Questions Answers FA560621Q2007.pdf

PDF 95 KB Posted

Attached to
Luggage X-Ray Scanner
Solicitation number
FA560621Q2007
Issued by

View the file

Other files

File Type Posted
Amendment 3.pdf PDF
Amendment 2.pdf PDF
Amendment 1.pdf PDF
Combo 726 AMS Luggage X-Ray Machine FA560621Q2007.pdf PDF
726 AMS Luggage X-Ray Machine SOW 15 Mar 2021.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

# Reference Paragraph Questions Answers

1 Statement of Work 4.2.2 Width

In order to ensure adequate competition, we recommend the following modifications to the Width Specification:

Width: Not greater than 203cm or 80".

We cannot adjust the width as we are limited on space. Per Salient Characteristics & Specifications document, width will be 134.6 cm or 53'.

2 Statement of Work 4.2.3 Height

We understand that the height is not a critical dimension of the X‐ray unit. In order to ensure adequate competition, we recommend the following modifications to the Height Specification:

Height: Not greater than 212cm or 83.5".

We can adjust to no greater than 212cm or 83.5". Per Salient Characteristics & Specifications document, height will be 147.3 cm or 58'.

3 Statement of Work

4.5 Description

of Product

There is no mention of including entry/exit roller tables with the X‐ray machine. Are these required and, if so, what size? 0.5m? 1.0m?

We would like entry/exit roller tables.

We have no requirement on size, however the Salient Characteristics and Specifications document lists these at 50cm increments.

4 Statement of Work

4.5.3 Conveyor

load

In order to ensure adequate competition, we recommend the following modifications to the Conveyor Load Specification:

Conveyor load (minimum) of 200kg or 441lbs.

We need the weight to cover 220kg or 485 lbs for deployment bags, pelican cases, etc. Per Salient

Characteristics & Specifications document, conveyor capacity will evenly distribute 165 kg or 360 lbs evenly.

5 Statement of Work

5. Contractor

Support

Does 726th AMS require that the contractor identify a local in‐country warranty service provider?

Yes, we will require the contractor identify a local in‐country warranty service provider.

6 Statement of Work

6. Installation and

Acceptances

Although 726 AMS prefers commercial shipping to Spangdahlem AB, is shipping to a military facility to be accepted into the military airlift system an acceptable approach?

Shipping through the military airlift system is acceptable.

7 Statement of Work 7. Training Is there a specific training duration that is desired, e.g., two‐day, 8 hours per day?

There is no training duration required. Only require minnimum training of 2 personnel.

8 Statement of Work

9. Date of

Delivery

The requirement states "Project completion shall be no later than five (5) months after date of award." However, in document "Combined

Synopsis/Solicitation" it is stated that "Equipment Delivery within 90 days of award. Installation/Training scheduled and performed within 30 days of equipment delivery." This totals only four (4) months after award. We recommend that project completion be no more than seven (7) months after date of award, to take into account uncertainties associated with Export

Licensing, Country‐Specific Customs Clearance procedures, Base Access requirements and lead‐time, COVID‐19 impacts on supply chain, and restricted travel of Field Service Rep's in the future due to COVID‐19 pandemic. Also, we recommend Equipment Delivery within 150 days of award, with Installation/ Training scheduled and performed within 60 days of equipment delivery, resulting in project completion no more than seven (7) months after date of award.

We can push the project completion to your recomendation of no more than 7 months after date of award. Please be aware that the fiscal year ends 30

September 2021, and we would highly prefer this to be expensed before that time.

Combined

Synopsis/Solicitation

Line Item

0003. Delivery

Regarding Delivery, it is understood that delivery is FOB Destination only.

However, do you require “dock‐dock” delivery, in which case your facility personnel would be required to move the equipment from the facility receiving dock to the specific install location inside the facility, and would also be responsible for removal/disposal of all crating materials ‐‐ OR – do you want me to quote “Inside” delivery, where the vendor would be responsible for delivery to the facility loading dock, for movement of the equipment to the specific install location inside the facility, and for removal/disposal of all pallet/shipping materials?

We would like the vendor to do a "inside" delivery.

Combined

Synopsis/Solicitation

Instructions to

Offerors

It is stated that "Quoted amounts need to be net prices without tax". Will

U.S. vendors shipping on Commercial freight to Spangdahlem, AB Germany be responsible for local Customs Duties and Value Added Taxes (VAT)?

Yes, the vendor will be responsible for local Customs Duties and VAT.

Combined

Synopsis/Solicitation

Instructions to

Offerors

In preparing a technical reponse to be evaluated for Technical Acceptability according to all requirements outlined in attachment 1 (726 AMS Luggage X‐

Ray Machine SOW 15 Mar 2021), is there guidance on page count, font size, etc.?

No guidance for this requirements.

Combined

Synopsis/Solicitation

Instructions to

Offerors

In accordance with FAR provision 52.212‐1, Instructions to Offerors ‐‐

Commercial, is relevant Past Performance information required and will it be considered as an evaluation factor?

No, we will do LPTA, not requesting past performance.

Will all electrical/power sockets etc be in situ?

Yes, we have electrical sockets.

Is power 220v and plugged for German power outlets?;

Yes, the outlets in the area are 220v. Per Salient Characteristics and Specifications, power will be dual voltage.

We supplied Patch Barracks in Stuttgart with similar products and training recently – the main issue we had there was unloading on delivery and moving the machines around. Will you be able to provide a forklift truck on base to unload the scanner from the lorry and then subsequently move it during installation (the latter is preferable but I understand it may not be possible given available space, if not my team can do it manually but they will certainly need one for unloading)? Will regulations allow our technicians to use the forklift on site (they are qualified) and if not will you be able to provide an operator? Best case scenario both would be available for two days but one day is essential.

We have 10K forklifts. Your technician can operate or we can provide a operator.

Does 726th AMS desire to purchase equipment from a contractor's GSA

Federal Supply Schedule 84?

Government will post this requirement on GSA.