PWS.pdf
PDF 321 KB Posted
- Solicitation number
- FA520918Q0029
About this file
Performance Work Statement
View the file
Other files
| File | Type | Posted |
|---|---|---|
| FA520918P0161.pdf | ||
| FA520918Q0029.pdf | ||
| Notice_to_Offeror_(Pre-con_plus_site_visit).pdf | ||
| Policies_Procedures_for_Business_Ltr.pdf | ||
| PWS_FBO_29_Jun_18.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
PO No. FA5209-18-P-0161
Attachment 1
DEPARTMENT OF THE ARMY
UNITED STATES ARMY GARRISON JAPAN
DIRECTORATE OF PUBLIC WORKS
UNIT 45006 APO AP 96343-5006
PERFORMANCE WORK STATEMENT
FOR
INSPECTION, MAINTENANCE, AND REPAIR
OF
NATURAL GAS ENGINES, ELECTRICITY GENERATORS
AND
AUXILIARY EQUIPMENT,
IN THE CO-GENERATION PLANT,
FACILITY NO. 348,
CAMP ZAMA
(FEWR No. JF-60031-6J)
2 May 2018
Table of Contents
SECTION 1 Description of Services/General Information Page 2
SECTION 2 Services Summary Page 9
SECTION 3 Appendices Page 9
Appendix A1-1. Project Site / Location A1-1
Appendix A1-2. Plant Equipment A1.2-1 thru A1.2-12
Appendix A2-1. Annual Maintenance Schedule A2.1-1
Appendix A2-2. Minimum Required Work Elements A2.2-1 thru A2.2-10
Appendix A2-3. Flow Chart for Analysis of Corona Discharge A2-3
Appendix A3. List of Minimum Required Replacement Parts A3-1 thru A3-20
DESCRIPTION OF SERVICES/GENERAL INFORMATION
1.0. DESCRIPTION OF SERVICES. The contractor shall provide all necessary labor, personnel, supervision, management, tools, equipment, transportation, materials, and any other items or services necessary to perform inspection, maintenance, and repair services of dual fuel (natural gas and diesel oil) engines, electricity generators and other auxiliary equipment and systems in the Co-generation plant, facility number 348, Camp Zama (CZ). These services shall be performed in accordance with (IAW) this
Performance Work Statement (PWS), attached appendices, manufacturer standards, and commercial standards and practices.
1.1. INSPECTION AND MAINTENANCE.
1.1.1. The contractor shall accomplish annual maintenance services on dual fuel (natural gas and diesel oil) engines, electricity generators and auxiliary systems to ensure reliable, functional, and continuous operation. The project site/location is provided in Appendix A1-1, the listing of equipment in Appendix
A1-2, the listing of minimum required maintenance items and maintenance description in Appendix A2-2
& A2-3, and the minimum required replacement parts in Appendix A3. One engine shall remain operational at all times. Services requiring complete plant stoppage shall not occur without COR approval.
1.1.2. Annual Work Schedule. Using the provided annual maintenance schedule in Appendix A2-1, the contractor shall provide a detailed work schedule in both English and Japanese to the Contracting
Officer’s Representative (COR) for approval no later than 30 calendar days after contract award and then again 30 calendar days prior to the start of each option period. The schedule shall show the order in which the contractor proposes to perform maintenance services, the dates on which the contractor will start each work element, the scheduled date for completion of each element, and the number of man– hours needed for each work element. The contractor shall not deviate from the approved schedule without obtaining prior to approval by the COR.
1.1.3. Inspection and Maintenance Report. The contractor shall provide an annual inspection and maintenance report in both English and Japanese to the COR within 30 calendar days after the completion date. Such reports shall be submitted in booklet-type form, which shall include as a minimum the following information:
(1) Type of required maintenance
(2) Engine and generator number
(3) Actual running hours of the each engine
(4) Date work started
(5) Name of people who performed
(6) Equipment item checklist
(7) Description of each service performed. And item no. of each maintenance requirement
Appendix A2-2)
(8) Drawings/sketches for specified service areas
(9) Pictures/photographs such as deteriorated parts, replacement of new parts, etc
(10) Test and analyzed data results
(11) Recommendation for effective future maintenance programs/schedules and operation
(12) Date work completion
(13) Cost break-down for each maintenance provided, per maintenance item (labor cost/material cost)
(14) Signature of manufacturer’s representative
1.2. REPAIRS.
1.2.1. Repair work includes the reprocessing or replacement of parts or materials which have deteriorated and could not have been corrected through maintenance servicing. Repairs may be identified during routine maintenance service or as an on-call service. Repair work may also be required for correction of conditions and equipment that adversely affects the use of system for designated purpose as well as to restore any failed or failing components.
