This Statement of Work (SOW) details the requirements for procuring nineteen (19) portable office spaces for the Resolute Force Pacific (REFORPAC) 25-1 Exercise at Antonio B. Won Pat Airport in Guam. The portable office spaces must be either 8ft by 40ft or 10ft by 40ft, positioned on a concrete surface, and will be utilized from 01 July to 10 August 2025 (40 total days). Each portable office space must include specific amenities such as exterior and interior lighting, emergency exit signs, electronic keypad locks, fire extinguishers, electrical receptacles, CAT5/CAT6 terminals, and furnished with 3 desks, 15 chairs, 1 microwave, and 1 refrigerator.

The contractor will be responsible for providing generators and air conditioning with 24/7 support, ensuring safety and securing mechanisms for inclement weather, and managing all mobilization and demobilization logistics. Critical requirements include obtaining Entry Authorization Letters, completing airfield driver training, adhering to base security protocols, and submitting various documentation like mobilization/demobilization schedules and entry access lists within specified timeframes. The contractor must also be prepared for potential emergency evacuation of equipment and provide contact points for maintenance support with a maximum one-hour response time for emergency maintenance.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

STATEMENT OF WORK

FOR

PORTABLE OFFICE SPACE

All amendments to the original Statement of Work have been highlighted in yellow.

Details: Portable Office Space to include Mobilization/De-Mobilization, footings/tie downs, generator, air conditions, furnishings, and step or deck for use as office and maintenance workspace at Antonio B. Won Pat

Airport, Guam.

Andersen Air Force Base (RESOLUTE FORCE PACIFIC (REFORPAC) 25-1)

Nineteen (19) 8ft by 40ft minimum or 10ft by 40ft portable office spaces positioned at Antonio B.

Won Pat Airport Dates: 01 July – 10 August 2025

Total Days: 40 Days

Purpose: Vendor will provide Portable Office Space (POS) in support of the Resolute Force Pacific

(REFORPAC) 25-1 Exercise Nineteen (19) 8ft by 40ft minimum or 10ft by 40ft portable office spaces positioned at Antonio B. Won Pat Airport, Guam no later than COB 01 July 2025. This includes all anchoring blocks and cabling, interior furnishings, and power. Dates, locations, and specifications are subject to change.

Portable Office Space: Nineteen (19) 8ft by 40ft minimum or 10ft by 40ft portable office spaces positioned at

Antonio B. Won Pat Airport, Guam.

Structures will be installed on a concrete or comparable surface with an approximate 1% grade in certain areas—regrade is not required but recommend the use of shims to accommodate minimal leveling.

Each structure shall include a minimum of (1) exterior outdoor light over each exit and interior battery powered emergency exit signs, interior overhead lighting IAW OSHA Standard table F-1

1915.82 minimal light intensities, installed power receptacles IAW US National Electrical Code

Section 210.52 (A)(1), adequate air conditioning for square footage and max occupancy, reliable electrical system to include generator and HVAC with 24/7 support in the event of equipment failure. Structures shall include electronic keypad locks at each exit with (1) master key. Structures shall have level flooring, a proper drainage system and shall be elevated to ensure no flooding.

Every interior section shall include locking interior access doors with electronic keypad locks, one (1) ABC fire extinguisher at each exit, a minimum of six (6) electrical power receptacles with two (2) grounded outlets each, and six (6) CAT5/CAT6 terminals with four (4) keystones per receptacles, per 640 square feet of space.

Furnishings: Each POS shall include the following furnishings: 3 desks, 15 chairs, 1 microwave, and 1 refrigerator. There are no special needs requirements for the furnishings, however interior offices will suffice if there are enough desks, seating, microwave and refrigerator per portable office space.

Delivery Location: Nineteen (19) 8ft by 40ft minimum or 10ft by 40ft portable office spaces positioned at Antonio B. Won Pat Airport, Guam.

Delivery Timeframe: Deliveries will be made by vendor on multiple dates and times that will be confirmed at award. Delivery POCs will be given after contract award for coordination purposes.

