Text version

INSTALLATION

CONSTRUCTION COST ESTIMATE BREAKDOWN
CONTRACTORADDRESS
CONTRACT FOR (Work to be performed)PROPOSED TOTAL CONTRACT PRICE
Fiber to Core 4 Buildings
PURCHASE REQUEST NUMBERPROJECT NUMBERWORK LOCATION
USAFE- QUUG-12-00005-01MORÓN AIR BASE, SPAIN
UNITMATERIAL COSTLABOR COSTSOTHER
LINITEMOFDIRECTLINE
NO.MEAS.QUANTI.UNITTOTALMH/MDAV.RATTOTALCOSTSTOTAL
(1)(2)(3)(4)(5)(6)(7)(8)(9)(10)
MANHOLE & DUCT SYSTEM WORK: DIGGING & CONDUITS INSTALLATION
Sistema de arquetas y conductos: excavacion e isnstallacion de conductos
1Install MH-Noncore 1 as shown on sketch 1
Instalar arqueta MH-Noncore 1 como se especifica en el sketch 1del SOOJOB
2Install MH-Noncore 2 as shown on sketch 1
Instalar arqueta MH-Noncore 2 como se especifica en el sketch 1del SOOJOB
3Install MH-Noncore 7 as shown on sketch 5
Instalar arqueta MH-Noncore 7 como se especifica en el sketch 5 del SOOJOB
4Install MH-Noncore 8 as shown on sketch 5
Instalar arqueta MH-Noncore 8 como se especifica en el sketch 5 del SOOJOB
5Install MH-Noncore 9 as shown on sketch 5
Instalar arqueta MH-Noncore 9 como se especifica en el sketch 5 del SOOJOB
6Install MH-Noncore 10 as shown on sketch 5
Instalar arqueta MH-Noncore 10 como se especifica en el sketch 5 del SOOJOB
7Install MH-Noncore 11 as shown on sketch 5
Instalar arqueta MH-Noncore 11 como se especifica en el sketch 5 del SOOJOB
8Install MH-Noncore 12 as shown on sketch 5
Instalar arqueta MH-Noncore 12 como se especifica en el sketch 5 del SOOJOB
9Install two (2) each 4" Schedule 40 PVC ducts - concrete encased - between MH-69, MH-New1, MH-New2, MH-New3, MH-Noncore 1 and MH-Noncore 2
Instalar 2 conductos de PVC de 4" Schedule 40 en prisma de hormigon entre MH-69, MH-New1, MH-New2, MH-New3, MH-Noncore 1 y MH-Noncore 2JOB
10Install two (2) each 4” Schedule 40 PVC ducts from MH-Noncore 2 to Bldg 302
Instalar 2 conductos de PVC de 4" Schedule 40 desde MH-Noncore 2 hasta el edificio 302JOB
11Install two (2) each 4” Schedule 40 PVC ducts from MH-Noncore 2 to Bldg 303
Instalar 2 conductos de PVC de 4" Schedule 40 desde MH-Noncore 2 hasta el edificio 303JOB
12Install two (2) each 4” Schedule 40 PVC ducts from MH-Noncore 1 to Bldg 107
Instalar 2 conductos de PVC de 4" Schedule 40 desde MH-Noncore 1 hasta el edificio 107JOB
13Install MH-Noncore 3 as shown on sketch 2.
Instalar arqueta MH-Noncore 3 como se especifica en el sketch 2 del SOOJOB
14Install two (2) each 4” Schedule 40 PVC ducts - concrete encased - between MH-Noncore 1 and MH-Noncore 3.
Instalar 2 conductos de PVC de 4" Schedule 40 en prisma de hormigon entre MH-Noncore 1 y MH-Noncore 3JOB
15Install two (2) each 4” Schedule 40 PVC ducts from MH-Noncore 3 to Bldg 320.