1.2.2. In the event that the contractor identifies needed repairs during maintenance service, the contractor shall immediately inform the COR and take temporary measures to ensure safety and to minimize/prevent further damages to the equipment. Additionally, the contractor shall submit a deficiency report in both English and Japanese to the COR of each installation within five (5) calendar days of the findings. The deficiency report shall include at a minimum of the following information:
(1) Location
(2) Finding date of failure
(3) Description of failure (pictures, drawings, etc.)
(4) Justification (what will happen if repair is not accomplished)
(5) Description of repair work
(6) Material list and man-hours for repair
(7) Proposed repair schedule
(8) Cost estimate for repair work
(9) Submission date of the report
(10) Contractor representative’s signature
1.2.3. If on-call service is required, the contractor shall dispatch an engineer within three (3) hours after notification from the COR during normal business operations. Other than normal duty hours, the contractor shall be available within eight (8) hours. The contractor shall report to the work location, survey, perform minor repairs, and restore the equipment and/or systems to the maximum extent practicable. If the repair is unable to be made at the time of the response, the contractor shall immediately take temporary measures to ensure safety and to minimize/prevent further damages to the systems as well as submit a deficiency report to the COR within five (5) calendar days.
1.2.4. If the estimated repair cost is below $5,000.00, or equivalent yen value, to include labor, material, equipment, and any costs associated with the on-call service (travel, labor, or other costs) if there was an on-call service, the COR will notify the contractor to immediately proceed with the repair. If the estimated repair exceeds $5,000.00, the contractor shall not commence until a notification is provided by the Contracting Officer. All repairs shall be invoiced under CLIN X002.
1.2.5. The contractor shall accomplish repair work IAW an approved schedule. If the repair work requires any utilities/operation outage, the contractor shall provide the detailed work schedule to include the outage plan, and obtain approval for the outage from all affected customers through the COR prior to shutting a system down.
1.2.6. Repair Report. The contractor shall prepare and submit a written report (2 copies in booklet-type form and 1 digital form) within ten (10) calendar days after the repair is accomplished. This report shall include:
(1) Date, time, and repair service performed, including step by step process
(2) Photographs showing deficiencies and repair performed
(3) Results of follow-on inspection, testing, and certification
(4) Repair material and labor cost, including man-hours
(5) Submission date of report with contractor’s representative’s signature
2.0. GENERAL INFORMATION.
2.1. CONTRACTOR PERSONNEL.
2.1.1. Contract Manager. The contractor shall provide a contract manager who shall be responsible for all requirements in this PWS. The name of this person and an alternate(s) who shall act for the contractor when the manager is absent, shall be designated in writing to the Contracting Officer (KO). The contract manager or alternate shall have full authority to act for the contractor on all matters relating to this contract. The contractor shall provide the contract manager’s names, addresses, and telephone numbers.
The contractor shall maintain a current listing of employees, providing updates as changes occur. The contract manager or alternate shall be proficient in English and have a good understanding of the requirements pertaining to this contract for interpretation and implementation of directives (written and oral), issued in English by the KO or COR. If the contract manager or alternate do not meet these requirements, the contractor shall provide a translator for them.
2.1.2. Contractor Employees. Contractor personnel shall be easily recognizable as contractor employees. This may be accomplished by wearing distinctive clothing bearing the name of the company or by wearing appropriate badges which contain the contractor’s company name and the employee’s name.
2.1.2.1. Personnel Qualifications. Contractor employees shall have the following valid and current professional certifications.
Engineering License for Electric Generation Systems of Private Use
(自家用発電設備専門技術者資格)
Individual being trained exclusively for Hanging Techniques by Hoists/Cranes
(玉掛技能講習修了)
Electrical License, 1st Class (電気工事士1種)
2.1.3. Removal of Contractor’s Employees. The contractor shall utilize only experienced, responsible and capable employees in the performance of this contract. The KO may require that the contractor remove any of his/her employees who endanger persons or property, or whose continued employment under this contract is inconsistent with the interests of the U.S. Government.
