This document is a set of Questions and Answers related to Solicitation FA561324Q0031 for the Ramstein AB EMCS & Water System BACnet/IP Applications contract opportunity.

The key details are:

  • The solicitation is for an EMCS Control System to BACnet/IP and Water Control System to BACnet/IP Cyber Security Update project at Ramstein Air Base.
  • Questions were due by August 29, 2024 and quotes are due by September 4, 2024.
  • The water production is 445,000,000 gallons per year, using 14 deep wells approximately 330 feet deep with 15,000 to 23,000 GPH submersible pumps.
  • The water treatment system requires 3 calcium carbonate filters with air blower, 6 activated carbon filters, post-aeration, chlorination, and sodium fluoride addition.
  • The contract is being issued by the Department of the Air Force, United States Air Forces in Europe - Air Forces Africa.

View the file

Other files

Show all 11

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

DEPARTMENT OF THE AIR FORCE

86TH AIRLIFT WING (USAFE)

6 September 2024

MEMORANDUM FOR INTERESTED PARTIES

FROM: 700 CONS/PKA

Kapaun AS, Germany

SUBJECT: Questions and Answers for Solicitation FA561324Q0031– Third Round

1. Interested parties are provided the following secondary questions and answers for the subject solicitation – please note that this document is a continuation of previously answered questions.

Question 12: Flow Rates – Could you please provide the expected flow rates for the water control system?

Answer 12: Water production – 445,000,000 Gal. per year. 14 Deep wells located on base are approximately 330 feet deep, 24 inches in diameter and equipped with 15,000 to 23,000 GPH submersible pumps.

Question 13: Water Treatment Requirements – Could you specify the type of water treatment that will be required for this project?

Answer 13: Water Treatment: 3 calcium carbonate treatment filters with air blower for deacidification of the raw water, with subsequent activated carbon filtration via 6 Active carbon filters. Post-aeration and chlorination and addition of sodium fluoride.

2. Please direct any questions or concerns to Contract Specialist, Ms. Cevonia Joshua at cevonia.joshua.1@us.af.mil and the Contracting Officer at christian.leyva_meraz.1@us.af.mil.