This document contains a question and answer file related to a federal contract solicitation for replacing switchgears at Andersen Air Force Base in Guam. The solicitation seeks a design-build project to remove existing 15kV SF6 gas insulated pad mounted switchgears and provide new vacuum fault interrupter biodegradable fluid switchgears. The work includes replacing lightning arresters, fault indicators, and load break elbow connectors. The period of performance is 540 calendar days. The estimated value is between $1-5 million. The acquisition is set aside as a HUBZone small business opportunity under NAICS code 237130. Proposals were due by May 5th, 2022 and must be submitted electronically through the Procurement Integrated Enterprise Environment website. The question and answer file provides responses to contractor questions on requirements, specifications, and timelines.

View the file

Other files

Show all 16

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

22 April 2022

Notice ID: FA524022R0003 – Solicitation

Project Title: AJJY 21-1009 Replace Various SF6 Gas Insulated Switchgears, Andersen Air Force Base, Guam

QUESTION AND ANSWER

Question #01: To confirm that a bid bond is required at 20% of the bid amount, not to exceed $3 million for this solicitation.

Answer #01: The Government confirms that a bid bond is required. In accordance with FAR 28.101-2(b), the bid guarantee amount shall be at least 20 percent of the bid price but shall not exceed $3 million. Be informed that FAR clause 52.228-1 Bid Guarantee will be incorporated in Solicitation No. FA524022R0003, Amendment #01 is forthcoming.

Question #02: Our switchgear manufacturer advised us that the lead time for the submittals is 6 weeks and production lead time is 46 weeks. May we request to have the performance period be changed from 330 calendar days to 540 calendar days?

Answer #02: Performance period is hereby extended from 330 calendar days to 540 calendar days due to long lead times for the switchgears. Solicitation No. FA524022R0003, Amendment #02 is forthcoming to reflect the change of the performance period in the statement of work.

Question #03: Is the Arc Flash and SCCS Study of this project to involve only the replacement of existing switches? Is the intent to determine the settings of the new switch only or to the next existing switch upstream?

Answer #03: Ensure coordination between new equipment design and the existing distribution system, immediately upstream and downstream of the new switches.

Question #04: The rating of the Lightning Arresters being 15kV, may we know the required surge MCOV typically used at AAFB?

Answer #04: Contractor shall determine the appropriate rating based on a 13.8kV system, code requirements, and manufacturer recommendation/industry standards.

Question #05: Please clarify if PWUC criteria requirement will also be basis for VFI protection device, e.g., fault protection relay be SCADA ready, cable fault indicators at the switch, installed at the outgoing side of the loop elbow, VFI protection device with programmable tri-phase with ground trip electronic control logic, and port for laptop connection, etc.

Answer #05: PWUC Chapter 2 Electric criteria for medium voltage systems shall apply to the project.

Should there be any discrepancies between PWUC and ACBDS requirements, ACBDS shall take precedence.

Question #06: Is the intent to provide new cable fault indicators on all cables, or only to replace where existing fault indicators exist. SOW indicates “all 15kV cables”.

Answer #06: Provide new cable fault indicators on all cables.

Question #07: SOW asks to test existing grounding system and to provide additional if 5 ohms is not achieved. Difficult to price this now since the SOW will not be defined until after the test.

As we know AAFB has high resistance grounding system, can the government define how many ground rods are needed?

Answer #07: For the grounding system, the statement of work (Section 2.4.2g) requires the contractors to provide additional ground rods to meet the ground resistance not to exceed 5 ohms.

Additional of Helical grounding system is acceptable to meet the specified ground resistance.

Question #08: Are viewing windows required? PWUC requires it but the RFP is not clear if PWUC applies to this project since it is in AAFB. Viewing windows will require two-sided switchgears which have larger footprint.

Answer #08: PWUC Chapter 2 Electric criteria for medium voltage systems shall apply to the project.

Should there be any discrepancies between PWUC and ACBDS requirements, ACBDS shall take precedence.

Question #09: RFP states, “Disconnect and remove medium voltage cables from the pad-mounted switches to manhole and replace with new. Provide in-line splice in manhole.” We assume new cabling is XLPE, MV-105, 133% insulation. We might have problem with ordering limited quantity of XLPE cables. Can we order minimum as required and the unused cables will be turned over to the Government?