2.1.4. Other Country Nationals (OCN). The security forces on each base control entry to the base.
Under certain circumstances, the OCN might be denied entry. It is the contractor’s responsibility to coordinate with security forces at each base when there is a question about particular entry circumstances.
2.1.5. U.S. Government and/or Master Labor Contract Employees. The contractor shall not hire employees of the U.S. Government and/or Government of Japan Master Labor Contract employees in violation of the Procurement Integrity Act. See FAR 3.104. Furthermore, the contractor shall not employ any Department of Defense employee, either military or civilian, unless such person seeks and receives approval in accordance with Department of Defense 5500.7-R, Joint Ethics Regulation.”
2.1.6. Military Personnel. The contractor is cautioned that off-duty active military personnel hired under this contract may be subject to permanent change of station (PCS), change in duty hours, or deployment. Military Reservists and National Guard members may be subject to recall to active duty.
Abrupt absence of these personnel could adversely affect contractor’s ability to perform; however, their absence at any time shall not constitute an excuse for non-performance under this contract.
2.1.7. Roster. The contractor shall provide a complete roster of all personnel (including the contract manager and alternate contract manager) to the COR prior to start of performance. The roster must include all employee names, addresses, and telephone numbers. The contractor shall maintain a current listing of employees, providing updates as changes occur.
2.2. QUALITY CONTROL. The contractor shall utilize its existing quality control program to ensure the services are performed in accordance with commonly accepted commercial practices. The contractor shall develop and implement procedures to identify, prevent and ensure non-recurrence of defective services. At a minimum, the contractor shall develop quality control procedures addressing the areas identified in Section 2, Services Summary
2.3. QUALITY ASSURANCE. The Government will evaluate the contractor’s performance in accordance with the Quality Assurance Surveillance Plan (QASP) by appointing a COR to monitor performance to ensure services are received.
2.4. GOVERNMENT REMEDIES. The KO shall follow FAR 52.212-4, Contract Terms and
Conditions-Commercial Items, for the contractor’s failure to perform satisfactory services or failure to correct non-conforming services.
2.5. CONTRACTING OFFICER (KO) AUTHORITY. Only the KO has authority to enter into, administer, terminate or modify the terms and conditions herein. Any changes made by persons other than the KO will be considered an unauthorized commitment and subject to ratification actions in accordance with FAR 1.602-3.
2.6. CONTRACTING OFFICER’S REPRESENTATIVE (COR). The contractor shall coordinate all aspects of this requirement with the COR. Completed work shall be subject to inspection and acceptance by COR. This designation will be made in writing by the KO at the time of contract award, or prior to commencement of COR duty. The COR shall NOT direct or redirect any contractor action(s). This can only be done by the KO.
2.7. AVAILABILITY OF FACILITY.
2.7.1. Hours of Service. The contractor’s personnel will perform scheduled work on weekdays, Monday through Friday (exclusive of the U.S. Federal and other designated holidays listed below), during normal duty hours, 0800 - 1600 hours unless prior arrangements have been made with the COR(s).
2.7.2. Legal American Holidays and Other Designated Holidays.
American Holidays
1 January New Year’s Days
3rd Monday in January Martin Luther King Jr.’s Birthday
3rd Monday in February President’s Day
Last Monday in May Memorial Day
4th of July* Independence Day
1st Monday in September Labor Day
2nd Monday in October Columbus Day
11 November* Veterans Day
4th Thursday in November Thanksgiving Day
25 December* Christmas Day
Other Designated Holidays
1, 2 & 3 January New Year’s Days
11 August Mountain Day
29, 30 & 31 December Year End Days
*Holidays falling on a Saturday will be observed on the preceding Friday, Holidays falling on a
Sunday will be observed on the following Monday.
2.7.3. Arrangements of the Performance Time. Should the contractor decide to perform any of the required services before or after normal duty hours, the contractor will request approval prior to performance from the COR and shall do so at no additional cost to the Government.
2.8. SECURITY AND SAFETY REQUIREMENTS.
2.8.1. Installation Base Passes. The U.S. Government will issue all required Installation/Base Passes and Controlled Area Badges to contractor personnel at no cost to the contractor. Vehicle insurance certificates are required to obtain Base Passes and must cover the automobile liability insurance in the types and minimum amounts of (a) Bodily Injury - ¥30,000,000 per person per occurrence, in addition to the Japanese Compulsory Insurance (JCI), and (b) Property Damage - ¥3,000,000 per occurrence. The prime contractor shall be responsible for all passes issued to his/her own or subcontractor’s employees under this contract. The contractor shall return all applicable passes upon termination of employment or completion of this contract to the Japanese Pass Section, and a certificate of receipt shall be obtained.
