FA5004-17-Q-C002-0002.pdf

PDF 97 KB Posted

Attached to
FTQW 17-1011 Replace Coal Feeders, Boiler #6 Federal contract opportunity
Solicitation number
FA5004-17-Q-C002
Issued by
Department of the Air Force Pacific Air Forces

About this file

FA5004-17-Q-C002-0002

View the file

Other files for this federal contract opportunity

Other files attached to FTQW 17-1011 Replace Coal Feeders, Boiler #6, newest first.
File Type Posted
JA-2_Specifications.pdf PDF
Site_Visit_Sign_In_Sheet.pdf PDF
FA5004-17-Q-C002-0001.pdf PDF
JA-3_Wage_Determination.pdf PDF
JA-1_Other_Contract_Requirements.pdf PDF
JA-4_AF_Form_66.pdf PDF
JA-2_Specifications.pdf PDF
FA5004-17-Q-C002.docx.pdf PDF

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

F1U3C57128A001 FTQW 17-1011

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15A. NAME AND TITLE OF SIGNER (Type or print)

30-105-04EXCEPTION TO SF 30

APPROVED BY OIRM 11-84

STANDARD FORM 30 (Rev. 10-83)

Prescribed by GSA

FAR (48 CFR) 53.243

The purpose of this amendment is to extend the period of performance of the contract from 30 days to 45 days to allow additional time for pre-construction and post-construction submittals. How ever, the period of performance for actual construction (installation) remains limited to 30 days.

1. CONTRACT ID CODE PAGE OF PAGES

J 1 3

16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)

16C. DATE SIGNED

BY 27-Jun-2017

16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR

(Signature of Contracting Officer)(Signature of person authorized to sign)

8. NAME AND ADDRESS OF CONTRACTOR (No., Street, County, State and Zip Code) X FA500417QC002

X 9B. DATED (SEE ITEM 11)

16-Jun-2017

10B. DATED (SEE ITEM 13)

9A. AMENDMENT OF SOLICITATION NO.

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer is extended, X is not extended.

Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:

(a) By completing Items 8 and 15, and returning 1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;

or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE

RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN

REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

12. ACCOUNTING AND APPROPRIATION DATA (If required)

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.

IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE

CONTRACT ORDER NO. IN ITEM 10A.

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority)

E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

10A. MOD. OF CONTRACT/ORDER NO.

2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO.(If applicable)

6. ISSUED BY

3. EFFECTIVE DATE

27-Jun-2017

CODE

354 CONTRACTING SQUADRON ISSUING OFFICE

2310 CENTRAL AVE, BLDG 2258

LGCA - CONSTRUCTION

EIELSON AFB AK 99702-1801

FA5004 7. ADMINISTERED BY (If other than item 6)

4. REQUISITION/PURCHASE REQ. NO.

CODE

See Item 6

FACILITY CODECODE

EMAIL:TEL:

FA500417QC002

SECTION SF 30 BLOCK 14 CONTINUATION PAGE

SUMMARY OF CHANGES

SECTION B - SUPPLIES OR SERVICES AND PRICES

CLIN 0001

The CLIN extended description has changed from:

Provide all labor, material, equipment, supervision, work and facilities necessary to complete project Replace Coal

Feeders, Boiler #6 at Eielson’s Central Heat & Power Plant, in accordance with the drawings and specifications.

To:

Provide all labor, material, equipment, supervision, work and facilities necessary to complete project Replace Coal

Feeders, Boiler #6 at Eielson’s Central Heat & Power Plant, in accordance with the drawings and specifications.

Total construction time for installation of the coal feeders is limited to 30 days.

SECTION F - DELIVERIES OR PERFORMANCE

The following Delivery Schedule item for CLIN 0001 has been changed from:

DELIVERY DATE QUANTITY SHIP TO ADDRESS DODAAC /

CAGE

30 dys. ANP 1 354 CES/CECC - F1U3C7

CARL HEIDEL

2310 CENTRAL AVE SUITE 3

EIELSON AFB AK 99702-2299

907 377-1146

FOB: Destination

F1U3C7

To:

DELIVERY DATE QUANTITY SHIP TO ADDRESS DODAAC /

CAGE

45 dys. ANP 1 354 CES/CECC - F1U3C7

CARL HEIDEL

2310 CENTRAL AVE SUITE 3

EIELSON AFB AK 99702-2299

907 377-1146

FOB: Destination

F1U3C7

SECTION J - LIST OF DOCUMENTS, EXHIBITS AND OTHER ATTACHMENTS

FA500417QC002

The Table of Contents has changed from:

Exhibit/Attachment Table of Contents

DOCUMENT TYPE DESCRIPTION PAGES DATE

Attachment 1 JA-1 Other Contract

Requirements

1 15-JUN-2017

Attachment 2 JA-2 Specifications 145 31-MAY-2017

Attachment 3 JA-3 Wage Determination 15 15-JUN-2017

Attachment 4 JA-4 AF Form 66 2 15-JUN-2017 to:

Exhibit/Attachment Table of Contents

DOCUMENT TYPE DESCRIPTION PAGES DATE

Attachment 1 JA-1 Other Contract

Requirements

1 15-JUN-2017

Attachment 2 JA-2 Specifications 145 27-JUN-2017

Attachment 3 JA-3 Wage Determination 15 15-JUN-2017

Attachment 4 JA-4 AF Form 66 2 15-JUN-2017

(End of Summary of Changes)

File details come from the government source that posted it. Updated .