Exhibit A

Exhibit A
ROADS/PAVEMENTS & MISC. CIVIL WORK IDIQ CONTRACTDate: 14 Jul 23
MISAWA AB, JAPAN
REQUEST FOR PROPOSAL No.FA520523R0007
CONTARCT No.

Offeror (Print Name, Title and Signature) Date Corporate Seal (Han)

Company Name and Address

CategoryELIN ADescriptionEstimated
QuantityUnit of IssueUnit Price
¥Estimated Amount
Survey and Test001Quantity Survey of Current Condition for Pavement and Construction Area, One Section per extension 10 m200LOT
002Core Drilling and Sampling of AC or Concrete Pavement of Roads, Parking Lots, and Other Surfaces20EA
003Test Digging of AC Pavement, not to exceed 1m x 1m x 1m includes temporary pavement restoration20EA
General004Construct Formwork for concrete work600SM
Construction005Construct Steel Reinforcement Bar2MTON
and006Frost Inhibition Course (RC-40)50CM
Other Work007Leveling Basis Crushed stone (RC-40, Average thickness 30mm)60CM
008Construct Basis Crushed Stone (RC-40)10CM
009Place Concrete (21-8-25)50CM
010Place Concrete (24-8-25)20CM
011Placing and Removing Steel Plate, Size 1.5m x 3.0m1,000EA/DAY
012Transportation of Removed Concrete, AC and Concrete products from Construction Site to Stock Yard/on Base900CM
013Transportation of Removed Miscellaneous Material from Construction Site to Stock Yard/on Base400CM
014Traffic Regulator (Flag Man)600MAN/DAY
Asphalt015Construct Subbase Course (RC-40)200CM
Paving Work016Leveling Base/Subbase Course8,000SM
017Leveling Base Course (M-25, Average thickness 30mm)300CM
018Construct Base Course (M-25)100CM
019Leveling AC Pavement (Recycled AC No.2, Average thickness 40mm)100MTON
02050mm Thick Recycled AC Intermediate Course (AC No.2)6,000SM
021Construct Recycled AC Wearing Course (AC No.5)400MTON
022Construct AC Surface by Modified Asphalt (AC No.5)500MTON
023Prime Coat (PK-3)8,000SM
024Tack Coat (PK-4)2,000SM
025Tack Coat (Modified PK-4)4,000SM
026AC Wearing Course (Labor)40MTON
027Base Stabilization for Pavement, Mix 150mm Thick5,000SM
Geotextile Work028Install Geotextile600SM
Sidewalk,029Base Course (RC-40, T=100mm)100SM
Curbs and030Base Course Restoration (RC-40, T=100mm)180SM
Gutters Work031Frost Inhibition Course (RC-40, T=250mm)20CM
032Frost Inhibition Course Restoration (RC-40, T=250mm)20CM
033Base Course Restoration for Road (M-25)30CM
034Leveling Base Course (RC-40, Average thickness 30mm)60CM
035Place Concrete (24-8-25) for Concrete Sidewalks200SM
036Place Concrete (24-8-25) for Concrete Curbs200LM
037Place Concrete (24-8-25) for Concrete Curbs & Gutters200CM
038Install Joint Filler60SM
039Install Sealant (10mm x 5mm)600LM
040Contraction Joint Cutter300LM
041Install Precast Type A Block200LM
Pavement042Install Reflective Marking, White (W=15cm)2,000LM
Markings,043Alphanumeric Concrete Curb Marking20EA
Traffic Safety044Install Handicap Symbol Marking, White2EA
Work045Relocate Traffic Sign & Post4EA
Earth Work,046Road Excavation800CM
Sodding,047Earthwork (Digging and Grading)200CM
Planting Work048Excavation for Underground Utility100CM
049Transportation of Excavated Soil to Stock Yard1,000CM
050Backfill Excavated Soil150CM
051Backfill Excavated Material (For Underground Utility)80CM
052Backfill New Soil200CM
053Place New Top Soil, 100mm Thick200CM
054Place Sod (Noshiba)2,000SM
055Removal and reinstallation of Sod100SM
Sanitary Sewer,056Install 200mm VU Rib Pipe10LM
Drainage Work057Install 300mm VU Rib Pipe10LM
058Install New Manhole Frame and Cover(T-25)4EA
059Raise/Lower existing Manhole Frame and Cover5EA
060Install New Concrete Frame and Grating Cover (T-20) of Gutter Inlet20EA
061Install New Gutter Inlet with Pre-cast Concrete Structures, Inlet Height 1.5m5EA
062Raise/Lower existing Concrete Frame and Grating Cover of Gutter Inlet10EA
063Install New Frame and Grating Cover (T-25) for Catch Basin, 900 mm square3EA
Water Line Wrok064Replace existing Gate Valve Box3EA
Removal and065Saw Cutting of Existing AC Pavement, less than 15cm3,000LM
Disposal Work066Saw Cutting of Existing AC Pavement, 15cm or more and less than 30cm600LM
067Saw Cutting of Existing Concrete Pavement, less than 15cm200LM
068Cold Milling of AC Pavement, less than 6cm1,500SM
069Cold Milling of AC Pavement, 6cm or more and less than 12cm500SM
070Removal of AC Pavement, less than 10cm8,000SM
071Removal of AC Pavement, 10cm or more and less than 20cm800SM
072Removal of Concrete Pipe20LM
073Removal of Existing Catch Basin4CM
074Removal of Existing Concrete Curbs800LM
075Removal of Existing Concrete Curbs and Gutters1,000LM
076Removal of Existing Concrete Sidewalks3,000SM
077Removal of Existing Levering Concrete20CM
078Removal of Reinforced Concrete by Labor5CM
079Removal of Existing Manhole Frame and Cover4EA
080Removal of Existing Frame and Grating Drainage Product20EA
081Removal of Precast Concrete Curb Block500LM
082Removal of Existing Tree and Stump, Circumference of tree less than 20cm10EA
083Removal of Existing Tree and Stump, Circumference of tree 21~30cm5EA
084Removal of PVC Pipe4LM
085Hauling and Disposal of Extra Soils/Gravels to Off Base700CM
086Hauling and Disposal of Asphalt Concrete to Off Base1,500MTON
087Hauling and Disposal of Cold Milling AC to Off Base1,250MTON
088Hauling and Disposal of Plain Concrete to Off Base600MTON
089Hauling and Disposal of Reinforced Concrete to Off Base100MTON
090Hauling and Disposal of Precast Concrete Product to Off Base300MTON
091Hauling and Disposal of Plastics to Off Base5MTON
092Hauling and Disposal of Trees and stump to Off Base40MTON
093Removal of AC Pavement with Soil Stabilizer2,000SM
General094Leveling Basis Crushed stone (RC-40, Average thickness 30mm)30CM
Construction095Construct Basis Crushed stone (RC-40)30CM
and Other Work096Place Concrete (21-8-25)30CM
for MFH Carport Area097Transportation of Removed Concrete, AC and Concrete products from Construction Site to Stock Yard/on Base500CM
098Transportation of Removed Miscellaneous Material from Construction Site to Stock Yard/on Base120CM
Asphalt099Construct Subbase Course (RC-40)120CM
Paving Work100Leveling Base/Subbase Course1,800SM
for MFH101Leveling Base Course (M-25, Average thickness 30mm)100CM
Carport Area102Construct Base Course (M-25)150CM
10350mm Thick Recycled AC Intermediate Course (AC No.2)1,800SM
104Construct Recycled AC Wearing Course (AC No.5)200MTON
105Prime Coat (PK-3)1,800SM
106Tack Coat (PK-4)1,800SM
107Tack Coat (Modified PK-4)1,500SM
108Install Reflective Marking, White (W=15cm)500LM
Sidewalk,109Base Course (RC-40, T=100mm)100SM
Curbs and110Base Course Restoration (RC-40, T=100mm)100SM
Gutters Work111Frost Inhibition Course (RC-40, T=250mm)20CM
for MFH112Frost Inhibition Course Restoration (RC-40, T=250mm)20CM
Carport Area113Base Course Restoration for Road (M-25)20CM
114Leveling Base Course (RC-40, Average thickness 30mm)20CM
115Place Concrete (24-8-25) for Concrete Sidewalks1,000SM
116Place Concrete (24-8-25) for Concrete Curbs10LM
117Place Concrete (24-8-25) for Concrete Curbs & Gutters50CM
118Install Precast Type A Block100LM
Earth Work119Excavation for Parking Lot100CM
for MFH120Earthwork (Digging and Grading)100CM
Carport Area121Transportation of Excavated Soil to Stock Yard300CM
122Backfill Excavated Soil50CM
123Backfill New Soil50CM
Removal and124Removal of AC Pavement, less than 10cm2,000SM
Disposal Work125Removal of Existing Concrete Curbs120LM
for MFH126Removal of Existing Concrete Curbs and Gutters50LM
Carport Area127Removal of Existing Concrete Sidewalks1,000SM
128Removal of Existing Leveling Concrete10CM
129Removal of Precast Concrete Curb Block300LM
TOTAL ESTIMATED AMOUNT OF ELINs (Yen)0