NOTE: Contractor personnel are required to comply with U.S. Army Regulation 190-5 for personnel pass requirements. Contractors are also required to comply with U.S. Army Garrison Japan Regulation
190-13 for vehicle pass requirements. These regulations are available for the selected contractor’s review upon personnel and/or vehicle pass issuance.
2.8.2 Security Requirements. The contractor shall ensure each employee obtains all the required passes and identification items for access to U.S. Government’s installations. These items are issued by the
Security Forces Pass and Registration Section. The contractor and employees shall return identification cards to Security Forces within 24 hours of termination or completion of this contract. All other
Government identification for terminated employees shall be returned to the KO within 24 hours of termination.
2.8.3. Off Limit Signs. The contractor shall provide warning and/or ”OFF LIMITS” signs in both
English and Japanese and post them at the entrances of jobsite, and barricades around the jobsite while the equipment and/or systems are being serviced. The contractor shall control all personnel desiring access into jobsite areas when work is in progress.
2.8.4. Photography Permission. The contractor shall obtain COR approval prior to commencing any photography.
2.8.5. Reports of Damages, Destruction, Injury, or Death
2.8.5.1. The contractor shall report all incidents of damage or destruction to property, or personal injury or death to any person, arising out of and during the performance of this contract. The term “property” includes equipment, freight, or property of any type, whether Government owned or not. The term
“contractor” includes the contractor, its agents, servants or employees.
2.8.5.2. The contractor shall submit these reports to the KO through the COR as follows:
(a) A preliminary report shall be made as soon as practicable after the time the incident occurs. The report may be either verbal or facsimile.
(b) A complete written report shall be submitted within 4 days (96 hours) after occurrence of the incident. A copy of this report shall be furnished to the COR.
2.8.6. Security Danger Warning, Accident Prevention, Fire Prevention and Fire Protection
Requirements. The contractor shall comply with all pertinent requirements of the U.S. Army and
USAG-J Fire Protection and Safety Regulations or Laws of Japan, whichever is more stringent, to insure compliance by all subcontractors.
2.8.7. Accident Prevention Plan and a Job Hazard Analysis. The contractor shall not commence work at the job site until an Accident Prevention Plan and a Job Hazard Analysis are submitted for review and approved by the COR. The contractor is responsible for reviewing section 1 and 34 of EM 385-1-1, the US Army Corps of Engineers’ Safety and Health Requirements Manual, http://140.194.76.129/publications/eng-manuals/em385-1-1/2008_English/toc.html.
2.8.8. Hazardous Materials. All hazardous materials must be contained and stored in the appropriate storage containers and/or cabinets. The contractor shall immediately report spills or release of hazardous materials to the COR. The contractor shall be liable for containment and environmental clean-up of spill or release of such substance. The contractor shall comply with municipal environmental laws to protect the health and safety of employees/residents and minimize or eliminate environmental pollution. The contractor shall follow manufacturer’s guidelines and professional recommendations for control of humidity, temperature, cleanliness, and materials handling. The contractor shall comply with environmental and hazardous materials storage and handling requirements and maintain current Safety
Data Sheets (SDS). Upon request of the COR, the contractor shall submit the SDS to the COR.
2.8.9. Environmental Regulations. The contractor shall comply with all U.S. Government and
Japanese environmental laws (whichever are most stringent) to protect the health and safety of employees/residents, and preserve the local and global environment. The contractor shall comply with the Japan Environmental Governing Standards (JEGS) and shall minimize or eliminate environmental pollution and energy/utility waste.
2.8.10. Environmental and Hazardous Material Handling. The contractor shall comply with the current Japan Environmental Governing Standards (JEGS) to protect the health and safety of employees/residents and minimize or eliminate environmental pollution. The Contractor shall follow the installation Spill Prevention Control and Countermeasure (SPCC) Plan and Oil and Hazardous Substance
(OHS) pollution Contingency Plan in case of a spill or release of POL and/or hazardous substances. The
Contractor shall immediately notify Fire and Emergency Services, Directorate of Emergency Services, U.S. Army Garrison Japan of any spills that occur on the installation through the Emergency Phone
Number. The contractor will be liable for containment and clean-up of the site.
