Questions and Answers .pdf

PDF 119 KB Posted

Attached to
Update USAG Okinawa Stormwater Pollution Prevention Plan
Solicitation number
FA527025Q0017
Issued by

About this file

This document is a Questions and Answers (Q&A) addendum for Request for Quote (RFQ) FA527025Q0017 regarding a Stormwater Pollution Prevention Plan project in Okinawa, Japan. The Q&A addresses a specific clarification about the Statement of Work (SOW) requirements for professional engineer (PE) involvement during field survey activities. The government's response indicates that a PE is not required to be present at all field surveys, but is necessary at certain points, such as the beginning of field survey activities. A note emphasizes that it is the contractor's responsibility to ensure email communications have been accepted by the government.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

QUESTIONS & ANSWERS RFQ: FA527025Q0017

QUESTIONS AND ANSWERS

For Solicitation Number: FA527025Q0017 Stormwater Pollution Prevention Plan, Okinawa Japan

1. Section 1.4.1.3 of the SOW states that “The survey team shall include, at a minimum, the project PE specialist.” Please confirm that the intent of the government is to have the field survey team include full-time PE Engineer staff on site during all field survey activities. Or is the intent of the government to have the field survey team perform work under the general oversight of a PE Engineer who may or may not present during field survey activities?

Answer: It is not required PE be present at all field surveys but required at the certain point such as begging period of field surveys.

NOTE: it is contractor’s responsibility that email has been accepted by the Government.