Attachment_2_BID_SCHEDULE_UPS.pdf

PDF 12 KB Posted

Attached to
Replace Service and Maintennance of Power Supply Units
Solicitation number
FA5606-18-Q-1008
Issued by

About this file

Attachment 2 BID SCHEDULE

View the file

Other files

File Type Posted
Combo_Synopsis.pdf PDF
Attachment_3_FAR_52.212-3.pdf PDF
Attachment_1_SOW_-_UPS_MX.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

For Official Use Only

For Official Use Only

17-Jul-18

Service Unit Price Total 1 ea. Replace existing UPS in the basement of

Bldg. 47 1 ea. Installation and assembly of batteries and

UPS in Bldg. 47 as well as the all cable connection work incl. all necessary cables and of the system commissioning

3 ea. Major maintenance (overhaul) on existing parallel feeding UPS systems in Bldg. 77 including delivery of replacement parts as specified in manufacture instructions.

1 ea. Preventive Maintenance (PM) on one UPS installed in basement of Bldg. 215

2 ea. PM on 2 parallel feeding UPS systems in Bldg. 544

1 ea. PM on one UPS installed in Bldg. 2077

1 ea. Major maintenance (overhaul) on existing parallel feeding UPS systems in Bldg. 71 including delivery of replacement parts as specified in manufacture instructions.

Qty

BID SCHEDULE

Replace 1 complete UPS System and provide Service and Maintenance

Please provide Price and Cost as applicable below.

TOTAL COST

Sheet1