2.8.11. Delivery and Storage of Materials. All materials delivered and placed in storage shall be protected from the weather, humidity and temperature variations, dirt and dust, or other contaminants by the contractor.
http://140.194.76.129/publications/eng-manuals/em385-1-1/2008_English/toc.html
2.8.12. Disposal of Materials. All debris and unserviceable materials generated under this contract such as industrial waste, non-recyclable materials and equipment/material not listed on hand-receipts shall be disposed of off-base by the contractor in accordance with the laws of Japan. Hand receipt items require turn-in action by the contractor when the listed items have to be replaced.
2.8.13. Responsibility for Damages. Any damages caused to U.S. Government property during the course of performing this contract shall be restored, replaced and/or repaired to its original condition at no additional cost to the U.S. Government.
2.8.14. Temporary Work Stoppage. In the event the Garrison Commander requests a temporary shutdown of the facility, the contractor will be notified in writing by the KO. Any Government caused delays as a result of a temporary shutdown that may require an adjustment to the contract will be coordinated through the KO.
2.9. CLEANLINESS. The contractor is responsible for cleanliness of the service areas. This includes, but is not limited to, washing, sweeping, dusting and other janitorial services necessary to maintain the area in a clean and sanitary condition. The contractor shall furnish such supplies as required.
2.10. COMMERCIAL WARRANTY. The contractor shall provide the Government with their commercial warranty. The Government shall receive the same warranty service as the contractor’s most favored customers. If the services fail to be performed or otherwise fail due to workmanship or materials, the contractor shall correct the affected area(s) at no additional cost to the U.S. Government. The
Government reserves the right to reject any unserviceable or substandard item and to require replacement with a serviceable like item or acceptable quality item or to require full credit for the item.
2.11. CONSERVATION OF UTILITIES. The contractor shall instruct employees in utility conservation practices. The contractor shall be responsible for operating under conditions, which preclude the waste of utilities. The contractor shall comply with additional energy policies upon notification by the KO.
2.12. CONTRACT MANPOWER REPORTING. The contractor shall report ALL labor hours
(including subcontractor labor hours) required for the performance of services provided under this contract via a secure data collection site. The contractor is required to completely fill in all required data fields at https://armycmra.dmdc.osd.mil/default.aspx?ReturnUrl=%2f
2.12.1. Reporting inputs will be for the labor executed during the period of performance for each
Government fiscal year (FY), which runs 1 October through 30 September. While inputs may be reported any time during the FY, all data shall be reported no later than 31 October each calendar year.
Contractors may direct questions to the CMRA help desk.
2.12.2. Information from the secure web site is considered to be proprietary in nature when the contract number and contractor identity are associated with the direct labor hours and direct labor dollars. At no time will any data be released to the public with the contractor name and contract number associated with the data.
https://armycmra.dmdc.osd.mil/default.aspx?ReturnUrl=%2f
SECTION 2
SERVICES SUMMARY
The following Services Summary (SS) identifies the performance objectives and performance thresholds for critical tasks associated with providing support services for this requirement. The performance threshold briefly describes the minimum acceptable levels of service required for each requirement.
These thresholds are critical to mission success.
SS Number and
Performance Objective PWS Paragraph Performance Threshold
Method of
Assessment
SS 1. Inspection and
Maintenance:
Completion of items listed in Appendix A1, A2, and
A3
Para 1.1.1. One (1) defect allowed 100% Inspection
SS #2. Repairs:
Timely completion of repair work
Para 1.2. No defects are allowed 100% Inspection
SS #3. Repairs:
Completion of repair IAW approved deficiency report
Para 1.2.2.
One (1) defect allowed per repair (correctable) 100% Inspection
SS #4. Submittals:
Timely and complete submission of required documents
Para 1.1.2, 1.1.3., &
1.2.6
(i) Annual Schedule: No delay allowed
(ii) Reports: Two (2) defects allowed per year
100% Inspection
SECTION 3
APPENDICES
Appendix A1-1. Project Site / Location A1-1
Appendix A1-2. Plant Equipment A1.2-1 thru A1.2-12
Appendix A2-1. Annual Maintenance Schedule A2.1-1
Appendix A2-2. Minimum Required Work Elements A2.2-1 thru A2.2-10
Appendix A2-3. Flow Chart for Analysis of Corona Discharge A2-3
Appendix A3. List of Minimum Required Replacement Parts A3-1 thru A3-20