Performance-based Work Statement
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Amend_01.pdf | ||
| PWS_4_Aug.pdf | ||
| Atch_3_(PPI_List).pdf | ||
| Goverment_Policy_Ltr_-_Lt_Col_Kapise.pdf | ||
| Notice_to_Offeror.pdf | ||
| 15-T-0130.pdf | ||
| Atach_2_Form66-YS69.pdf | ||
| Atch_4_Survey.pdf | ||
| Copy_of_Gate_Pass_Request_Form_New.xlsx | XLSX spreadsheet |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
FA5209-15-T-0130
Attachment 1
PERFORMANCE-BASED WORK STATEMENT
FOR
ERECTION, RENTAL AND DISMANTLING OF
PREFABRICATED FACILITIES
AT CAMP ITAMI,
JAPAN
YS-16-69 (CCF, CP AREA/DFAC)
(FFWR No. HU-00011-5J)
18 July 2015
TABLE OF CONTENTS
SECTION TITLE PAGE (S)
1 Description of Services/General Information 3 - 12
2 Services Summary 12 - 13
3 Government Furnished Property and/or Services 13
4 Appendices 14 - 15
SECTION 1
DESCRIPTION OF SERVICES/GENERAL INFORMATION
1. DESCRIPTION OF SERVICES. The contractor shall provide all personnel, equipment, tools, materials, supervision and other items and services necessary to perform the following work in accordance with drawings provided at YS-16-69
Engineering Drawings, Base Camp, Camp Itami:
(a) The erection, rental, maintenance, heating and dismantling of four (4)
Prefabricated Buildings to be used as a temporary Mission Training Complex (also referred to as Central Control Facility) and two (2) entry control access points for the
Main Command Post (CP) area:
1. Prefab No. 1: 9m x 64.8m, 2-Story for Central Control Facility (Sheet S-03)
2. Prefab No. 2: 9m x 75m, 2-Story for Central Control Facility (Sheet S-04)
3/4. Prefab No. 3&4: 3.6m x 3.6m, 1-Story for access control points at Main
Command Post Area (referenced drawings Sheets S-06/7)
(b) The erection, rental, noise abatement testing, maintenance and dismantling of an electrical power distribution system(s) sufficient to fully power or supplement the following facilities:
1. Prefabricated Buildings
2. Post Gymnasium BLDG #205
3. Main Command Post Area
4. Camp Dining Facility, BLDG #195
All facilities, equipment and material will be furnished to the U.S. Government on a rental basis at Camp Itami, Hyogo, Japan Ground Self Defense Force (JGSDF), Japan.
1.1. PRINCIPAL FEATURES OF WORK: The contractor shall perform the following work:
(a) The contractor shall provide rental services for four (4) prefabricated buildings, specified room heating and an electrical power distribution system that in addition to prefabricated buildings includes the Main Command Post and Dining Facility.
(b) The contractor shall erect and install all required equipment, materials, and service in accordance with (IAW) this Performance-based Work Statement (PWS).
(c) The contractor shall provide maintenance/repair services for the duration of contract performance.
(d) The contractor shall dismantle all items and restore the site to an acceptable condition.
1.2. PERFORMANCE PERIOD: The performance period of this contract is 10
September 2015 (or date of award if later) through 31 January 2016.
1.3. DELIVERY:
(a) Erection: The contractor shall deliver and commence erection on 10 September
2015 (or date of contract award if later) and complete work by 12 November 2015.
Generator installation with noise abatement testing and verified compliance with local ordinance shall be completed by 12 November 2015.
(b) Rental: Prefabricated building and Generator rental period shall be from 15
November to 15 December 2015. 13-14 November will allow for final inspection/testing and correction of any noted shortcomings. Customer will occupy facilities and initiate set-up on 15 November and complete de-installation of equipment by 15 December.
(c) Dismantling: The contractor shall dismantle the prefabricated buildings, electrical power distribution system, heaters and other provided equipment no later than 31 January
2016. Dismantling includes restoration of all worksites and facilities to an acceptable and reasonable condition. The start date and schedule for dismantling/restoration work will be coordinated with the Contracting Officer Representative (COR) prior to commencement of work.
1.4. PREFABRICATED BUILDING: Prefabricated buildings shall be “Kumitate-
Shiki” type buildings using ”V” shape 0.8mm thick (H= 88mm) light-gage steel.
Minimum section modulus (Zx) is 22.42 cm³/cm with flat-type ceilings, insulated walls, windows, fixed and/or sliding doors, floor panels, access stairways and door canopies.
Exterior building buttress support and outer stairways shall be provided for two-story prefabricated buildings. Erection standards for each building shall be IAW guidelines established by the manufacturer for the intended purpose of use.
1.4.1. Wall panels shall be 40 mm (minimum) thick and consist of an insulation core faced on both sides with approximately 0.27 mm metal sheets.
1.4.2. Two (2) 1800mm interior wooden stairways with handrails and two (2) 750mm steel exterior stairways with inside handrails, sidewalls and plastic corrugated sheet roofing will be constructed at both ends of each two-story building.
1.4.3. Skirt boards (12mm thick plywood) between building base and ground shall be provided for each building.
1.4.4. Baffles and vertical walls shall be provided at each interior stairway to prevent heat loss from the lower floors.
1.4.5. Plastic corrugated sheet canopy, exterior lighting, wooden steps with doormat and stairs shall be provided at each exterior entrance by the contractor.
1.4.6. Exterior entrance doors shall be aluminum panel sliding doors (2000 mm height) and shall include a lock device.
1.4.7. All window glass shall be frosted.
Note: The contractor shall provide access holes for network/electrical cabling in walls, ceiling panels and floorboards throughout prefabricated buildings. COR will direct access-hole location and size.
1.4.8. Provide floor to ceiling partition walls with lockable sliding doors in Prefabricated
Buildings number one and two. Wall thickness should be no less than 90 mm.
1.4.9. Provide kerosene forced flue (FF) type heaters as follows:
(a) Prefabricated Building No. 1, provide six (6) heaters with a capacity of 13,700
Kcal/H and two (2) heaters with a capacity of 4,300 Kcal/H; heaters should be arrayed with two (2) small and three (3) large on first floor and three (3) large on second floor.
(b) Prefabricated Building No. 2 provide eight (8) heaters with a capacity of 13,700
Kcal/H four (4) per floor.
(c) Prefabricated Building’s No. 3&4, one (1) heater with 4,300 Kcal/H capacity per building.
In addition to heating units, provide external fuel tanks (one for each heater) with a
490-liter capacity and fume exhaust system. Fuel pumps (fuel servers) shall be installed on the top-floor of buildings with two floors. Fuel reservoirs must be positioned to avoid foot and vehicle traffic; a fuel-spill container shall be provided at the base of each fuel tank to prevent ground contamination in the event of leakage.
Note: Heater fuel is not included in this contract beyond that required for the initial operation test.
1.4.10. Provide a noise reduction fence or barrier with access doors around electrical generator plants. The soundproof barrier/fence shall consist of a stable foundation, fence with soundproofing material and support structure to ensure stability and safety. Noise reduction barriers will be constructed IAW procedures specified by the manufacturer.
Before delivery, the contractor will perform sound abatement tests that comply with local ordinance and regulation. In the event of test failure, the contractor will modify the structure as required to achieve minimum noise abatement standards.
1.4.10.1. Noise Standards (Not to Exceed) in Weighted Decibels (IAW Itami Master
Plan/Sound Proof Handbook)
(a) 2200-0600: 45dBA
(b) 0600-0800: 50dBA
(c) 0800-1800: 60dBA
(d) 1800-2200: 50dBA
1.5. ELECTRICAL SYSTEM ERECTION AND MAINTENANCE OF
PREFABRICATED BUILDINGS AND OTHER FACILITIES: Provide an electrical power distribution system for the following buildings and facilities: (1) temporary prefabricated buildings; (2), JGSDF Bldg 195 (DFAC); (3), JGSDF Bldg 205
(Gymnasium); (4), U.S. provided Deployable Shelter (DRASH) adjacent to Bldg No.
233; (5), U.S. tent area located east of Bldg No. 209 and (6), Main Command Post area.
This electrical system shall be completed with cable wiring, panel boards, fluorescent lighting, wall switches, receptacles and bracket lights at entrances IAW drawings and paragraph 1.8. of this Performance-Based Work Statement (PWS).
1.5.1. Provide nine (9) generator plants with two (2) generators each as follows:
(1), Diesel engine generator 270KVA, 3PH-4W-120/208V, 60Hz.
(2), Diesel engine generator 190KVA, 3PH-4W-120/208V, 60Hz.
(3), Diesel engine generator 190KVA, 3PH-4W-120/208V, 60Hz.
(4), Diesel engine generator 150KVA, 3PH-4W-120/208V, 60Hz.
(5), Diesel engine generator 150KVA, 1PH-3W-105/210V, 60Hz.
(6), Diesel engine generator 150KVA, 1PH-3W-105/210V, 60Hz.
(7), Diesel engine generator 270KVA, 3PH-4W-120/208V, 60Hz.
(8), Diesel engine generator 270KVA, 3PH-4W-120/208V, 60Hz.
(9), Diesel engine generator 125KVA, 3PH-4W-120/208V, 60Hz.
All power plants must be serviced by two (2) generators for a total of eighteen (18); one generator for continuous operation while its alternate remains in reserve. Generators will be enclosed and/or sound-proofed consistent with previously listed local ordinance. Fuel tanks with a minimum capacity of 490 liters and individual spillage containers will be provided for each diesel engine generator.
1.5.2. Provide and install electrical distribution wiring, fixtures, outlets, cables, wiring, accessories, and molded case circuit breakers.
Note: Fuel and lubricants shall be provided by the contractor for all generators throughout the rental period; the contractor will leave fuel/oil delivery slips with the COR after each delivery.
1.5.3. Provide suspension wires in work tents sufficient to attach fluorescent lighting systems.
1.5.4. Electrical system shall be installed in prefabricated buildings, existing buildings and the tents with cable wiring, panel boards, fluorescent lighting (with suspension wire for tents), wall switches, receptacles and bracket lights at entrances.
1.5.5. All 120V power drops will be painted red for easy identification.
1.5.6. Electrical power and generator maintenance/repair service shall be provided by the contractor 24-hours per day, 7-days per week, to provide continuous and uninterrupted power throughout the rental period specified at paragraph 1.3(b).
1.5.7. Maintenance and repair service for all the electrical facilities, generators, power distribution system, electrical accessories, fluorescent lights and other light fixtures shall be provided by the contractor on an “on-call” basis. The contractor will provide 24-hour maintenance coverage IAW paragraph 1.5.6. of this work statement.
Note pertaining to paragraph 1.5.7: At no time will the contractor accept requests to add, modify, repair or extend electrical power or services from anyone other than the
COR; neither the Japan Ground Self-Defense Force (JGSDF), their representatives or visiting U.S. Military forces are authorized to request new work. All requests for contract modification will be noted and reported to the COR. The contractor will provide
24-hour maintenance coverage IAW paragraph 1.5.6. of this PWS.
1.6. WORK SHED: The contractor shall provide a well-lighted, heated, fully-enclosed workspace with external portable latrine sufficient for an on-site engineer to provide electrical service and maintenance 24-hours per day, 7-days per week. The contractor shall provide the equipment and materials required for all maintenance/repair work. Shed location will be coordinated through the COR and provided to the contractor prior to contract performance; the COR will provide suitable ground space in close proximity to the work site but not to exceed twenty (20) square meters.
1.7. ENGINEERING SUPPORT: The contractor shall provide an engineer at the job site 24-hours a day, 7-days per week to offer maintenance and repair services for contracted generators and power distribution system. On-site maintenance service will be provided without delay or interruption and commence 15 November 2015 at 8:30 and conclude 15 December 2015 at 17:00 (rental period). The engineer(s) provided shall be well-qualified and licensed/certified to maintain and repair electrical generators, power distribution systems and all other contractor-provided equipment.
1.8. ELECTRICAL WORK SPECIFICATION: Electrical work shall meet or exceed the following specifications.
1.8.1. Code Compliance: Electrical installation shall comply with all requirements specified by the National Fire Protection Association (NFPA), No. 70, National Electrical
Code, Chapter 5, Special Occupancies, Article 590, ‘Temporary Installations’ and the
Japan Electric Association (JEAC).
(NFPA): http://www.nfpa.org/index.asp?rp=t
(JEAC): http://www.denki.or.jp/pub/jeacjeag.html
1.8.2. General Installation Requirements: All materials and equipment shall be installed IAW approved codes, standards and manufacturer recommendations.
1.8.3. Grounding: Ground rods and wire conductors for equipment grounding shall be installed IAW Article 590 of National Electrical Code and Japan Electric Association
(JEAC) standards.
1.8.4. Operating Tests: Upon installation of electrical generators and power distribution systems, the contractor shall conduct operating tests to verify serviceability prior to delivery. Equipment tests shall be performed in the presence of the COR. The contractor shall furnish instruments, materials and personnel required for the test.
1.8.5. Ground-Resistance Measurements: Ground-resistance measurements shall be certified by the contractor and provided to the COR upon completion of electrical system installation; data provided will include the measured ground resistance of each grounding rod, the rod’s location, grounding system used, soil conditions and noted resistance at the time of measurement. Ground-resistance measurements shall be made in normal dry weather, not less than 48-hours after rainfall, with the underground test location isolated from other grounding rods. If applicable, the contractor shall dig a hole and shall remove frozen soil to make dry conditions for the measurements. The ground resistance shall be measured using the ‘fall-of-potential’ method before the operating test and shall not exceed 25 ohms (10 ohms for the Command Post area) when measured in normal dry conditions.
1.8.6. Facility Acceptance Inspection: The Government will conduct a facility acceptance inspection with the COR on 12 Nov 2015, the date is subject to change.
1.9. SUBMITTALS: The contractor shall provide submittals to the COR for approval for each item listed in sub-paragraph 1.9.1. within the specified number of days following contract award.
1.9.1. Descriptive data for materials identified below shall be submitted to the COR within the number of days specified following contract award. Descriptive information shall be supported by catalogs, certificates of compliance or other data published by the manufacturer to demonstrate conformance with specification requirements prior to installation.
a. Building shop drawings: (Provide the COR within seven (7) business days)
(1) Plans for prefabricated building with bracing locations.
(2) Plans for generator sound proofing enclosure.
b. Utility equipment: (Provide the COR within ten (10) business days)
(1) FF type heaters, capacity, 13,700 Kcal/H/4,300 Kcal/H.
(2) 490-liter fuel reservoirs with spillage containers.
(3) Fuel lift pump (Fuel server).
c. Electrical materials and equipment: (Provide the COR within twelve (12) business days)
(1) Cables.
(2) Light fixtures.
(3) Enclosed circuit breakers
(4) Panel board.
(5) Generator.
d. Electrical generator noise abatement tests: Provide completed noise abatement testing certifying compliance with local ordinance to the COR by 12 November
2015; retesting prompted by conflicting or questionable results and any required modifications to the noise abatement enclosure materials or design, must be completed no later than 14 November 2015.
1.10. DISPOSAL OF MATERIALS: The contractor shall remove all debris and unsalvageable materials generated at the work site IAW local Japanese law. No debris will be disposed of on the JGSDF installation.
1.11. REMOVAL AND RESTORATION: After removal of prefabricated buildings, the contractor will repair ground surface damage caused by temporary construction to its
“as was” or original condition.
1.12. GENERAL INFORMATION:
1.12.1. Qualification
1.12.1.1. Contractor’s Qualification: The contractor shall be responsible for obtaining all necessary licenses and permits to perform the work described by this PWS.
