Past Performance Questionnaire (PPQ)
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Comb_Synop-Sol_15-R-0007_26May15.doc | DOC document | |
| Atch_6 _EMS_Flyer.doc | DOC document | |
| Atch_2 _PWS_22_Apr_15_final.doc | DOC document | |
| Atch_1 _Pricing_Schedule__26_May_15.doc | DOC document | |
| Atch_4 _PMP-QCP_27May15.doc | DOC document | |
| Atch_3 _Clauses Prov_26May15_final.doc | DOC document |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Attachment 5, Past Performance Questionnaire (PPQ)
FA5613-15-R-0007
Past Performance Questionnaire (PPQ) This acquisition is for A Occupational Health Care (OHC) and Consultation Service of Local National Civilians at Ramstein, Spangdahlem Air Base and their Geographically Separated Units (GSUs) in Germany A.
GENERAL INFORMATION: Please correct any information below known to be inaccurate:
Contractor’s Name: ____________________ Address:
Telephone Number: ____________________
Email Address:
Point of Contact:
Project Title or Brief Description of Work*:
Contract Number*:
Contract Amount:
Contract Period or Dates of Performance*:
Contractor performed as the ( Prime Contractor ( Sub-Contractor ( Key Personnel.
To be completed by the respondent and returned directly to the contracting office.
* Note: If offeror holds or has held other contracts with your agency/organization in the last 3 years, please complete separate evaluation forms for those contracts as well.
B.
RATER INFORMATION:
Name of Rater:
Title:
Address:
Phone Number:
Email Address:
C. RETURN COMPLETED SURVEY FORM WITHIN 4 WORKING DAYS AFTER RECEIPT TO:
Claudia Ledig/Contract Specialist Inge Jenkins/Contracting Officer
700 CONS/LGCA
and
700 CONS/LGCA
claudia.ledig.de@us.af.mil ingeborg.jenkins.1.de@us.af.mil
+49-631-536-0014 or DSN 489-0014 +49-631-536- 6800 or DSN 489-6800
CONTRACTOR’S NAME:
CONTRACT NUMBER:
D. PERFORMANCE INFORMATION: Choose the appropriate letter on the scale (A or U) that most accurately describes the contractor’s performance or situation. PLEASE PROVIDE A NARRATIVE EXPLANATION FOR ANY RATINGS OF Unacceptable (U).
| A |
| U |
| Acceptable |
| Unacceptable |
| Performance meets contractual requirements. The contractual performance of the element or sub-element may have contained some minor problems for which corrective actions taken by the contractor were satisfactory. |
| Performance does not meet most contractual requirements and recovery is not likely in a timely manner. The contractual performance of the element or sub-element contains a serious problem(s) for which the contractor’s corrective actions appear or were ineffective. |
Place an “X” in the appropriate column using the definitions matrix above.
| The contractor: |
| Acceptable |
| Unacceptable |
| 1. |
| Provided experienced managers and supervisors with the technical and administrative abilities needed to meet contract requirements and adequate project supervision at the place of performance. |
| 2. |
| Demonstrated ability to hire, maintain, and/or replace, if necessary, qualified personnel during the contract period. |
| 3. |
| Provided adequately certified, licensed and trained personnel. |
| 4. |
| Interfaced and cooperated with government quality assurance personnel (or corporate/agency equivalent) after being awarded the contract and/or commencement of project performance. |
| 5. |
| Maintained sanitary conditions within the work environment. |
| 6. |
| Provided effective quality control and/or inspection procedures to meet contract requirements. |
| 7. |
| Provided timely resolution of contract discrepancies pursuant to their quality control procedures and established procedures to prevent recurrence of discrepancy. |
| 8. |
| Identified problems as they occurred and/or suggested alternative approaches to problem resolutions. |
| 9. |
| Displayed initiative to solve problems and follow-up to ensure desired results were achieved. |
| 10. |
| Provided timely and courteous service to clients. |
| 11. |
| Was responsive to contract changes (if applicable). |
| 12. |
| Contractor adequately coped with any sudden surge in requirements (if applicable). |
| 13. |
| Contractor adequately coped with short notice requirements. |
| 14. |
| How would you rate the vendor's overall performance? |
REMARKS/COMMENTS: