SOW Amdnment 02.docx

DOCX document 40 KB Posted

Attached to
Replace DSN-HDD Generator for 78th Signal Battalion, Camp Zama, Japan.
Solicitation number
FA520926Q0077
Issued by

About this file

This is an updated Statement of Work (SOW) Amendment for the replacement and disposal of a 150 kVA emergency power diesel generator located at Building 121, Camp Zama, Japan, issued by the 78th Signal Battalion and updated October 26, 2026, to incorporate contractor clarifications. The contractor must perform complete decommissioning and removal of the existing unserviceable Toyo Denki Seizo TYND-215 generator, including safe fuel and coolant disposal in compliance with Japanese environmental regulations at authorized off-base facilities, with documentation of hazardous waste disposal required. The contractor shall retain and reuse the existing stainless-steel diesel fuel tank (renewed 2008), fuel piping, electrical wiring, and air intake ducts if serviceable after inspection and certification, while removing old conduits and exhaust piping that cannot be reused. A temporary backup generator must remain operational during the construction period to maintain emergency power for Building 121.

The new generator must be exactly rated 150 kVA / 120 kW at 208/120 VAC, 50 Hz diesel-powered, featuring a radiator fan guard, water jacket heater (thermostatically controlled, 1,000-1,500 W maintaining 40-50°C standby temperature), phase-to-phase and phase-to-neutral metering, automatic frequency adjustment (49.5-50.5 Hz steady-state), automatic voltage regulation (±5% per ANSI C84.1), and EPA Tier 3 or Tier 4 engine certification. The contractor must conduct an 8-hour load test using site loads (approximately 30-40 kVA) supplemented by dummy load as necessary, with the system required to start, reach rated voltage and frequency, and accept full emergency load through the existing Automatic Transfer Switch within 40 seconds. All work must comply with the more stringent of applicable U.S. or Japanese requirements, including Japanese national noise standards and all references listed in Section 13 (UFC, NFPA, JEGS 2024, and relevant standards). The contractor must provide personnel holding current 2nd Class Electrician License, 3rd Class Chief Electrical Engineer License, and Specialized Electrical Construction Qualification for Emergency Backup Generator Construction certifications. Deliverables include the new generator, installation, minimum 8-hour load test, three sets of work performance and test reports in English and Japanese, as-built drawings, full replacement parts catalogs with manufacturer drawings, operation manuals, warranty documents, and training for 78th Signal and DoD personnel. A minimum one-year warranty (parts and labor) covering premature failures under normal operations is required. The contractor must submit a detailed construction schedule at least 30 business days prior to on-site work and provide power outage notifications 30 business days in advance. Asbestos testing and abatement costs shall not be included in base quotation; the Government will handle asbestos assessment separately and may add a dedicated Contract Line Item via formal amendment if removal is necessary. The federal contract opportunity (Solicitation FA520926Q0077) references a minimum 2-year warranty requirement in the opportunity description, creating a potential conflict with the SOW's stated 1-year minimum.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

FI-MUE Replace Zama DSN-HHD Generator – Updated SOW

STATEMENT OF WORK (SOW)

FI-MUE Replace Zama DSN-HHD Generator 78th Signal Battalion Camp Zama, Japan Updated: 26 October 2026 (Incorporates responses to Contractor Questions / Clarifications)

1. INTRODUCTION

This Statement of Work (SOW) defines the requirements, scope, responsibilities, and deliverables for the replacement and disposal of the 150 kVA emergency power diesel generator located on Camp Zama, Japan, Building 121.

This updated SOW incorporates clarifications provided in response to Contractor (KTR) questions. Where a conflict exists between this document and prior drafts, this updated version governs. The more stringent of applicable U.S. or Japanese requirements shall apply.

2. SCOPE OF WORK

The contractor shall provide all necessary materials, equipment, labor, and services to:

2.1. Decommissioning and Removal of Existing Generator

• Disconnection from the electrical distribution system.

• Safe removal of residual fuel and proper disposal in accordance with environmental regulations.

• Safe removal of coolant and oil and proper disposal in accordance with environmental regulations.

• Disassembly and transport of the existing generator from the site (Bldg. 121, Camp Zama) to an authorized disposal facility. "Authorized waste disposal facilities" means facilities licensed under Japanese laws and regulations.

• Removal and disposal of old conduits and exhaust piping that cannot be re-used for the new generator system.

• The existing stainless-steel diesel fuel tank (renewed 2008 and confirmed serviceable), associated fuel piping, and electrical wiring shall be retained if they remain in a serviceable condition after contractor inspection, testing, and certification. Section 4.1 intent is to remove the generator unit itself while retaining serviceable tank, piping, and wiring.

2.2. Disposal and Environmental Compliance

• Disposal of the generator, engine, batteries, coolant, and oils shall be completed by the contractor utilizing off-base locations.

• Proper handling and disposal of hazardous materials, including oil, fuel, and battery components.

• Contractor shall provide a copy of the receipt of disposal of any hazardous waste to the Government Representative (GR). In Japan, an industrial waste management manifest is used for industrial waste; submission of a copy of this manifest is acceptable documentation.

• The contractor shall comply with all U.S. Government and Japanese environmental laws (whichever are most stringent) to protect the health and safety of employees/residents and preserve the local and global environment. The contractor shall comply with the Japan Environmental Governing Standards (JEGS) and shall minimize or eliminate environmental pollution and energy/utility waste.

2.3. Installation of New Generator

• Site preparation, including foundation modifications if required. Validity of the anchoring method may be demonstrated by seismic calculations based on Japanese seismic standards. Once the seismic evaluation determines the most suitable anchoring method, foundation modifications (if required) are part of site preparation.

• Delivery and offloading of the new generator.

• Installation and secure anchoring of the generator unit. A radiator fan guard is required on the new generator set. The contractor shall provide a safe installation complying with applicable Japanese and U.S. safety standards. OEM guarding equivalent to or better than the existing protective arrangement is expected.

• Electrical integration with the existing power panel and/or new Automatic Transfer Switch (ATS). Contractors are permitted to reuse existing wires and conduits from Panel L-M-2 (also referenced as L-M and P-M in related drawings) to the generator provided they reach without the need for splicing. Splicing of wires is not permitted. If existing wire does not reach, the contractor shall supply new wires from the connection point in the panel to the new generator output breaker.

• Connection and modification of the exhaust system. The contractor may reuse existing exhaust piping to avoid new holes and core drilling of the outside wall.

• The contractor shall utilize all existing air intake ducts, both internal and external, for compatibility. The contractor is encouraged and permitted to re-use the existing fuel piping and radiator exhaust ducting, provided that they are thoroughly inspected, tested, and certified by the contractor to be in fully functional, safe, and leak-free condition prior to integration with the new generator system.

• The existing Stainless Steel Diesel Tank, renewed in 2008 and confirmed to be serviceable, shall be utilized by the contractor. Technical drawings for this tank are available upon request from the COR/GR. If required for compatibility, the installation height of the existing fuel tank may be modified (by modifying the existing mounting stand or adding a new one), provided the tank remains serviceable and all connections are inspected, tested, and certified leak-free and safe.

• A temporary/backup generator shall be installed and operational during the construction period while the existing generator is removed and the new unit is not yet commissioned, to maintain emergency power capability for Building 121.

2.4. Testing and Commissioning

• Verification of electrical connections and power output.

• Contractor shall conduct a minimum 8-hour load test utilizing site loads as part of the post-installation test and commissioning plan. Site load is approximately 30–40 kVA. The generator shall be rated 150 kVA / 120 kW so that it can operate near the intended load range; oversized units are not acceptable. Contractor may supplement site loads with a dummy/resistive load bank as necessary to achieve meaningful loading and demonstrate performance. Fuel from the existing stainless-steel diesel tank may be used for the test.

• Contractor shall provide a draft post-installation test and commissioning plan to the GR no later than 30 days prior to final acceptance of the new generator system. This test plan will need to be reviewed and approved by the GR prior to being implemented for acceptance. The test plan shall address both steady-state operating tolerances and transient performance during load application or motor starting.

2.5. Handover and Documentation

• Training for facility personnel on new generator operation and maintenance.

• The contractor shall submit three (3) sets of work performance and test result reports, as-built drawings, operation manuals, and warranty documents in both English and Japanese, to the GR (78th Signal Battalion/DPW) within 15 calendar days after the work completion date. Such reports shall be submitted in booklet-type and digital forms with catalog cuts/manufacturer drawings of replacement parts.

• When using U.S.-made parts or products for which documentation is available only in English, submission of a Japanese version may be omitted for those specific items.

• A parts list alone is not acceptable in place of the full replacement parts catalog or manufacturer’s drawings. Both the full replacement parts catalog/manufacturer drawings are required to ensure future maintainability.

3. TECHNICAL SPECIFICATIONS

3.1. Existing Generator Details (To Be Disposed of)

• Capacity: 150 kVA / 120 kW

• Voltage Output: 208/120 VAC

• Make/Model: Toyo Denki Seizo / TYND-215

• Fuel Type: Diesel

• Frequency: 50 Hz

• Current Status: Unserviceable and Obsolete, to be decommissioned

3.2. New Generator Specifications

• Capacity: 150 kVA / 120 kW (exact rating required; oversized units are not acceptable)

• Voltage Output: 208/120 VAC

• Frequency: 50 Hz

• Fuel Type: Diesel

• Wiring: 3 Phase, 4 Wire Plus 1 Ground

• The new diesel generator shall be fully compatible and connected to the new or existing ATS inside Building 121, Camp Zama. The Contractor is responsible for conducting pre-proposal survey(s) prior to quote submission to confirm compatibility of the proposed generator with the new or existing ATS. (Note: The previously advertised site visit has passed; no further site surveys will be arranged for prospective offerors.)

• New generator/engine shall come equipped with a water jacket heater to ensure the diesel engine is maintained at a temperature of 40–50 °C while in standby mode. To ensure reliable starting performance during Japan’s colder winter months in the Kanagawa area, the technical specifications sheet for the quote must outline heater sizing and output: a thermostatically controlled immersion or tank-style block heater (typically 1,000 W to 1,500 W) calibrated to sustain an engine coolant temperature profile of 40 °C to 50 °C in standby. Use of 40–50 °C as the standard setting is acceptable provided the installed heater actually maintains that range.

• New generator system shall have an output breaker local to the generator to ensure proper isolation for maintenance.

• New generator shall have Phase-to-phase and Phase-to-neutral power, voltage, and amperage indication gauges/meters affixed to the generator for operational trending. A standard three-phase four-wire (3φ4W) configuration displaying line-to-line voltage (R-S, S-T, T-R), phase voltage (R-N, S-N, T-N), current (R, S, T, N), and power is acceptable.

• New generator shall automatically adjust frequency based on load demands to maintain a tight operational tolerance between 49.5 – 50.5 Hz.

• New generator shall automatically adjust AVR based on load demands to maintain a tight operational tolerance of ±5 % of nameplate per ANSI C84.1 (198 V to 218 V and 114 V to 126 V). These bands are operating (steady-state) tolerances after the unit is online. Transient response during load application or motor starting is not separately specified beyond the requirement to start, reach rated voltage and frequency, and accept the full emergency load through the ATS within 40 seconds of a start signal. Address transient performance in the approved test plan.

• Japanese domestic standards (JIS, JEM, JEC, NEGA) may be used in addition to, not in place of, the stated performance requirements. The generator must still meet the SOW voltage/frequency bands, ATS compatibility, emissions, and other stated requirements. If Japanese standards are used, demonstrate equivalent or better performance.

• Environmental Compliance / Emissions: The emergency generator is exempt from Japanese emission limits and monitoring requirements under JEGS 2024 Chapter 4, Paragraph 4.8.4 (stationary backup/emergency power equipment). However, new stationary emergency diesel engines must still meet applicable U.S. EPA certification standards as outlined in JEGS 2024 Chapter 4, Table 4.11. Providing an EPA Tier 3 or Tier 4 certified engine (depending on engine specifications and manufacture year) is required.

• Noise: While Camp Zama may fall outside local municipal zoning maps, the project must comply with Japanese national noise standards as mandated by SOW Sections 5.2 and 10.1. The JEGS does not regulate ambient noise limits or specify site-boundary distances.

• Warranty: This contract shall include a minimum 1-year warranty provided either by the contractor or Original Equipment Manufacturer (OEM) that covers any repairs or replacement of premature failures of the system or its subcomponents under normal operations (parts and labor). Normal consumables and scheduled wear items are outside warranty unless they fail prematurely.

3.3. Existing Automatic Transfer Switches (ATS)

Building 121 contains two (2) existing Automatic Transfer Switches (ATS) for the emergency power system. These units are documented in the site survey files labeled “ATS and Generator” and “A.C Switch Board (ATS)” photographs. The contractor shall ensure the new generator is fully compatible with these existing or new ATS units. The contractor is directed to utilize the new or existing ATS wiring and configuration to the maximum extent possible to minimize project costs and timelines.

Panel identifiers appearing in this SOW and related drawings (L-M-2, L-M, and P-M) refer to the same or related switchboard locations. Additional information about existing ATS specifications, electrical/as-built drawings, and tank drawings is available from the Contracting Officer’s Representative (COR) / Government Representative (GR).

3.4. Existing Diesel Fuel Tank

The existing Stainless Steel Diesel Tank, renewed in 2008, is serviceable and shall be utilized for the new generator system. Technical drawings for this tank are available for contractor reference from the COR/GR. The contractor shall ensure compatibility and proper connection of the new generator to this existing fuel tank. Fuel connections are intended to be retained. Height adjustment of the tank mounting (by modifying the existing stand or adding a new one) is acceptable if required for generator compatibility, subject to inspection, testing, and certification of all connections as leak-free and safe.

4. DISPOSAL OF THE EXISTING OLD GENERATOR

The contractor shall be responsible for the disposal of the existing generator and waste utilizing off-base resources. The U.S. Government / DoD will not be responsible for nor assist with the disposal of waste generated from the replacement of the diesel generator.

4.1. Removal

The contractor shall remove the existing old generator from the site. The stainless-steel diesel tank (renewed 2008), fuel piping, and electrical wiring shall be retained if serviceable after inspection, testing, and certification. The intent is to remove the generator unit itself while keeping serviceable associated systems in place.

4.2. Disconnection

The contractor shall disconnect the existing old generator from the electrical systems and any other systems, including the ATS (Automatic Transfer Switch).

4.3. Drainage

The contractor shall drain and dispose of any remaining fuel, oil, and fluids in an environmentally responsible manner utilizing resources off-base.

4.4. Demolition / Disposal

The contractor shall demolish/dispose of the old generator and all materials, including metal, plastic, and other components, in accordance with Japanese regulations and laws at licensed facilities.

4.5. Documentation

The contractor shall provide documentation, including receipts, certificates of disposal, and photos, to confirm the disposal of the existing old generator. Acceptable documentation includes:

• Receipt from a licensed waste disposal facility

• Industrial waste management manifest (Japanese standard form)

• Certificate of disposal from the Japanese Ministry of the Environment (if applicable)

• Photos of the disposal process, including the removal of the generator and disposal of materials

5. ACQUISITION OF THE NEW 150 KVA DIESEL GENERATOR

The contractor shall supply and deliver a new 150 kVA diesel generator that meets the following specifications:

• Power rating: 150 kVA / 120 kW

• Voltage: 208/120 VAC

• Frequency: 50 Hz

• Fuel type: Diesel

5.1. Automatic Transfer Switch (ATS)

The new generator must be compatible with the new or existing ATS unit inside of Panel P-M / L-M (see as-built drawings available from COR/GR).

5.2. Compliance with Japanese and U.S. Regulations

The generator shall comply with all relevant Japanese regulations and laws, including those related to emissions (as clarified under Section 3.2 – EPA Tier compliance required even though emergency units are exempt from certain Japanese emission monitoring), noise, and safety. Japanese national noise standards apply.

6. INSTALLATION OF THE NEW DIESEL GENERATOR

The contractor shall install the new generator, including all necessary electrical connections, testing, and commissioning, in accordance with the following requirements:

6.1. Electrical connections

The contractor shall connect the new generator to the existing electrical system and ATS located in Panel L-M / L-M-2 / P-M. Contractors are permitted to reuse the existing electrical wires from the panel to the new generator provided they are not damaged and the wire connections reach without splicing. If the existing wire does not reach, the contractor shall supply new wires from the connection point in the panel to the new generator output breaker.

6.2. Mechanical connections

The contractor is encouraged and permitted to reuse the existing fuel line pipes, exhaust piping, and radiator exhaust ducts to minimize disruption to the building, subject to inspection, testing, and certification as fully functional, safe, and leak-free.

6.3. Testing

The contractor shall perform thorough testing of the new generator, including the minimum 8-hour load test utilizing site loads (approximately 30–40 kVA), supplemented by dummy load as needed, to ensure that it meets the performance requirements outlined in this SOW.

6.4. Commissioning

The contractor shall commission the new generator, including the ATS, to ensure that it is fully functional and meets the performance requirements outlined in this SOW.

6.5. Documentation

The contractor shall provide documentation, including testing and commissioning reports, to confirm that the new generator is fully functional and meets the performance requirements outlined in this SOW.

6.6. Power Outages

The contractor is required to submit any power outages for the installation at least 30 business days in advance so that tenants of the building have time to plan for the disruption. Power outages will be submitted via email to the POCs listed in this SOW.

6.7. Temporary Power

Because the existing backup generator is non-functional and will be removed, a temporary/backup generator shall be installed and remain available during the construction period until the new generator is fully commissioned and accepted.

7. PERFORMANCE REQUIREMENTS

The new generator shall meet the following performance requirements:

7.1. Power supply

The generator shall provide a stable and reliable power supply.

7.2. Voltage and Frequency Regulation

The generator shall maintain voltage regulation of ±5 % and frequency regulation between 49.5 – 50.5 Hz (steady-state, after the unit is online). The generator shall automatically adjust for variable loads without user intervention.

7.3. Response Time

System Response and Startup Time: The new generator system shall be designed, configured, and tested to automatically start, reach rated voltage and frequency, and accept the full emergency load through the Automatic Transfer Switch (ATS) within 40 seconds of receiving the start signal upon loss of utility power.

7.4. Automatic Transfer

The new generator shall be compatible with the new or existing transfer switch inside Panel L-M / L-M-2 / P-M. The contractor is responsible for confirming generator compatibility with the existing ATS prior to submitting a proposal during the solicitation period. (Further site surveys beyond the previously advertised visit will not be arranged.)

8. WARRANTY AND MAINTENANCE

The contractor shall provide a minimum of 1-year warranty for the new generator, including parts and labor, covering repairs or replacement of premature failures of the system or its subcomponents under normal operations. Normal consumables and scheduled wear items associated with normal use are not covered under warranty unless they fail prematurely.

8.1. On-Demand Repair and Replacement

The contractor shall repair or replace any faulty or damaged parts covered under warranty as needed.

8.2. Technical Support and Troubleshooting

The contractor shall provide technical support and troubleshooting to ensure that the generator is fully functional and meets the performance requirements outlined in this SOW.

Example warranty documentation: Warranty certificate; contact information for warranty support; repair and replacement reports.

9. DELIVERABLES

The contractor shall provide the following deliverables:

9.1. New 150 kVA Diesel Generator

The contractor shall deliver a new 150 kVA diesel generator that meets the specifications outlined in this SOW.

9.2. Installation and Testing

The contractor shall install and test the new generator, including all necessary electrical connections and testing (including the 8-hour load test).

9.3. Documentation

The contractor shall provide documentation, including testing and commissioning reports, as-built drawings, operation manuals, full replacement parts catalog/manufacturer drawings, and warranty documents, to confirm that the new generator is fully functional and meets the performance requirements outlined in this SOW. English-only documentation is acceptable for U.S.-made parts when Japanese versions are unavailable.

9.4. Training

The contractor shall provide training to 78th Signal and DoD personnel on the operation and maintenance of the new generator.

9.5. Warranty and Maintenance Support

The contractor shall provide warranty and maintenance support, including parts and labor, for a minimum of 1 year (consistent with Sections 3.2 and 8).

9.6. Construction Schedule

The contractor shall submit a detailed construction and installation schedule to the GR at least thirty (30) business days prior to the scheduled commencement of any on-site work, to allow sufficient time for affected tenants to coordinate and prepare for potential service disruptions. Offerors are advised that high production volume at certain generator factories may result in on-site delivery around April 2028 (manufacturing start late February to March 2028, approximately 560 days lead time). Contractors shall propose realistic schedules reflecting actual production capacity.

10. CONTRACTOR RESPONSIBILITIES

The contractor shall be responsible for:

10.1. Ensuring Compliance with Japanese and U.S. Regulations

The contractor shall ensure that the new generator and all work performed comply with all relevant Japanese regulations and laws, as well as applicable U.S. criteria. Where a conflict exists, the more stringent applicable U.S. or Japanese requirement applies. Section 13 references are governing contract criteria, not merely informational.

10.2. Providing a Safe Working Environment

The contractor shall provide a safe working environment for all personnel, including NEC personnel.

10.3. Maintaining Confidentiality and Security

The contractor shall maintain confidentiality and security of all 78th Signal information and assets.

10.4. Contractor Personnel Qualifications

The contractor or their sub-contractors shall ensure their employees have the following current and valid professional certifications to provide the required services under this contract. The contractor shall be responsible for ensuring their employees have these qualifications for the entire life of this contract. A copy of the certificates or permits must be submitted prior to contract award:

• 2nd Class Electrician License (第二種電気工事士)

• 3rd Class Chief Electrical Engineer License (第三種電気主任技術者)

• Specialized Electrical Construction Qualification for Emergency Backup Generator Construction (特殊電気工事資格:非常用予備発電装置工事)

10.5. Asbestos

Offerors shall not include bulk sampling, survey fees, or asbestos abatement costs in their base quotation. The Government is arranging asbestos testing and inspection separately under an independent contract. If asbestos removal is deemed necessary based on the Government’s independent testing, the Government plans to add a dedicated Contract Line Item (CLIN) via formal Amendment prior to award.

11. POINT OF CONTACTS

The points of contact for this project are:

• Derrick L. Lewis – Electronics Maintenance Supervisor – DSN: 315-262-3290

• Shaun S. Campbell – Logistics Manager – shaun.campbell5.civ@army.mil – DSN: 315-262-3272 Additional drawings, ATS specifications, and tank drawings referenced in this SOW may be obtained from the COR / GR.

12. ACCEPTANCE CRITERIA

The 78th Signal Battalion shall accept the new generator based on the following criteria:

• Compliance with specifications: The new generator shall meet the specifications outlined in this SOW (including exact 150 kVA / 120 kW rating, voltage, frequency, heater performance, metering, fan guard, and EPA Tier emissions compliance).

• Performance requirements: The new generator shall meet the performance requirements outlined in this SOW (voltage/frequency regulation, 40-second response time, ATS compatibility).

• Installation and testing: The new generator shall be properly installed and tested, including all necessary electrical connections, the minimum 8-hour load test, and temporary power continuity during construction.

• Documentation: The contractor shall provide documentation, including testing and commissioning reports, disposal manifests/receipts, as-built drawings, full parts catalogs, and warranty documents.

• Training completed for designated personnel.

• All environmental and safety requirements satisfied, including licensed disposal and required certifications.