1.12.1.2. Contract Manager’s Qualification: The Contract Manager and/or alternate(s) shall possess at least 2nd Category Electrical Engineer’s Licenses (第二種電気工事士) to supervise the work site.
1.12.2. Contractor Personnel:
1.12.2.1. Contract Manager: The contractor shall provide a contract manager who shall be responsible for the work. The name of this person and an alternate(s) who shall act for the contractor when the manager is absent, shall be designated in writing to the
KO. The contract manager or alternate shall have full authority to act for the contractor on all matters relating to this contract. The contractor shall provide the contract manager’s names, addresses, and telephone numbers. The contractor shall maintain a current listing of employees, providing updates as changes occur.
1.12.2.2. Contract Manager Availability: The contract manager or alternate shall be physically present or readily available throughout the contract period. The contract manager should be available for meetings at the worksite within one (1) hour of a COR request for emergency service or maintenance and two (2) hours for routine administrative matters.
1.12.2.3. The contract manager or alternate shall be proficient in English and have a good understanding of the requirements pertaining to this contract for interpretation and implementation of directives (written and oral), issued in English by the KO or COR. If the contract manager or alternate do not meet these requirements, the contractor shall provide a translator for them.
1.12.2.4. Contractor Employees: Contractor employees shall be easily recognized either by wearing distinctive clothing bearing the company’s name or logo or by identification badges that include the employee’s name and contracted company.
1.12.2.5. Removal of Contractor’s Employees: The contractor shall utilize only experienced, responsible and capable employees in the performance of this contract. The
KO may require that the contractor remove from the Government work site, any employee who endangers persons or property, or whose continued employment under this contract is inconsistent with the interests of military security.
1.12.2.6. Third Country Nationals (TCN): JGSDF Security Forces strictly control access to bases and facilities. Contractors are advised to obtain permission for third-country entry before initiation of contract work. Installation Commander’s may deny third-country access without prior notice; exceptions to access restrictions must be coordinated directly with the JGSDF installation.
1.12.2.7. U.S. Government or Japanese National Employee: The contractor shall not hire employees of the United States Government and/or Master Labor Contract employees in violation of the Procurement Integrity Act. See Federal Acquisition
Regulations, Section 3.104. Further, the contractor shall not employ any U.S.
Department of Defense employee, either military or civilian, unless such person seeks and receives approval IAW Department of Defense Joint Ethics Regulation, 5500.7-R.
1.12.2.8. Quality Control: The contractor shall develop and maintain a quality control program to ensure the services are performed IAW commonly accepted commercial practices. The contractor shall develop and implement procedures to identify, prevent and ensure non-recurrence of defective services. At a minimum, the contractor shall develop quality control procedures addressing the areas identified in paragraph 2, Services Summary.
1.12.3. Quality Assurance: The government will evaluate the contractor’s performance
IAW the Quality Assurance Surveillance Plan (QASP) by appointing a COR to monitor performance to ensure services are received.
1.12.4. Government Remedies: The KO will follow FAR 52.212-4, ‘Contract Terms and Conditions - Commercial Items’ for a contractor’s failure to perform satisfactorily or failure correct non-conforming services.
1.12.5. Contracting Officer’s Representative (COR): The contractor shall coordinate all aspects of this project with the COR. Completed work shall be subject to inspection and acceptance by the COR. The COR shall NOT direct or redirect any contractor action(s). This can only be done by the KO. The COR shall NOT Advise the contractor
HOW to perform but rather WHAT is required per this PWS and contract.
1.12.6. Contracting Officer (KO) Authority: Only the KO has authority to enter into, administer, terminate or modify the terms and conditions herein. Any changes made by persons other than the KO will be considered an Unauthorized Commitment and subject to Ratification Actions IAW the Federal Acquisition Regulation part 1.602-3.
1.12.7. Hours of Operation: The work site will be made available to the contractor for erection and dismantling of buildings and other facilities, and for repair and maintenance of buildings and utilities systems 24-hours per day, 7-days per week, including Japanese and U.S. holidays. Deviation from this requirement may be made with the approval of the COR.