Answer #09: New MV cabling shall comply with ACBDS requirements. Contractor shall order the minimum as required and any unused cables shall be turned over to the Government/BOSC- DZSP21 Annex 1601.

Question #10: RFP states, “Trace, identify, and tag all underground cables in all accessible locations such as pad mounted switches and manholes.” As worded, this means all cables including existing ones not touched by the project. Clarify if the intent is to only tag the cables the project will replace with new.

Answer #10: Intent is to tag all cables affected in switches and manholes where connections are made.

Question #11: The RFP requires submission of bid bond. Please advise if the original copy of the bid bond needs to be hand delivered to the contracting office.

Answer #11: Original copy sent electronically is acceptable. Please ensure that proof of “ORIGINAL” markings are visible on the electronic submission.

Question #12: May we request for Division 01, General Requirements specifications?

Answer #12: As this is a stand-alone project, there are no Division 01 general requirement specifications. However, the contractor shall complete a usable final product that can be used to fully satisfy the requirements and the intended purpose of this project.

Question #13: We would like to request a 2 week extension to the proposed due date of our proposal.

The reason for this request to ensure we have enough time to receive our quotes from suppliers and are able to give the government the best possible price proposal. Thank you for your consideration.

Answer #13: Amendment #01 granted a one-week extension to the proposal deadline from 21 April

2022 up to and including 28 April 2022. Amendment #02 is forthcoming to extend the proposal deadline one more week from 28 April 2022 up to including 05 May 2022.

Question #14: SOW requires 316 stainless steel for the pad mounted switch housing, please confirm if stainless steel 304 is acceptable.

Answer #14: 304L SSTL enclosure is acceptable.

Question #15: Please provide misc. detail drawing for the concrete pad.

Answer #15: Contractors shall conduct field investigations/library research as needed to collect concrete pad details.

Question #16: We would like to respectfully request for a one (1) week time extension on the bid submission date. The additional time is necessary to prepare a competitive bid and give vendors/suppliers ample time to provide their quotations.

Answer #16: Amendment #01 granted a one-week extension to the proposal deadline from 21 April

2022 up to and including 28 April 2022. Amendment #02 is forthcoming to extend the proposal deadline one more week from 28 April 2022 up to including 05 May 2022.

Question #17: Is the MEC required for this project?

Answer #17: MEC is required per RFP Part 1 SOW, section 3.3.

Question #18: Kindly identify facilities that will affect during the power outage? Are the affected facilities having its own power generator?

Answer #18: Refer to RFP Part 2, Attachment 1 for Partial AAFB One-line Diagrams. Listed below are the

Andersen Air Force Base facilities with generators. Phase work to accomplish minimal impact as possible to base operations.

10 23028 COMMAND POST

15 9060 WATER PLANT

16 25024 TROPICANA

18 14509 ANDY 2

29 17002 BASE OPS/FIRE 1 PAX AND WEATHER

31 23020 SFS

32 1722B FIRE STATION 3

34 18002 SUPPLY

48 23008 CRG

51 683 BOOSTER 3

52 1618 (MOA1620) BOOSTER 2

53 1098 GOLF COURSE LIFT

54 1294 PALUA LOOP

55 1881 BACK GATE LIFT

63 2403 VISITOR CENTER

69 1000 WELL 8

70 715 WELL 6

71 998 (WAS 999) WELL 9

77 1625 CDC

84 1091

OVCC (SUNRISE CONFRENCE CENTER (GOLF

COURSE))

89 21004 ICC (RENAME) INSTALLATION CONTROL CENTER

5 26052 SUBSTATION

9 25008 TELE EXCHANGE (COMMUNICATIONS FACILITY)