&10 Exhibit A RFP No. FA520523R0007 &10page &P of &N &10Revised per Addendum No. 1

Exhibit B

Exhibit B
ROADS/PAVEMENTS & MISC. CIVIL WORK IDIQ CONTRACTDate: 14 Jul 23
MISAWA AB, JAPAN
REQUEST FOR PROPOSAL No.FA520523R0007
CONTARCT No.

Offeror (Print Name, Title and Signature) Date Corporate Seal (Han)

Company Name and Address

CategoryELIN BDescriptionEstimated
QuantityUnit of IssueUnit Price
¥Estimated Amount
Survey and Test001Quantity Survey of Current Condition for Pavement and Construction Area, One Section per extension 10 m200LOT
002Core Drilling and Sampling of AC or Concrete Pavement of Roads, Parking Lots, and Other Surfaces20EA
003Test Digging of AC Pavement, not to exceed 1m x 1m x 1m includes temporary pavement restoration20EA
General004Construct Formwork for concrete work600SM
Construction005Construct Steel Reinforcement Bar2MTON
and006Frost Inhibition Course (RC-40)50CM
Other Work007Leveling Basis Crushed stone (RC-40, Average thickness 30mm)60CM
008Construct Basis Crushed Stone (RC-40)10CM
009Place Concrete (21-8-25)50CM
010Place Concrete (24-8-25)20CM
011Placing and Removing Steel Plate, Size 1.5m x 3.0m1,000EA/DAY
012Transportation of Removed Concrete, AC and Concrete products from Construction Site to Stock Yard/on Base900CM
013Transportation of Removed Miscellaneous Material from Construction Site to Stock Yard/on Base400CM
014Traffic Regulator (Flag Man)600MAN/DAY
Asphalt015Construct Subbase Course (RC-40)200CM
Paving Work016Leveling Base/Subbase Course8,000SM
017Leveling Base Course (M-25, Average thickness 30mm)300CM
018Construct Base Course (M-25)100CM
019Leveling AC Pavement (Recycled AC No.2, Average thickness 40mm)100MTON
02050mm Thick Recycled AC Intermediate Course (AC No.2)6,000SM
021Construct Recycled AC Wearing Course (AC No.5)400MTON
022Construct AC Surface by Modified Asphalt (AC No.5)500MTON
023Prime Coat (PK-3)8,000SM
024Tack Coat (PK-4)2,000SM
025Tack Coat (Modified PK-4)4,000SM
026AC Wearing Course (Labor)40MTON
027Base Stabilization for Pavement, Mix 150mm Thick5,000SM
Geotextile Work028Install Geotextile600SM
Sidewalk,029Base Course (RC-40, T=100mm)100SM
Curbs and030Base Course Restoration (RC-40, T=100mm)180SM
Gutters Work031Frost Inhibition Course (RC-40, T=250mm)20CM
032Frost Inhibition Course Restoration (RC-40, T=250mm)20CM
033Base Course Restoration for Road (M-25)30CM
034Leveling Base Course (RC-40, Average thickness 30mm)60CM
035Place Concrete (24-8-25) for Concrete Sidewalks200SM
036Place Concrete (24-8-25) for Concrete Curbs200LM
037Place Concrete (24-8-25) for Concrete Curbs & Gutters200CM
038Install Joint Filler60SM
039Install Sealant (10mm x 5mm)600LM
040Contraction Joint Cutter300LM
041Install Precast Type A Block200LM
Pavement042Install Reflective Marking, White (W=15cm)2,000LM
Markings,043Alphanumeric Concrete Curb Marking20EA
Traffic Safety044Install Handicap Symbol Marking, White2EA
Work045Relocate Traffic Sign & Post4EA
Earth Work,046Road Excavation800CM
Sodding,047Earthwork (Digging and Grading)200CM
Planting Work048Excavation for Underground Utility100CM
049Transportation of Excavated Soil to Stock Yard1,000CM
050Backfill Excavated Soil150CM
051Backfill Excavated Material (For Underground Utility)80CM
052Backfill New Soil200CM
053Place New Top Soil, 100mm Thick200CM
054Place Sod (Noshiba)2,000SM
055Removal and reinstallation of Sod100SM
Sanitary Sewer,056Install 200mm VU Rib Pipe10LM
Drainage Work057Install 300mm VU Rib Pipe10LM
058Install New Manhole Frame and Cover(T-25)4EA
059Raise/Lower existing Manhole Frame and Cover5EA
060Install New Concrete Frame and Grating Cover (T-20) of Gutter Inlet20EA
061Install New Gutter Inlet with Pre-cast Concrete Structures, Inlet Height 1.5m5EA
062Raise/Lower existing Concrete Frame and Grating Cover of Gutter Inlet10EA