1.12.8. Security Requirements:
1.12.8.1. The contractor shall ensure each employee obtains required access passes and identification items for entry to the JGSDF work site. The contractor shall be responsible for all controlled-area pass or badges issued to his employees under this contract IAW
JGSDF regulations. The Contractor shall return employee identification cards to JGSDF security forces within 24-hours of work termination. Management of access passes and entry approval remains the sole responsibility of JGSDF security forces. Questions concerning entry policy must be addressed directly to the installation security office.
1.12.9. Reports of Damage, Destruction, Injury, or Death:
1.12.9.1. The contractor shall report all incidents of damage, destruction of property, personal injury or death of any person, arising out of and during the performance of this contract. For the purposes of this clause, the term “property” includes equipment, freight, or property of any type, whether Government owned or not. The term “contractor” includes the contractor, its agents, servants or employees.
1.12.9.2. The contractor shall submit these reports to the KO through the COR as follows:
(1) A preliminary report shall be made as soon as practicable after the time the incident occurs. Report may be either verbal or facsimile.
(2) A complete written report shall be submitted within 96 hours after occurrence of the incident. A copy of this report shall be furnished to the COR.
1.12.10. Contractor Manpower Reporting: The Office of the Assistant Secretary of the Army (Manpower & Reserve Affairs) operates and maintains a secure Army data collection site where the contractor shall report ALL contractor manpower (including subcontractor manpower) required for performance of this contract. The contractor is required to completely fill in all the information in the format using the following web address https://cmra.army.mil/. The required information includes: (1) Contracting office, Contracting Officer, Contracting Officer’s Technical Representative; (2) Contract number, including task and delivery order number; (3) Beginning and ending dates covered by reporting period; (4) Contractor name, address, phone number, e-mail address, identity of contractor employee entering data; (5) Estimated direct labor hours (including sub-contractors); (8) Predominant Federal Service Code (FSC) reflecting services provided by contractor (and separate predominant FSC for each sub-contractor if different); (9) Estimated data collection cost; (10) Organizational title associated with the
Unit Identification Code (UIC) for the Army Requiring Activity (the Army Requiring
Activity is responsible for providing the contractor with its UIC for the purposes of reporting this information); (11) Locations where contractor and sub-contractors perform the work (specified by zip code in the United States and the nearest city, country, when in an overseas location, using standardized nomenclature provided on website); (12)
Presence of deployment or contingency contract language; and (13) Number of contractor and sub-contractor employees deployed in theater this reporting period (by country). As part of its submission, the contractor shall also provide the estimated total cost (if any) incurred to comply with this reporting requirement. Reporting period will be the period of performance not to exceed 12 months ending September 30 of each government fiscal year and must be reported by 31 October of each calendar year. Contractors may use a direct XML data transfer to the database server or fill in the fields on the website. The
XML direct transfer is a format for transferring files from a contractor’s systems to the secure website without the need for separate data entries for each required data element at the website. The specific formats for the XML direct transfer may be downloaded from the web site.
SECTION 2
SERVICE SUMMARY
2. SERVICES SUMMARY. The following Services Summary identifies the performance objectives and performance thresholds for critical tasks associated with providing support services for this requirement. The performance threshold briefly describes the minimum acceptable levels of service required for each requirement. These thresholds are critical to mission success. As a general rule, defects are categorized as follows: (1), ‘Major’ deficiencies that present significant safety or health hazards to customer or contract employees (e.g. improperly braced or attached exterior stairs) and
(2), ‘Minor’ deficiencies that though inconvenient or annoying, do not impede or delay mission accomplishment (e.g. missing light fixture or plug receptacle). Performance https://cmra.army.mil/ thresholds identified in the accompanying table indicate number of defects accepted before failing a critical task.