13. REFERENCES

The documents listed below are governing safety, environmental, electrical, fuel, and emergency-power criteria for this contract. They are not merely for reference. Where a conflict exists, the more stringent applicable U.S. or Japanese requirement applies.

Document Number
Document Title
Engineering Manual 385-1-1
Safety and Health Requirements
AR 385-10
The Army Safety Program
AR 200-1
Environmental Protection and Enhancement
AR 385-40
Accident Reporting and Records
29 CFR Part 1926
OSHA Standards for Construction
OMA 214
Standard Technical Specifications for OMA Projects Korea
TIA-607-C
Generic Telecommunications Bonding and Grounding (Earthing)
TM 5-692
Maintenance of Mechanical and Electrical Equipment at C4ISR Facilities
NETCOM Reg 420-1
Site Power Coordinator Program
UFC 3-540-01
Engine-Driven Generator Systems for Prime and Standby Power
UFC 3-560-01
Safety / Operations / Management
UFC 3-600-01
Fire Protection Criteria
UFC 3-501-01
Electrical General Requirements
UFC 3-580-01
Telecommunications Interior Infrastructure Planning & Design
UFC 3-460-01
Petroleum Fuel Facilities
NFPA 1
Fire Code
NFPA 30
Flammable and Combustible Liquids Code
NFPA 37
Installation and Use of Stationary Combustion Engines and Gas Turbines
NFPA 70
National Electrical Code
NFPA 70E
Electrical Safety in the Workplace
NFPA 110
Emergency and Standby Power Systems
JEGS 2024
Japan Environmental Governing Standards (esp. Ch. 4 emissions & emergency generators)

14. ATTACHMENTS AND DOCUMENTATION

The drawings attached to or referenced by this SOW represent only a portion of the site layout. The contractor may request additional relevant drawings, schematics, or technical data (including ATS specifications, electrical/as-built drawings, and tank drawings for L-M-2 / L-M / P-M) through the designated Point of Contact (POC), COR, or GR during the solicitation and planning phases.

15. SUMMARY OF KEY CLARIFICATIONS FROM CONTRACTOR QUESTIONS

The following summarizes major clarifications incorporated into this updated SOW:

• Authorized disposal facilities = those licensed under Japanese law; industrial waste management manifest is acceptable documentation.

• Seismic calculations per Japanese standards are acceptable to validate anchoring methods.

• Existing 2008 stainless-steel diesel tank and serviceable fuel piping/wiring shall be retained and reused (after inspection/certification). Height adjustment of tank mounting is permitted if needed for compatibility.

• 8-hour load test utilizing site loads (~30–40 kVA) is required; generator must be 150 kVA / 120 kW (no oversized units). Fuel from existing tank may be used. Dummy load may supplement as needed.

• English-only documentation acceptable for U.S.-made parts; full manufacturer catalogs/drawings required (parts list alone insufficient).

• Water jacket heater: thermostatically controlled (typically 1,000–1,500 W) maintaining 40–50 °C in standby.

• Steady-state voltage/frequency bands apply after online; transients addressed in test plan. Japanese standards (JIS/JEM/JEC/NEGA) may supplement but not replace SOW performance requirements.

• Emergency generators are exempt from certain Japanese emission limits under JEGS, but must meet applicable U.S. EPA Tier 3 or Tier 4 certification.

• Japanese national noise standards apply.

• Temporary/backup generator required during construction period.

• Radiator fan guard required on new unit (OEM equivalent or better).

• Warranty standardized to minimum 1 year (parts & labor) for premature failures; consumables/scheduled wear excluded unless premature failure.

• Asbestos survey and abatement costs shall not be included in base quotes; Government will handle separately and may add CLIN if needed.

• No additional pre-quotation site surveys will be arranged.

• Long-lead manufacturing/delivery timelines (approx. 560 days / delivery ~April 2028) are acknowledged; realistic schedules required.

• Section 13 references are governing criteria; more stringent U.S. or Japanese requirement applies in case of conflict.

— End of Updated Statement of Work — 78th Signal Battalion – Camp Zama, Japan | Page 1 of 2