063Install New Frame and Grating Cover (T-25) for Catch Basin, 900 mm square3EA
Water Line Wrok064Replace existing Gate Valve Box3EA
Removal and065Saw Cutting of Existing AC Pavement, less than 15cm3,000LM
Disposal Work066Saw Cutting of Existing AC Pavement, 15cm or more and less than 30cm600LM
067Saw Cutting of Existing Concrete Pavement, less than 15cm200LM
068Cold Milling of AC Pavement, less than 6cm1,500SM
069Cold Milling of AC Pavement, 6cm or more and less than 12cm500SM
070Removal of AC Pavement, less than 10cm8,000SM
071Removal of AC Pavement, 10cm or more and less than 20cm800SM
072Removal of Concrete Pipe20LM
073Removal of Existing Catch Basin4CM
074Removal of Existing Concrete Curbs800LM
075Removal of Existing Concrete Curbs and Gutters1,000LM
076Removal of Existing Concrete Sidewalks3,000SM
077Removal of Existing Levering Concrete20CM
078Removal of Reinforced Concrete by Labor5CM
079Removal of Existing Manhole Frame and Cover4EA
080Removal of Existing Frame and Grating Drainage Product20EA
081Removal of Precast Concrete Curb Block500LM
082Removal of Existing Tree and Stump, Circumference of tree less than 20cm10EA
083Removal of Existing Tree and Stump, Circumference of tree 21~30cm5EA
084Removal of PVC Pipe4LM
085Hauling and Disposal of Extra Soils/Gravels to Off Base700CM
086Hauling and Disposal of Asphalt Concrete to Off Base1,500MTON
087Hauling and Disposal of Cold Milling AC to Off Base1,250MTON
088Hauling and Disposal of Plain Concrete to Off Base600MTON
089Hauling and Disposal of Reinforced Concrete to Off Base100MTON
090Hauling and Disposal of Precast Concrete Product to Off Base300MTON
091Hauling and Disposal of Plastics to Off Base5MTON
092Hauling and Disposal of Trees and stump to Off Base40MTON
093Removal of AC Pavement with Soil Stabilizer2,000SM
General094Leveling Basis Crushed stone (RC-40, Average thickness 30mm)30CM
Construction095Construct Basis Crushed stone (RC-40)30CM
and Other Work096Place Concrete (21-8-25)30CM
for MFH Carport Area097Transportation of Removed Concrete, AC and Concrete products from Construction Site to Stock Yard/on Base500CM
098Transportation of Removed Miscellaneous Material from Construction Site to Stock Yard/on Base120CM
Asphalt099Construct Subbase Course (RC-40)120CM
Paving Work100Leveling Base/Subbase Course1,800SM
for MFH101Leveling Base Course (M-25, Average thickness 30mm)100CM
Carport Area102Construct Base Course (M-25)150CM
10350mm Thick Recycled AC Intermediate Course (AC No.2)1,800SM
104Construct Recycled AC Wearing Course (AC No.5)200MTON
105Prime Coat (PK-3)1,800SM
106Tack Coat (PK-4)1,800SM
107Tack Coat (Modified PK-4)1,500SM
108Install Reflective Marking, White (W=15cm)500LM
Sidewalk,109Base Course (RC-40, T=100mm)100SM
Curbs and110Base Course Restoration (RC-40, T=100mm)100SM
Gutters Work111Frost Inhibition Course (RC-40, T=250mm)20CM
for MFH112Frost Inhibition Course Restoration (RC-40, T=250mm)20CM
Carport Area113Base Course Restoration for Road (M-25)20CM
114Leveling Base Course (RC-40, Average thickness 30mm)20CM
115Place Concrete (24-8-25) for Concrete Sidewalks1,000SM
116Place Concrete (24-8-25) for Concrete Curbs10LM
117Place Concrete (24-8-25) for Concrete Curbs & Gutters50CM
118Install Precast Type A Block100LM
Earth Work119Excavation for Parking Lot100CM
for MFH120Earthwork (Digging and Grading)100CM
Carport Area121Transportation of Excavated Soil to Stock Yard300CM
122Backfill Excavated Soil50CM
123Backfill New Soil50CM
Removal and124Removal of AC Pavement, less than 10cm2,000SM
Disposal Work125Removal of Existing Concrete Curbs120LM
for MFH126Removal of Existing Concrete Curbs and Gutters50LM
Carport Area127Removal of Existing Concrete Sidewalks1,000SM
128Removal of Existing Leveling Concrete10CM
129Removal of Precast Concrete Curb Block300LM
TOTAL ESTIMATED AMOUNT OF ELINs (Yen)0

&10Exhibit B RFP No. FA520523R0007 &10 page &P of &N &10Revised Per Addendum No. 1

Exhibit C

Exhibit C
ROADS/PAVEMENTS & MISC. CIVIL WORK IDIQ CONTRACT
MISAWA AB, JAPANDate: 14 Jul 23
REQUEST FOR PROPOSAL No.FA520523R0007
CONTARCT No.

Offeror (Print Name, Title and Signature) Date Corporate Seal (Han)

Company Name and Address

CategoryELIN CDescriptionEstimated
QuantityUnit of IssueUnit Price
¥Estimated Amount
Survey and Test001Quantity Survey of Current Condition for Pavement and Construction Area, One Section per extension 10 m200LOT
002Core Drilling and Sampling of AC or Concrete Pavement of Roads, Parking Lots, and Other Surfaces20EA
003Test Digging of AC Pavement, not to exceed 1m x 1m x 1m includes temporary pavement restoration20EA
General004Construct Formwork for concrete work600SM
Construction005Construct Steel Reinforcement Bar2MTON
and006Frost Inhibition Course (RC-40)50CM
Other Work007Leveling Basis Crushed stone (RC-40, Average thickness 30mm)60CM
008Construct Basis Crushed Stone (RC-40)10CM
009Place Concrete (21-8-25)50CM
010Place Concrete (24-8-25)20CM
011Placing and Removing Steel Plate, Size 1.5m x 3.0m1,000EA/DAY
012Transportation of Removed Concrete, AC and Concrete products from Construction Site to Stock Yard/on Base900CM
013Transportation of Removed Miscellaneous Material from Construction Site to Stock Yard/on Base400CM
014Traffic Regulator (Flag Man)600MAN/DAY
Asphalt015Construct Subbase Course (RC-40)200CM
Paving Work016Leveling Base/Subbase Course8,000SM
017Leveling Base Course (M-25, Average thickness 30mm)300CM
018Construct Base Course (M-25)100CM
019Leveling AC Pavement (Recycled AC No.2, Average thickness 40mm)100MTON
02050mm Thick Recycled AC Intermediate Course (AC No.2)6,000SM
021Construct Recycled AC Wearing Course (AC No.5)400MTON
022Construct AC Surface by Modified Asphalt (AC No.5)500MTON
023Prime Coat (PK-3)8,000SM
024Tack Coat (PK-4)2,000SM
025Tack Coat (Modified PK-4)4,000SM
026AC Wearing Course (Labor)40MTON
027Base Stabilization for Pavement, Mix 150mm Thick5,000SM
Geotextile Work028Install Geotextile600SM
Sidewalk,029Base Course (RC-40, T=100mm)100SM
Curbs and030Base Course Restoration (RC-40, T=100mm)180SM
Gutters Work031Frost Inhibition Course (RC-40, T=250mm)20CM
032Frost Inhibition Course Restoration (RC-40, T=250mm)20CM
033Base Course Restoration for Road (M-25)30CM
034Leveling Base Course (RC-40, Average thickness 30mm)60CM
035Place Concrete (24-8-25) for Concrete Sidewalks200SM
036Place Concrete (24-8-25) for Concrete Curbs200LM
037Place Concrete (24-8-25) for Concrete Curbs & Gutters200CM