17 26206 ANDY 1

19 26201 PUMP HOUSE 1

20 19025 PUMP HOUSE 2

24 2750 COMM WEATHER

25 70 MT SANTA ROSA

26 70A MT SANTA ROSA FP

27 2616 REMOTE TEL

28 18110 HANGAR 8 GLOBAL HAWK

39 18033 (MOA 18104) HANGAR 7

47 51109 CALCM/PMEL

57 24102 ARC LIGHT LIFT

61 2647 HSC-25

62 25010 MAGELLAN INN

64 9003 EOD/AMMO

65 25045 HAWC

66 17000 MXG/PMEL

PRIORITY BUILDING NUMBER SITE NAME

72 9034 MUNS CONTROL

73 8417 MUNS SQUADRON

79 19033 734TH AIR FREIGHT

1 2800 TACAN CAT

1 2800 TACAN KOHLER

3 2662 GLIDE SLOPE 1

3 2662 GLIDE SLOPE 2

4 18015 CONTROL TOWER

7 23002 COMM 13

21 2589 PUMP HOUSE 3

22 2594 PUMP HOUSE 4

35 17016 HANGAR 1

36 18017 HANGAR 2

37 18017 HANGAR 2 FP 1

37 18017 HANGAR 2 FP 2

38 18114 (18110 IS THE ACTUAL) HANGAR 6 FP 1 (NOW HANGAR 8) (AF)

38 18114 HANGAR 6 FP 2 (NOW HANGAR 8) (AF)

38 18114 HANGAR 6 FP 3 (NOW HANGAR 8) (AF)

44 18001 CE CONTROL

49 2510 ALERT FACILITY

65 2655 FIRE STATION 2

78 87 NEXRAD

80 21001 (MOA21002) PUBLIC AFFAIRS

68 9050 Well 3

2 18010 AIRFEILD LIGHTING

8 20011 DATA AUTOMATION

30 18011 FAA (OSI)

40 18104 (NOT 18033) HANGAR 7 FP 1

41 18104 HANGAR 7 FP 2

42 18104 HANGAR 7 FP 3

43 18104 HANGAR 7 FP 4

45 18042 VEHICLE MAINTAINCE

46 17006 NDI LAB

50 20029 SOUTH RAMP BOOSTER

58 21018 ANG DELUGE PUMP

65 18035 TRANSPORTATION

68 25010 (9007G) AF WELL 1

74 51104 MUNS FP (CALC/PMEL FIRE PUMP)

75 20019 BEACON TOWER

76 14625 ACE VEHICLE

Question #19: During the site visit, Contractors are not allowed to take photos inside existing manhole.

Requesting photos inside the manholes.

Answer #19: Opening a manhole requires coordination with Operations/DZSP 21. All circuits inside electrical manholes are energized, and therefore a scheduled outage is required to open the manholes. Refer to RFP Part 2, Attachment 1 for Partial AAFB One-line Diagrams for existing quantities and sizes of conduits and cables inside the manhole.

Question #20: Are the contractors required to install enclosures for every switchgear to be installed?

Answer #20: Individual enclosures are not required. The existing switchgears are located within Building 26052’s concrete enclosure.

Question #21: Page 15 paragraph 4.6 Cybersecurity indicates: “Design, acquire and execute all control system in accordance with UFGS 25 02 11 Cybersecurity of Facility-Related Control Systems, and as required by individual Facilities Engineering Command (FEC) or Installation implementation policy. Comply with UFGS 25 05 11 – Cybersecurity of Facility-Related Control System and complete Cybersecurity Hygiene Checklist. Due to price impact, please clarify the extent of cybersecurity requirement, do we need to provide equipment such as computer/ethernet system per individual facilities that affected by work? Please advise.

Answer #21: No, Computer and Ethernet system are not required, however, the proposed pad-mounted switchgears shall be provided with VFI protection device equipped with programmable tri-phase with ground-trip electronic control logic, relay action indicator or detector, and port for laptop connection. The device shall be capable of storing fault events log data. Provide applicable software.

************NONE TO FOLLOW************

84 14600A ACE ENTRY

85 18013 AMC MAINTANICE

86 19009 WATER TOWER

83 26006 TOP OF THE ROCK (USO)

6 10 DET-2 Power Plant #3 6 10 DET-2 Power Plant #1 6 10 DET-2 Power Plant #2

11 61207 (BLDG 25) NWF WATER PLANT (DET WATER PUMP)

12 36 RADOME DET-2 Radar DET 2 SOP

13 91 DET-2, SOP

14 61300 COMM (PRTC)

33 61210 Fire Station 4 PRTC 56 61380 NWF Lift Station 59 61207 NEED TO RENAME DUPLICATE NWF Fire Deluge Pump 2 60 61207 NWF Fire Deluge Pump 1