Enamel shall applied in the corridor (room #02) only where missing, inside aerobics room (#09) in the upper part of the walls and in the kids room (#08) in the bottom part of the wall until 1.20 mt height from the floor.
SQ.M 230.00
5.2 Provide manpower, materials and equipment necessary for scraping gypsum board ceilings-plaster on walls in the male/female showers stalls and corridors leading in and out of same (rooms # 03). Item includes smoothing work of the scraped surfaces thus application of smoothing products suitable for gypsum board brand Knauf or equivalent and any other work to give a job performed in a workmanlike manner.KE KEIM Mycal®-FixIM Mycal®-FixKEIM Mycal®-Fix
SQ.M 120.00
5.3 Furnishing and application of two coats of high-quality silicate-based paint for interiors type
CAPAROL Sylitol Bio-Innenfarbe or equivalent, with the following characteristic:
Solvent-free, un-plasticized, free of fogging-active substances, higly diffusion capable sd
H2O<0.02 m as per DIN EN 1062, potassium silicate, retain the diffusibility and water vapour permeability of substrates. Item includes application of one coat of primer Caparol Haftgrund where necessary.
The above described paint shall be applied in all male/female restrooms walls/ceilings: rooms 03- 04- 05- 06- 07.
SQ.M 610.00
31FSS 5
KEIM MlKEMMycal®-Top®-Top
5.4 Furnishing and application of two coats of high-quality water-based paint for interiors based on styrene - acrylic resin and selected fillers, class 1 coverage and washability, matte, ultra-fine, high washing resistance and high coverage, type CAPAROL CAPATOP or equivalent, with the following characteristic: wet abrasion: Class 1; Density: approx. 1.5g/ml; good resistance to brushing, diffusion to water vapor and dries in a short time allowing rapid reuseof enviroments.
The above described paint shall be applied in the rooms: 01-10-11 and 08 (from 1.20 mt until the false ceiling).
SQ.M 1534.00
5.5 Provide manpower, materials and equipment necessary for the repair of existing wallpaper, where damaged, (approx.. 20 SQ.M.) and verification of the existing rubber sheet adherence to wall support (room #01, #09) and following bonding where necessary (approx. 15 SQ.M).
Item includes furnishing and installation of new material where existing wallpaper or rubber sheet are not longer in good condition and cannot be fixed. New material shall have the same characteristic and similar color of existing material, including all operation in order to give a job performed in a workmanlike manner.KE KEIM Mycal®-FixIM Mycal®-FixKEIM Mycal®-Fix L.S.
5.6 Provide manpower, material and equipment necessary to close up an existing opening ( approx.
97 x 265 cm), as showed in the pictures # 1, thus the furnishing and installation of one new soundproofed door, having dimension 85x210 cm, with scratch-proof plastic laminate finish, galvanized factory painted steel frame and counter-frame, same color of other existing doors.
Door shall be complete with fixing hardware, sealing gasket, accessories, lockset type “Best Access System F84” or equivalent.
The upper part of the door shall be close by transom window, complete with frame and stratified glazing 3+3 mm. Item includes plaster repair, painting touch-up, removal and disposal of existing frame and wooden wainscot and any other work to give a job performed in a workmanlike manner
L.S.
5.7 Provide manpower, material and equipment necessary to close up the existing snack bar serving window (approx. 2.60 x 2.48 mt), see pictures # 2, thus the furnishing and installation of one new blind roller shutter, made of galvanized steel elements (pitch 11.5 cm), version micro perforated, type De Nardi, or equivalent, thickness 10/10 and equipped with slide ways, bearings, shaft with springs, screws, anchoring elements and side locks. Contractor will furnish and install of one-phase reversible gear motor 220V 50 Hz, protected by heat sensor located in coil and opening with man attending. New motor shall be equipped with stop, electromagnetic lock, inner unlocking for manual emergency operation and it shall be electrically connected to the nearest secondary electrical panel, including wiring, conduits, junction box, dedicated circuit breaker, etc. Item includes closing the upper part of the serving window thus gypsum board, modification of existing false ceiling and installation of new steel support for the roller shutter. Contractor shall submit before installation a shop drawing to Project Manager for approval. The roller shutter shall be polyester powder –coated paint finish on both side and RAL colours shall be selected by Project Manager. Contractor shall perform all works necessary to give a job performed in a workmanlike manner without any additional cost for the Government.
31FSS 6
5.8 Contractor shall use proper scaffolding to perform work on interior of the facility due to the height of the areas that needs to be painted. At all times, the contractor shall adhere to proper safety procedures where scaffolding has been set up and for all personnel that are working in the immediate area to wear the proper safety equipment at all times.
Picture #1 Picture #2
Picture corridor, room#2 Picture room # 9
31FSS 7
Picture room # 11
6. APPLICABLE TECHNICAL SPECIFICATIONS
The following Sections of the Master Specifications for construction projects of the Air Base in Aviano (PN), Italy, dated November 2005 and applicable modifications shall be applicable to the present project, together with the List of Work Items to be performed:
01100R GENERAL CONDITIONS
01101R PROJECT SIGN
05500R METAL FABRICATIONS
08331 08210
ROLLING SERVICE GRILLS
WOOD DOORS
09900R PAINTS AND COATINGS
7. LIST OF ATTACHMENTS:
Attachment 1 – Floor Plan of Fac. 1405
DATE: AUGUST 2016