Synopsis_Questions.docx

DOCX document 12 KB Posted

Attached to
Renovate Nose Dock 1 A&E Federal contract opportunity
Solicitation number
FA5004-AE-FTQW17-1009
Issued by
Department of the Air Force Pacific Air Forces

About this file

Responses to Questions submitted

View the file

Other files for this federal contract opportunity

Other files attached to Renovate Nose Dock 1 A&E, newest first.
File Type Posted
Synopsis_Attach_3_-_Statement_of_Work.pdf PDF
Attachment_5_-_PPQ_Nose_Dock_1_Reno.pdf PDF
Synopsis_Attach_2_-_Evaluation_Factors_ND1_Reno.pdf PDF
Synopsis_Attach_1_-_Instructions_to_Offerors.pdf PDF
Attachment_4_-_SF_330.pdf PDF

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Questions for Project FTQW 17-1009 Nose Dock 1 Renovation

Q1. Could you please clarify whether this solicitation is a small business set-side with a size standard of $15M?

A1. The Nose Dock 1 project is being solicited on an unrestricted basis (NOT a small business set aside). The size standard for a small business is $15M; however, this is open to any business to submit a qualification package.

Q2. The synopsis on FBO and the synopsis in Attachment 2 (page 2, a.1 and a.2) state different disciplines to be included in the proposal. Which should be go by?

A2. The synopsis in Attachment 2 contains the correct disciplines. The FBO Synopsis will be updated with the addition of the Question & Answer attachment.

Q3. Does the industrial hygienist need to be a certified industrial hygienist (CIH)?

A3. Yes - the industrial hygienist should be certified - a CIH Q4. Could you please clarify whether this solicitation is a small business set-side with a size standard of $15M?

A4. The Nose Dock 1 project is being solicited on an unrestricted basis (NOT a small business set aside). The size standard for a small business is $15M; however, this is open to any business to submit a qualification package.

Q5. Is a completed project one where design is complete or construction of the design is complete?

A5. We are looking for projects that have been completed through construction.