Performance Objective PWS Para Performance Threshold
SS#1: Prefabricated Buildings, Temporary Work Shed, Electrical System Erection and
Maintenance of Prefabricated
Buildings and other Facilities
1.4, 1.5 &1.6 One (1) major defect allowed (must be correctable)
Five (5) minor defects allowed (must be correctable)
SS#2: Maintenance and Repair 1.5.7 Three (3) defects allowed but none of them failure to respond in a timely manner
SS#3: Submittals 1.9.1. Two (2) late deliverables allowed
SECTION 3
GOVERNMENT FURNISHED PROPERTY AND SERVICES
3. GOVERNMENT FURNISHED PROPERTY AND SERVICES. Power and water will not be provided by the Government.
3.1. Security Forces and Fire Protection: Upon request for assistance, the following units will provide services on base as necessary:
(a) Base Security Forces Telephone 110
(b) Base Fire Department Telephone 119 phone number verified at exercise site
(c) Base Emergency Telephone 119
SECTION 4
APPENDICES
A. Site Plans and/or Details
Drawing No. Description
YS-16-69 T-01 Camp Itami
Base Camp
Title sheet
YS-16-69 S-01 CCF Site Layout Plan
YS-16-69 S-02 Plans of Bldg 205
YS-16-69 S-03 Plans of Prefab Bldg No.1 and Detail
YS-16-69 S-04 Plans of Prefab Bldg No.2
YS-16-69 S-05 Typ Section of Prefab Bldg
YS-16-69 S-06 CP Area Layout Plan
YS-16-69 S-07 Plans and Section
YS-16-69 S-08 Electrical Distribution Plan for “CCF” Area, 100V
YS-16-69 S-09 Electrical Distribution Plan for “CCF” Area, 120V
YS-16-69 S-10 Electrical Plan for Bldg No. 205 and Detail, 100V
YS-16-69 S-11 Electrical Plan for Bldg No. 205 and Details, 120V
YS-16-69 S-12 Electrical Plan for Bldg No. 205 and Details, 120V
YS-16-69 S-13 Electrical Plan for Bldg No. 205 and Details, 120V
YS-16-69 S-14 Electrical Plan for Bldg No. 205 and Detail, 120V
YS-16-69 S-15 Electrical Plan for Prefab Bldgs and Details, 100V
YS-16-69 S-16 Electrical Plan for Prefab Bldgs and Details, 100V
YS-16-69 S-17 Electrical Plan for Prefab Bldgs and Detail, 120V
YS-16-69 S-18 Electrical Plan for Prefab Bldgs and Detail, 120V
YS-16-69 S-19 Electrical Plan for Prefab Bldgs and Details, 120V
YS-16-69 S-20 Electrical Plan for Tech. Cont. Room and Details, 120V
YS-16-69 S-21 Electrical Feeder Plan for Bldg No. 205, 100V
YS-16-69 S-22 Electrical Feeder Plan for Bldg No. 205, 120V
YS-16-69 S-23 Electrical Feeder Plan for Prefab Bldgs 1st Floor, 100V
YS-16-69 S-24 Electrical Feeder Plan for Prefab Bldgs, 2nd Floor, 100V
YS-16-69 S-25 Electrical Feeder Plan for Prefab Bldgs 1st Floor, 120V
YS-16-69 S-26 Electrical Feeder Plan for Prefab Bldgs, 2nd Floor, 120V
YS-16-69 S-27 Electrical Distribution Plan for “CP” Area, 100V
YS-16-69 S-28 Electrical Distribution Plan for “CP” Area, 120V
YS-16-69 S-29 Electrical Plan for Tent, 100V and Details
YS-16-69 S-30 Electrical Plan for Tent, 100V and Details
YS-16-69 S-31 Electrical Plan for Tent, 120V and Details
YS-16-69 S-32 Electrical Plan for Tent, 120V and Details
YS-16-69 S-33 Electrical Plan for Tent, 120V and Details
YS-16-69 S-34 Electrical Plan for Tent, 120V and Details
YS-16-69 S-35 Electrical Plan for Access Check Point, 100V and Details
YS-16-69 S-36 Electrical Distribution Plan for “DFAC” Area, 100V and
120V
YS-16-69 S-37 Electrical Distribution Plan for Bldg No. 195 and Details
YS-16-69 S-38 Electrical Plans and Details