Instalar 2 conductos de PVC de 4" Schedule 40 desde MH-Noncore 3 hasta el edificio 320JOB
16Install one (1) new Handhole 4’x4’x51” on locations MH-Noncore 4 as shown on Sketch 3
Instalar arqueta MH-Noncore 4 como se especifica en el sketch 3 del SOOJOB
17Install two (2) each 4” Schedule 40 PVC ducts - concrete encased - between MH-Noncore 3 and MH-Noncore 4.
Instalar 2 conductos de PVC de 4" Schedule 40 en prisma de hormigon entre MH-Noncore 3 y MH-Noncore 4JOB
18Install two (2) each 4” Schedule 40 PVC ducts from MH-Noncore 4 to Bldg 314
Instalar 2 conductos de PVC de 4" Schedule 40 desde MH-Noncore 4 hasta el edificio 314JOB
19Install one (1) new Handhole 4’x4’x51” on locations MH-Noncore 5 as shown on Sketch 3
Instalar arqueta MH-Noncore 5 como se especifica en el sketch 3 del SOOJOB
20Install two (2) each 4” Schedule 40 PVC ducts - concrete encased - between MH-Noncore 4 and MH-Noncore 5.
Instalar 2 conductos de PVC de 4" Schedule 40 en prisma de hormigon entre MH-Noncore 4 y MH-Noncore 5JOB
21Install two (2) each 4” Schedule 40 PVC ducts from MH-Noncore 5 to Bldg 313
Instalar 2 conductos de PVC de 4" Schedule 40 desde MH-Noncore 5 hasta el edificio 313JOB
22Install one (1) new Handhole 4’x4’x51” on locations MH-Noncore 6 as shown on Sketch 4.
Instalar arqueta MH-Noncore 6 como se especifica en el sketch 4 del SOOJOB
23Install two (2) each 4” Schedule 40 PVC ducts - concrete encased - between MH-Noncore5 and MH-Noncore6
Instalar 2 conductos de PVC de 4" Schedule 40 en prisma de hormigon entre MH-Noncore 5 y MH-Noncore 6JOB
24Install two (2) each 4” Schedule 40 PVC ducts from MH-Noncore6 to Bldg 311
Instalar 2 conductos de PVC de 4" Schedule 40 desde MH-Noncore 6 hasta el edificio 311JOB
25Install two (2) each 4” Schedule 40 PVC ducts from MH-Noncore6 to Bldg 310
Instalar 2 conductos de PVC de 4" Schedule 40 desde MH-Noncore 6 hasta el edificio 310JOB
FO INSTALLATION & ACCESS TO THE BUILDINGS
Installacion de FO y acceso a los edificios
26Install metallic conduits and NEMA 4 X enclosures to acess buildings 107, 302, 303, 310, 311, 313, 314, and 320 Instalar cajas de registros y conductos metalicos de acceso a los edificios 107, 302, 303, 310, 311, 313, 314 y 320JOB
27Install 3X3 maxcell & innerducts 1" in one of the vacant 4” ducts for the route as specified in the SOO. Instalar 3X3 maxcell & innerducts 1" como se especifica en el SOO.JOB
28Install Comm. equipment Cabinet in buildings 107, 302, 303, 310, 311, 313, 314, and 320 Instalar RACKS 24U en sala de comunicaciones de los edificios 107, 302, 303, 310, 311, 313, 314 y 320
29Run 12 str FOC from ITN160 to Bldg 302. Instalar cable de 12 FO desde ITN 160 hasta Bldg 302.JOB
30Install one each 96 port FOC panel in existing Comm. Cabinet in Bldg 160
Instalar un Panel de Conexion de FO para 96 fibras en el armario de comunicaciones del edificio 160.JOB
31Install one each 12 port FOC panel in new Comm. Cabinet in Bldg 302
Instalar un Panel de Conexion de FO para 12 fibras en el armario de comunicaciones del edificio 302.JOB
32Terminate the 12-str to the FOC panel using fusion splice to pigtails with SC connectors in Bldgs 160 & 302
Terminar las 12 fibras fusionando con pigtails con conectores SC en Bldgs 160 & 302JOB
33Run 12 str FOC from ITN160 to Bldg 303. Instalar cable de 12 FO desde ITN 160 hasta Bldg 303.JOB
