Appendix_B-1 _List_of_Maintenance_and_Inspection_-_20160208.pdf
PDF 306 KB Posted
- Attached to
- Inspection and Maintenance of Runoff Treatment Facility, Kawakami Ammunition Depot, Hiroshima, Japan
- Solicitation number
- FA5209-15-T-0102
About this file
Revised Appendix B-1
View the file
Other files
| File | Type | Posted |
|---|---|---|
| PWS_22_Feb_16_(Revised_B-1).pdf | ||
| 0003.pdf | ||
| Amendment_02.pdf | ||
| Amendment_01.pdf | ||
| Appendix_B-2 _Drawing_of_System.pdf | ||
| Copy_of_Gate_Pass_Request_Form_New.xlsx | XLSX spreadsheet | |
| Notice_to_Offeror.pdf | ||
| Copy_of_Appendix_B-1_List_of_Maintenance_and_Inspection_-_20150826.pdf | ||
| 15-T-0102.pdf | ||
| PWS_4_Sep_15.pdf | ||
| Goverment_Policy_Ltr_-_Lt_Col_Kapise.pdf |
Show all 11
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
FA5209-15-T-0102
Attachment 1
Appendix B-1 Runoff Water Treatment System
Revised 8 Feb 16
Maintenance and Inspection List (1/4) item apparatus name long-term periodic check years item number # check item 0.5 1 1.5 2 2.5 3
T-0 pump pit 1 removal of adhered substances O O O
2 dredge mud and sludge
3 leakage check O O
T-1 precipitation tank 1 removal of adhered substances O O O O O O
2 leakage check O O O O O O
3 dredge mud and sludge O
4 removal of schele O
5 check and tighten bolts O
6 check the mounted parts O
7 cleaning of the inclined pads O
8 cleaning of the vacuum pipes O
9 corrosion check O
T-2 sand bed 1 removal of sludge and cleaning O O
2 supplement of filtration material O O
3 leakage check O O O O O
4 exchange sand filter(1.8cubic meters) O
5 check and tighten bolts O O
6 check the mounting parts O O
7 cleaning of the vacuum pipes O O
8 corrosion check O O
9 cleaning of the collecting pipes O O
10 exchange of collecting nets O O
T-3 equalization tank 1 removal of adhered substances O O
2 leakage check O O O O O O
3 removal of sludge O
4 check control panel O O O O O O
5 dredge mud and sludge O
6 removal of schele O
7 check and tighten bolts O
8 check the mounted parts O
9 cleaning of the pipings O
10 corrosion check O
Appendix B-1 Runoff Water Treatment System
Maintenance and Inspection List (2/4) item apparatus name long-term periodic check years item number # check item 0.5 1 1.5 2 2.5 3
T-4 sand filter 1 record of the amount water/pressure O O O O O O
2 leakage check from the tower O O O O O O
3 leakage check from the piping O O O O O O
4 check automatic valves O O O O O O
5 adjustment of the flow O O O O O O
6 cleaning of the flowmeter O O O O O O
7 check of the pressure gauges O O O O
8 exchange sand filter(0.6cubic meters) O
9 exchange pressure gauges O
10 cleaning of the medicine injection point O O O O
11 corrosion check O
T-5 adsorption tower 1 record of the amount water/pressure O O O O O O
2 leakage check from the tower O O O O O O
3 leakage check from the piping O O O O O O
4 check automatic valves O O O O O O
5 exchange chelating resin(0.8cubic meters) O
6 exchange of the pressure gauges O
T-6 back wash tank 1 removal of adhered substances O O O
2 leakage check O O O O O O
3 cleaning of the flowmeter O O O O O O
4 dredge mud and sludge O
5 removal of schele O
6 check and tighten bolts O O O O
7 cleaning of the pipings O
T-7 PAC tank 1 leakage check from the piping O O O O O O
2 leakage check from the tower O O O O O O
3 confirmation of the liquid level O O O O O O
4 supplement of liquid O O O
5 quality check of PAC O O O
6 cleaning of the tank O O O
7 check and tighten bolts O O O
Appendix B-1 Runoff Water Treatment System
Maintenance and Inspection List (3/4) item apparatus name long-term periodic check years item number # check item 0.5 1 1.5 2 2.5 3
P-1 Raw water pump 1 operation check O O O O O O
2 check water volume and pressure O O O O O O
3 leakage check O O O O O O
4 vibration check O O O O O O
5 measurement of the current O O O O O O
6 check the noise O O O O O O
7 check and tighten bolts O O O
8 test of the insulation resistence O O O
P-2 Filter pump 1 operation check O O O O O O
P-4 back wash tank 2 check water volume and pressure O O O O O O
3 leakage check O O O O O O
4 vibration check O O O O O O
5 measurement of the current O O O O O O
6 check the noise O O O O O O
7 check and tighten bolts O O O
8 test of the insulation resistence O O O
P-3 PAC pump 1 operation check O O O O O O
2 check water volume O O O O O O
3 leakage check from connection point O O O O O O
4 leakage check from injection point O O O O O O
5 wear check of the diaphragm O O O O O O
6 wear check of the check ball O O O
7 check and tighten bolts O O O
H-1 Heater 1 check the heater O O O
2 test of the insulation resistence O O O
Appendix B-1 Runoff Water Treatment System
Maintenance and Inspection List (4/4) item apparatus name long-term periodic check years item number # check item 0.5 1 1.5 2 2.5 3
CP-1 control panel 1 check operation panel O O O O O O
2 check record of alarm and repair O O O O O O
3 check the light bulbs in the panel O O O
4 check and tighten bolts for terminal O O O
5 check the breakers O O O analysis of water quality 1 analysis pH, SS and Pb of raw water O O O O O and discharge