038Install Joint Filler60SM
039Install Sealant (10mm x 5mm)600LM
040Contraction Joint Cutter300LM
041Install Precast Type A Block200LM
Pavement042Install Reflective Marking, White (W=15cm)2,000LM
Markings,043Alphanumeric Concrete Curb Marking20EA
Traffic Safety044Install Handicap Symbol Marking, White2EA
Work045Relocate Traffic Sign & Post4EA
Earth Work,046Road Excavation800CM
Sodding,047Earthwork (Digging and Grading)200CM
Planting Work048Excavation for Underground Utility100CM
049Transportation of Excavated Soil to Stock Yard1,000CM
050Backfill Excavated Soil150CM
051Backfill Excavated Material (For Underground Utility)80CM
052Backfill New Soil200CM
053Place New Top Soil, 100mm Thick200CM
054Place Sod (Noshiba)2,000SM
055Removal and reinstallation of Sod100SM
Sanitary Sewer,056Install 200mm VU Rib Pipe10LM
Drainage Work057Install 300mm VU Rib Pipe10LM
058Install New Manhole Frame and Cover(T-25)4EA
059Raise/Lower existing Manhole Frame and Cover5EA
060Install New Concrete Frame and Grating Cover (T-20) of Gutter Inlet20EA
061Install New Gutter Inlet with Pre-cast Concrete Structures, Inlet Height 1.5m5EA
062Raise/Lower existing Concrete Frame and Grating Cover of Gutter Inlet10EA
063Install New Frame and Grating Cover (T-25) for Catch Basin, 900 mm square3EA
Water Line Wrok064Replace existing Gate Valve Box3EA
Removal and065Saw Cutting of Existing AC Pavement, less than 15cm3,000LM
Disposal Work066Saw Cutting of Existing AC Pavement, 15cm or more and less than 30cm600LM
067Saw Cutting of Existing Concrete Pavement, less than 15cm200LM
068Cold Milling of AC Pavement, less than 6cm1,500SM
069Cold Milling of AC Pavement, 6cm or more and less than 12cm500SM
070Removal of AC Pavement, less than 10cm8,000SM
071Removal of AC Pavement, 10cm or more and less than 20cm800SM
072Removal of Concrete Pipe20LM
073Removal of Existing Catch Basin4CM
074Removal of Existing Concrete Curbs800LM
075Removal of Existing Concrete Curbs and Gutters1,000LM
076Removal of Existing Concrete Sidewalks3,000SM
077Removal of Existing Levering Concrete20CM
078Removal of Reinforced Concrete by Labor5CM
079Removal of Existing Manhole Frame and Cover4EA
080Removal of Existing Frame and Grating Drainage Product20EA
081Removal of Precast Concrete Curb Block500LM
082Removal of Existing Tree and Stump, Circumference of tree less than 20cm10EA
083Removal of Existing Tree and Stump, Circumference of tree 21~30cm5EA
084Removal of PVC Pipe4LM
085Hauling and Disposal of Extra Soils/Gravels to Off Base700CM
086Hauling and Disposal of Asphalt Concrete to Off Base1,500MTON
