Questions/Answers #1
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| Questions__2.pdf | ||
| Mass_Notification_SOW_20180703.pdf | ||
| Attachment_2_-_Wings_A_&_B.pdf | ||
| Attachment_1_-_Mass_Notification_SOW_20180515.pdf | ||
| Attachment_6_-_UFC_4-021-01.pdf | ||
| Attachment_4_-_GE_EST3.pdf | ||
| Attachment_5_-_Honeywell.pdf | ||
| Attachment_3_-_Wing_C.pdf | ||
| Combo_Synopsis_Solicitation.pdf |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Questions and Answers (3 July 2018)
FA5215-18-R-8007
1. REFERENCE: SOW Item 8.0 Testing and attachment 6 UFC 4-021-01 para 1-5.3 Performance and Acceptance Testing:
QUESTION: Who is the Authority Having Jurisdiction (AHJ) for this project, and who will be the AHJ's representative who will witness the acceptance test for the gov't?
Answer: Asia Pacific Center for Security Studies
2. REFERENCE: attachment 6 UFC 4-021-01 para 4-2 Requirements for System Designers:
QUESTION: Please confirm whether a NICET IV (fire alarm systems) engineering technologist will suffice as the Designer of Record for this project.
Answer: Yes, NICET IV will suffice.
3. REFERENCE: SOW Item 3.0 Specific Tasks and 9.0 Period/Place of Performance
QUESTION: What, if any, are the specific design phase (i.e. preparation of drawings and equipment submittals and gov't approval thereof) requirements for this project?
QUESTION: Does the design phase need to be accomplished within the 120 days of award?
QUESTION: Who is the AHJ's representative that will review and approve the design documents, and does the time it takes for that task count against the 120 day completion?
Answer: Submit plans and equipment submittals for Government approval prior to beginning of installation. The Design phase is not part of the 120-day project completion window. An amendment to the Statement of Work is attached addressing the design phase (Section 6).