Attachment 3 - Questions and Answers FA560624Q0073.docx
DOCX document 30 KB Posted
- Attached to
- Custom ISU - Amendment 1
- Solicitation number
- FA560624Q0073
About this file
This document contains Questions and Answers related to Solicitation FA560624Q0073 for a Custom ISU (Internal Slingable Unit). The key details are:
The solicitation is seeking a customized internal airlift/helicopter slingable container unit (ISU) capable of housing tools and equipment necessary to maintain and store explosives in any environment. This is a re-solicitation due to no technically acceptable quotes received previously under Solicitation FA560624Q0046.
The questions address details such as the base container part number, requirement for ATTLA certification for internal air transport, operating temperature requirements, and the responsibilities of the contractor versus the end user. Responses indicate that alternative ISUs will be considered, a certifiable container is acceptable if dimensions are met, the operating temperature range is -65F to 160F, and the contractor is responsible for the ISU and customization while the end user will provide and install other equipment.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Questions and Answers for Solicitation FA560624Q0073
1. Are you able to provide the base container part number?
The requirement is based off of the AAR 56TBD‐TBD, 56257996, but alternative ISUs will be considered for acceptance.
1. Does the base container need to be certified by ATTLA for internal air transport? Would it be acceptable to offer a certifiable container?
Yes & Yes, if dimensions are met
1. Can you provide additional details in regards to the following line listed in the minimum requirements document? “The unit must also be compliant with the 11P series T.O. for required operating temperatures”
-65°F Min thru 160°F Max degrees
1. Is the contractor installing required equipment or is the end user?
The contractor is responsible for the ISU and the customization of the ISU to accommodate the build in Attachment 2. The end user will provide and install the other equipment.