Generator and HVAC Support: Vendor will provide generator(s) and air conditioner(s) capable of supporting the above requested square footage of office space on a 24/7 basis. Contractor shall coordinate with 36 CES for generator and facility grounding requirements. Contractor shall be responsible for fuel to power generators as needed, upkeep and periodic maintenance of all equipment to reduce risk of potential equipment failures. Contractor shall provide customer with a primary and alternate point of contact and phone number to coordinate 24/7 emergency maintenance support and be available within a maximum response time of one (1) hour from initial notification of emergency maintenance.

Safety: Vendor will provide a securing mechanism that prevents damage to surrounding areas and keeps the structures in place during inclement weather or high wind conditions of 40 to 57 miles per hour.

Vendor must follow all safety and traffic procedures while operating on base.

Setup/Teardown: Customer will only support airfield gate entry during mobilization and demobilization.

No government furnished equipment, or manpower will be provided for mobilization, installation, tear-down, or de-mobilization. Contractor must obtain Entry Authorization Letter (EAL) and airfield driver training from the 36th Operations Support Squadron (36 OSS) for unescorted access to container location.

EAL information or copy of Base Pass information must be submitted to the Contracting Office NLT 3 days after award.

Inclement Weather: IAW with the basic contract, containers shall be secured for inclement weather.

Frequency: Vendor may make multiple pre-coordinated deliveries with designated POCs.

Additional Rental Equipment: Contractor equipment shall be clearly marked with vendor company name and contact information. Equipment must be clean upon delivery, made of quality material, and durable to withstand heavy use. Government shall return equipment in clean, fair wear and tear, and operable condition. Excessive damages and any lost or missing equipment shall be reported to Contracting

Officer in writing within 10 days of demobilization. Damages, beyond fair wear and tear, must be photo documented (before and after).

Andersen AFB Emergency Evacuation of Contractor Equipment: At any time during the period of performance, the contractor may be directed by order of the 36th Wing Commander for 36 WG/CAT to demobilize/remove all equipment from the airfield and/or base. Reasons for evacuation may be typhoon, natural disaster or military/national security related. Contractor shall be required to remove all equipment within 48 hours. Once emergency is resolved contractor will be notified to remobilize or if services are no longer required. Contractor will be entitled to submit a Request for Equitable Adjustment (REA) for emergency demobilization and remobilization costs.

Base Security: Base security is of the utmost importance. Contractor shall abide by all base security rules and regulations. Current 36 SFS policy directs all contractors must enter and exit through the North Gate between 0600 hours and 1800 hours, Monday through Friday. Exiting after 1800 hours is authorized through Main Gate however Contractor shall utilize the North Gate for all Mobilization/De-Mobilization of Portable Office Space. All access through North Gate outside normal operating hours must be coordinated NLT 3 duty days prior, unless it is an emergency, through the Contracting Officer, and is subject to approval by 36 SFS. If required, the Contractor must submit any Base Access Request revisions and/or renewals NLT 3 calendar days after award, base pass request shall be valid through the contract’s ultimate completion date.

Airfield Access and Driver Training: Contractor shall submit initial EAL as stated in the “Submittals” section below. Contractor shall update EAL as required and must notify the Government within 24 hours of employee termination. Personnel accessing the airfield must obtain airfield driver training from 36 OSS prior to performance, all restricted area badges must be returned to 36 SFS upon contract completion.

Badges from any terminated employee shall be turned in within 5 calendar days.

Contractor Submittals

Airport Access Request: Updates must be submitted to the Contracting Office NLT 3 calendar days after award (as required). If contractor does not need to make any changes an email submittal stating, “no changes required” must be submitted NLT 3 calendar days after award. The Government will not be responsible for contractor delays if contractor fails to provide information on time.

Entry Access List: Contractor shall submit the full name and Social Security number for all employees requiring airfield access to the Contracting Office, NLT 3 calendar days after task order award or notice to proceed. Government will not be responsible for contractor delays if contractor fails to provide information on time.

Mobilization Schedule: Contractor shall submit mobilization schedule to the Contracting Office NLT 3 calendar days after award. Government will not be responsible for contractor delays if contractor fails to provide information on time.

Demobilization Schedule: Contractor shall submit demobilization schedule to the Contracting Office

NLT 5 calendar days prior to the expiration of the period of performance. Government will not be responsible for contractor delays if contractor fails to provide information on time.