087Hauling and Disposal of Cold Milling AC to Off Base1,250MTON
088Hauling and Disposal of Plain Concrete to Off Base600MTON
089Hauling and Disposal of Reinforced Concrete to Off Base100MTON
090Hauling and Disposal of Precast Concrete Product to Off Base300MTON
091Hauling and Disposal of Plastics to Off Base5MTON
092Hauling and Disposal of Trees and stump to Off Base40MTON
093Removal of AC Pavement with Soil Stabilizer2,000SM
General094Leveling Basis Crushed stone (RC-40, Average thickness 30mm)30CM
Construction095Construct Basis Crushed stone (RC-40)30CM
and Other Work096Place Concrete (21-8-25)30CM
for MFH Carport Area097Transportation of Removed Concrete, AC and Concrete products from Construction Site to Stock Yard/on Base500CM
098Transportation of Removed Miscellaneous Material from Construction Site to Stock Yard/on Base120CM
Asphalt099Construct Subbase Course (RC-40)120CM
Paving Work100Leveling Base/Subbase Course1,800SM
for MFH101Leveling Base Course (M-25, Average thickness 30mm)100CM
Carport Area102Construct Base Course (M-25)150CM
10350mm Thick Recycled AC Intermediate Course (AC No.2)1,800SM
104Construct Recycled AC Wearing Course (AC No.5)200MTON
105Prime Coat (PK-3)1,800SM
106Tack Coat (PK-4)1,800SM
107Tack Coat (Modified PK-4)1,500SM
108Install Reflective Marking, White (W=15cm)500LM
Sidewalk,109Base Course (RC-40, T=100mm)100SM
Curbs and110Base Course Restoration (RC-40, T=100mm)100SM
Gutters Work111Frost Inhibition Course (RC-40, T=250mm)20CM
for MFH112Frost Inhibition Course Restoration (RC-40, T=250mm)20CM
Carport Area113Base Course Restoration for Road (M-25)20CM
114Leveling Base Course (RC-40, Average thickness 30mm)20CM
115Place Concrete (24-8-25) for Concrete Sidewalks1,000SM
116Place Concrete (24-8-25) for Concrete Curbs10LM
117Place Concrete (24-8-25) for Concrete Curbs & Gutters50CM
118Install Precast Type A Block100LM
Earth Work119Excavation for Parking Lot100CM
for MFH120Earthwork (Digging and Grading)100CM
Carport Area121Transportation of Excavated Soil to Stock Yard300CM
122Backfill Excavated Soil50CM
123Backfill New Soil50CM
Removal and124Removal of AC Pavement, less than 10cm2,000SM
Disposal Work125Removal of Existing Concrete Curbs120LM
for MFH126Removal of Existing Concrete Curbs and Gutters50LM
Carport Area127Removal of Existing Concrete Sidewalks1,000SM
128Removal of Existing Leveling Concrete10CM
129Removal of Precast Concrete Curb Block300LM
TOTAL ESTIMATED AMOUNT OF ELINs (Yen)0

&10Exhibit C RFP No. FA520523R0007 &10 page &P of &N &10Revised Per Addendum No. 1