34Install one each 12 port FOC panel in new Comm. Cabinet in Bldg 303
Instalar un Panel de Conexion de FO para 12 fibras en el armario de comunicaciones del edificio 303.JOB
35Terminate the 12-str to the FOC panel using fusion splice to pigtails with SC connectors in Bldgs 160 & 303
Terminar las 12 fibras fusionando con pigtails con conectores SC en Bldgs 160 & 303JOB
36Run 12 str FOC from ITN160 to Bldg 107. Instalar cable de 12 FO desde ITN 160 hasta Bldg 107.JOB
37Install one each 12 port FOC panel in new Comm. Cabinet in Bldg 107
Instalar un Panel de Conexion de FO para 12 fibras en el armario de comunicaciones del edificio 107.JOB
38Terminate the 12-str to the FOC panel using fusion splice to pigtails with SC connectors in Bldgs 160 & 107
Terminar las 12 fibras fusionando con pigtails con conectores SC en Bldgs 160 & 107JOB
39Run 12 str FOC from ITN160 to Bldg 320. Instalar cable de 12 FO desde ITN 160 hasta Bldg 320.JOB
40Install one each 12 port FOC panel in new Comm. Cabinet in Bldg 320
Instalar un Panel de Conexion de FO para 12 fibras en el armario de comunicaciones del edificio 320.JOB
41Terminate the 12-str to the FOC panel using fusion splice to pigtails with SC connectors in Bldgs 160 & 320
Terminar las 12 fibras fusionando con pigtails con conectores SC en Bldgs 160 & 320JOB
42Run 12 str FOC from ITN160 to Bldg 314. Instalar cable de 12 FO desde ITN 160 hasta Bldg 314.JOB
43Install one each 12 port FOC panel in new Comm. Cabinet in Bldg 314
Instalar un Panel de Conexion de FO para 12 fibras en el armario de comunicaciones del edificio 314.JOB
44Terminate the 12-str to the FOC panel using fusion splice to pigtails with SC connectors in Bldgs 160 & 314
Terminar las 12 fibras fusionando con pigtails con conectores SC en Bldgs 160 & 314JOB
45Run 12 str FOC from ITN160 to Bldg 313. Instalar cable de 12 FO desde ITN 160 hasta Bldg 313.JOB
46Install one each 12 port FOC panel in new Comm. Cabinet in Bldg 313
Instalar un Panel de Conexion de FO para 12 fibras en el armario de comunicaciones del edificio 313.JOB
47Terminate the 12-str to the FOC panel using fusion splice to pigtails with SC connectors in Bldgs 160 & 313
Terminar las 12 fibras fusionando con pigtails con conectores SC en Bldgs 160 & 313JOB
48Run 12 str FOC from ITN160 to Bldg 311. Instalar cable de 12 FO desde ITN 160 hasta Bldg 311.JOB
49Install one each 12 port FOC panel in new Comm. Cabinet in Bldg 311
Instalar un Panel de Conexion de FO para 12 fibras en el armario de comunicaciones del edificio 311.JOB
50Terminate the 12-str to the FOC panel using fusion splice to pigtails with SC connectors in Bldgs 160 & 311
Terminar las 12 fibras fusionando con pigtails con conectores SC en Bldgs 160 & 311JOB
51Run 12 str FOC from ITN160 to Bldg 310. Instalar cable de 12 FO desde ITN 160 hasta Bldg 310.JOB
52Install one each 12 port FOC panel in new Comm. Cabinet in Bldg 310JOB
Instalar un Panel de Conexion de FO para 12 fibras en el armario de comunicaciones del edificio 310.
53Terminate the 12-str to the FOC panel using fusion splice to pigtails with SC connectors in Bldgs 160 & 310
Terminar las 12 fibras fusionando con pigtails con conectores SC en Bldgs 160 & 310JOB
Total Project USAFE- QUUG-12-00005-01
Total Proyecto USAFE- QUUG-12-00005-01

&"Times New Roman,Regular"AF Form 3052 (Computer Generated) &"Times New Roman,Regular"Page &P of &N